System Heads Off Interagency Construction Coordination Conflicts

Text size: A A

The annual marathon in Baltimore is a tricky affair to coordinate among the city’s agencies, especially amid a full spate of construction and infrastructure projects. Conflicts between new construction and the race route are a key challenge for officials to manage. Enter Envista, a web-accessible infrastructure coordination software system that Baltimore’s chief of design and construction calls a game changer.

Envista displays integrated construction scheduling data from public and private utilites, municipalities and highway agencies on an online map to prevent conflicts and synch operations.
Image: Tiop Courtesy of Envista
Envista displays integrated construction scheduling data from public and private utilites, municipalities and highway agencies on an online map to prevent conflicts and synch operations.
----- Advertising -----

“Last year, we coordinated the Baltimore Marathon on Envista,” says Margaret Martin, chief of design and construction for the city’s department of general services. “This was the first year we didn’t have a complaint.”

The Beverly, Mass.-based Envista offers a map-driven product that helps different parties exchange and coordination construction and maintenance schedules. Municipalities, public and private utilities and highway agencies can overlay their construction data to create a holistic view of the status of city roads and highways. The firm claims its product keeps construction budgets on track while reducing the impact of street cuts.

One problem that sparked Martin’s quest for an improved coordinating system was the repeated repaving of roads by different utilities.

“First the water department would come through, tear up the road, do [its] installation repave, and then the gas company would do the same,” says Martin. “Coordinating transportation, water and gas projects is like choreographing three gorillas to dance,” says Martin.

Envista overlays on the same map the different departments’ projects, sends e-mail notifications when there is a conflict among projects and sets moratoriums on newly paved streets. Envista also reports when any department manager updates his or her schedule.

“If each department doesn’t keep the data up to date, it’s not credible,” admits Martin. However, as long as the data is entered into the system, the advantages are substantial. “You can literally save hundreds of thousands of dollars in paving costs,” she says.

 

----- Advertising -----
  Blogs: ENR Staff   Blogs: Other Voices  
Critical Path: ENR's editors and bloggers deliver their insights, opinions, cool-headed analysis and hot-headed rantings
Project Leads/Pulse

Gives readers a glimpse of who is planning and constructing some of the largest projects throughout the U.S. Much information for pulse is derived from McGraw-Hill Construction Dodge.

For more information on a project in Pulse that has a DR#, or for general information on Dodge products and services, please visit our Website at www.dodge.construction.com.

Information is provided on construction projects in following stages in each issue of ENR: Planning, Contracts/Bids/Proposals and Bid/Proposal Dates.

View all Project Leads/Pulse »

 Reader Comments:

Sign in to Comment

To write a comment about this story, please sign in. If this is your first time commenting on this site, you will be required to fill out a brief registration form. Your public username will be the beginning of the email address that you enter into the form (everything before the @ symbol). Other than that, none of the information that you enter will be publically displayed.

We welcome comments from all points of view. Off-topic or abusive comments, however, will be removed at the editors’ discretion.