 |
|
 |

| special advertising sections |
 |
|
Demolition has been around
for as long as man has stood erect.
Archaeologists digging in ancient Mesopotamia
searching for cities built at the dawn of civilization
always discover that the structures were built
using material recycled from past buildings.
When the famous German archaeologist Hermann
Schliemann was digging in western Turkey, trying
to locate Homer's Troy, he discovered that seven
other cities lay beneath the metropolis sacked
by the Greeks during the Iliad.
The majesty that was ancient Rome and Constantinople
was built on materials reclaimed over and over
again by people versed in the arcane arts of demolition
and reuse. The same is true for most medieval
castles and monasteries. Their walls and ceilings
came from other structures that had outlived their
usefulness.
The modern demolition contractor enjoys the benefits
of a continuing technological evolution that began
with Galileo. It was Charles II of England who
ordered the first "demolition engines"
to knock down the wooden structures that were
fueling the "Great Fire of London" in
1666. As the Industrial Revolution began, new
equipment was developed to deal with the growth
of the large cities. As the great cities of London,
Paris, Berlin, Moscow and New York grew, so too
would the demand for construction and demolition
services.
In the 20th Century, the tragedy of World War
I would foster the development of a variety of
technological advancements that would enjoy wide
usage after the war. Better trucks and more powerful
dozers meant the demolition industry was becoming
safer and more productive. It was still a relatively
labor intensive process but you could see on the
horizon that equipment and technology was going
to play a larger and larger role in demolition.
As with the First War, World War II brought improvements
to equipment that would impact construction around
the world. Combat engineers and Navy Seebees developed
new construction skills building for war from
Western Europe to the South Pacific.
Since the early 1950s, the pace of innovation
has quickened. As with the rest of the construction
industry, the demolition industry has benefited
from the quiet hydraulic revolution that has taken
place over the last fifty years. New, more powerful
excavators with super-long boom arms have replaced
the old crane and wrecking ball. The wide array
of versatile attachments that allow demolition
contractors to chew through concrete or slice
through steel continues to grow each year.
As the environmental challenges that were brought
about by the industrial and chemical revolutions
confront the country, the demolition industry
has been able to react by developing new, safer
methods to decontaminate sites for productive
reuse.
Demolition contractors are in the forefront of
recycling the nation's waste. Estimates are that
the demolition industry recycles approximately
40% of the 165 million tons of construction waste
and demolition debris generated each year in the
United States. And this number continues to grow.
The people involved with this work are members
of the National Association of Demolition Contractors.
For nearly thirty years, the NADC has represented
the interests of demolition contractors in the
United States and Canada.
|
|
AED Heads Successful
Automotive Stripout |
|
It was prepared to meet the
challenge head on.
Allied Erecting & Dismantling Co., Inc.,
(AED), an NADC member in Youngstown, Ohio, was
selected as the prime contractor for a major automotive
dismantling project.
The monumental project involved the total stripout
of manufacturing equipment, utility lines, conveyors
and structural steel from almost 2 million sq
ft in only 4 weeks. The work was divided into
22 scheduled areas with new construction occurring
simultaneously in some areas and planned to start
immediately after the stripout crews finished
in others.
Planning began with the determination of the
type, size and quantity of equipment needed to
perform the job. AED had to consider units that
were small enough for maneuverability, light enough
not to damage the floor slabs, and durable enough
to work on an intense 24-hours-a-day, 7-days-a-week
schedule for the entire four weeks. It was determined
that over 100 pieces of equipment would be needed
for the project, including the new Allied-Gator
MT 70 Multi-Tool Processors and Allied-Gator Claw
Buckets, which were used to provide the power
and efficiency to process and load the masses
of scrap. In addition, AED engineered and built
specialized tools in six weeks to be ready when
the project kicked off.
Another area of detailed planning was staffing.
Given the enormous size of the job and the short
schedule, numerous work crews covering all shifts
and 22 work areas needed to be established. AED
decided to supplement its own workforce, but needed
workers knowledgeable in demolition practices
and specifically in the precision work involved
with stripout projects. AED contacted a long-time
friendly competitor, Dan Hoffman of Asset Recovery
Contracting, LLC (ARC) in Skokie, Ill., another
NADC member, which provided the additional supervision
and skilled workers that met AED's criteria regarding
experience, training and safe work practices.
Utilizing manpower from six states, AED and ARC
accumulated a massive amount of manhours on site
in just four weeks from when the project kicked
off on May 12.
As with every project, safety was a high priority-especially
considering the fast pace of the work-and to their
credit, neither AED nor ARC had a single OSHA-recordable
incident at the site. AED's dedication to safety
was rewarded with a Contractor of the Month "Best
of the Best" award from the project manager
for outstanding safety performance.
Capitalizing on 28 years of experience, AED's
management team and employees turned the task
of stripping out over 15,000 tons of materials
and over 200 truckloads of salvaged equipment
into a complete success. The combination of AED's
project management and equipment know-how and
ARC's manpower resources enabled AED to finish
the extensive work ahead of schedule.
|
|
Cherry Demolition
Braves Iowa Winter to Demolish Bayer Plant |
|
There's an old saying that goes,
"Neither rain nor snow nor sleet nor hail...."
Of course, this has usually been applied to the
local postman, but in this case, it is appropriate
to apply the adage to Houston-based Cherry Demolition
in Muscatine, Iowa.
Cherry Demolition was awarded the $2-million-plus
contract to provide dismantling and removal services
down to grade level in the closure of Bayer Corporation's
facility on a site owned by the Monsanto Company.
This was no run-of-the-mill plant demolition.
The project started in July, 2000 with the investment
recovery portion that had to adhere to a strict
time schedule for shipping the carefully dismantled
and matched-marked equipment to a compounding
facility overseas for re-use. The project ended
in June, 2001 with the demolition of the remaining
process facilities and infrastructure. Cherry
recycled 2,500 tons of scrap material and 6,200
tons of concrete.
A detailed dismantling plan was provided by Cherry
based on the required scope of work. The dismantling
portion of the plant was in close proximity to
the Monsanto Company facilities that remained
operational at all times during the performance
of this work. At no time was Cherry Demolition
allowed to interrupt utility or rail service to
these facilities.
"Cherry Demolition's performance handled
all of these concerns in a professional and competent
fashion," said Earl Howard, Bayer Corporation's
project manager. "Cherry's job superintendent,
Curtis Hollis, and his crew were extremely capable
and a pleasure to work with."
Although safety is always the number one issue
for Cherry Demolition on any job site, the close
proximity of the operational Monsanto Company
facilities made the issue even more critical.
|
|
Homrich
Leads Detroit Into its 300th Renaissance |
| Leading
Detroit farther into the future.
For the last 37 years, Homrich, Inc., a third-generation,
family-owned firm, has been leading Detroit, step
by step, into the future.
On April 29, 2001, Homrich did its part in leading
Detroit farther into the future. The firm was
chosen to remove four, 15-story Edward J. Jeffries
Housing Projects buildings in downtown Detroit.
The Jeffries projects once consisted of eight,
15-story buildings, four that were razed by Homrich,
two that have been renovated, and two more that
are now undergoing renovation.
After earlier performing extensive environmental
removals from all the structures and underground
tunnels, Homrich chose as implosion sub-contractor
fellow NADC member Dykon Explosive Demolition
Corporation from Tulsa, Okla. Homrich chose to
implode the structures because they wanted to
cause as little disturbance to the elderly city
residents remaining within the complex.
In only three days, and roughly 230 lbs of explosives
later, the buildings were ready to come down.
The explosives were set in selected columns in
the basements, first, second, fifth, and tenth
floors of the buildings.
The charges were detonated. Then all the pressure
came rushing downward as, one after the other,
all four buildings found their way safely to the
ground.
The next step was to begin processing, segregating,
and loading out the materials. This was the longest
and most tedious task of the project and took
nearly two months.
|
|
Brewing
New Life into an Old Building |
| The
108-year-old Grain Belt Brewery in north Minneapolis
became a popular landmark during the last century.
The picturesque, 108-year-old Grain Belt Brewery
in north Minneapolis became a popular landmark
during the last century, attracting beer lovers,
tourists and curiosity seekers from all over the
Upper Midwest. Unfortunately for many, the brewery
went dry and the building became vacant, when
the company was sold more than 25 years ago.
Finally, after many development schemes had come
and gone, a solid plan was put together by a leading
contractor/developer, the city's own development
agency and a leading architectural firm, who will
become the building's primary tenant. Their plan
is to retain the brewery's charming exterior appearance,
but re-construct the interior of the seven-story
behemoth into an upscale office complex. The remodeled
structure would also serve to attract other businesses
and multiple housing units, as part of a larger
development plan to improve an area along the
Mississippi River just north of downtown Minneapolis.
The $20.3-million project got underway in October,
2000 with a $3-million contract for environmental
remediation and selective demolition.
Spearheading the charge, as it has for so many
milestone development projects in the Twin Cities,
was Veit & Company, a leading excavation,
demolition and utility contractor. It was joined
by Veit Environmental, Inc., an asbestos, lead
and microbial abatement company. Both are units
of Veit Companies, which is headquartered in nearby
Rogers, Minn.
Veit Environmental removed large quantities of
asbestos-containing materials, such as thermal
insulation from the brew house, and unearthed
and disposed of asbestos-containing materials
that were buried on the property years earlier.
The asbestos removal included stripping the boilers
located in a three-story boiler house.
Lead-based paint, which was located throughout
the 104,000-sq-ft facility, was removed by using
sandblasting and waterblasting techniques. Microbial
abatement was accomplished by Veit employees in
boson chairs moving up and down the walls of the
brewery's six huge granaries.
Entire floors constructed of concrete with steel
perlins were deteriorated and needed to be removed
by Veit. Interior cat walks and mezzanines for
monitoring beer-processing equipment were demolished.
Plaster and limestone finishes were removed from
interior walls to reveal the building's elaborate
architecture.
Veit also removed additions to the building that
were outside the footprint of the facility in
order to make way for modern conveniences. Wall
and floor openings were made for new stairwells
and elevators. Acetylene torches, saws and brute
force were needed to remove 14 fermenting tanks,
two 20,000-gallon stainless steel holding tanks,
three 10,000-gallon tanks, three massive boilers,
and thousands of feet of pipe.
Ryan Companies recently awarded Veit Companies
with its Subcontractor of the Year Safety Award.
Veit's outstanding safety record over the years
was also recognized earlier this year with the
Governor's Safety Award from the Minnesota Safety
Council.
|
|
In a Box--AMC
Works on GWCC |
| AMC
Demolition Specialists, Inc. has recently started
the demolition of a very difficult dismantlement
project.
The project, at the Georgia World Congress Center
(GWCC) in downtown Atlanta, is part of an approximately
$300-million expansion.
The existing structure is a 100-ft-tall parking
garage, consisting of 11 alternating levels of
cast-in-place concrete. The scope of the project
includes the removal of all but two full levels
of the structure. Concrete beams and joists ranging
from 2 ft by 6 in. to 2 ft by 4 ft thick need
to be removed, while leaving the existing structural
concrete columns intact. These columns support
an area above that will remain occupied throughout
the project.
A typical demolition project generally requires
awareness of at least one exposure, such as an
adjacent building, a street, or pedestrian access.
This project, however, is surrounded on all six
sides with 2 in. of expansion joint being the
farthest distance to the adjacent structure, literally
in a box-thus providing limited ingress and egress
to the site.
Planning for the project began several years
prior to mobilization; it involved some of the
top structural engineers and architects in the
world .
AMC also installed specific shoring for the 22-in.-deep
pan deck concrete floors and floor beams during
the removal process. AMC in-house engineers determined
that the use of small, light, extremely powerful
demolition equipment would be required.
AMC developed a plan that included the use of
robotic, hydraulic, pneumatic equipment that they
altered and developed. These means and methods
were used throughout the project to assist in
dealing with the structural constraints of the
parking structure.
AMC's unique primary methods of demolition were
a million dollars less than the next closest bidders
using traditional concrete and wire sawing methods
and techniques.
|
|
CST Levels Northrop
Site |
| It
may look like ground zero of a B-2 strike in the
middle of Southern California.
But actually it is CST Environmental, Inc.'s
Demolition Division that is clearing this 160-acre,
4.5 million-sq-ft site in Pico Rivera, Calif.
Originally a Ford manufacturing plant, in the
early 1980s Northrop Grumman converted the facility
to a defense establishment for the United States.
It is here that the famous B-2 Stealth bomber
was produced for two decades.
The northern 90 acres of the site had to be cleared
within the first ten weeks to meet delivery dates
required by the owner. This section included over
one million sq ft of concrete and steel buildings,
slabs, footings, underground utilities, tunnels
and hazardous building materials. CST completed
the work within 60 days, a critical milestone
in the overall project. On-time completion was
accomplished by several means: comprehensive planning,
efficient utilization of CST's manpower and equipment
resources, and daily oversight by CST's senior
management.
CST developed a strategy that segregated the
site into 10 major demolition zones. Zones were
then established with clear dividing lines so
that each area could be safely completed.
Work commenced with up to 90 multi-tasked and
cross-trained employees on site at a time. One
team performs the environmental remediation while
the other team focuses on recycling and recovery
services. CST is utilizing up to 40 pieces of
heavy demolition equipment on the site.
CST anticipates it will recycle close to 300,000
tons of concrete by the end of the project, along
with 4 million sq ft of asphalt that will be pulverized
in place. In total, CST will accomplish approximately
85% total recycling on this project.
|
|
Viking Equipment
and J&G Industries "Recycle" Southern
California |
| Converting
the facility.
In the rush to get fighter planes into production
during the early years of the Korean War, Douglass
Aircraft Co. converted a former aluminum production
facility into an aircraft assembly plant. Thirty-eight
days after converting the facility, they began
producing airplanes.
In the process, they built over the foundation
pits and other underground concrete on the site.
When the facility's current owner, Boeing Realty
Co., retained NADC members Viking Equipment Corp.
and J&G Industries to demolish the plant,
the memories and records of details of this wartime
conversion had long been lost.
During the demolition of the two million sq ft
of buildings on the 57-acre site, Viking and J&G
began to uncover unexpected concrete. A search
of facility archives uncovered a picture of the
old ALCOA plant, which revealed the extent of
concrete on the site. Before the project was completed,
an additional 31,000 yds of concrete from this
previous use on the site was excavated. In total,
over 250,000 tons of concrete were crushed on
site to be sold as road base.
During the same period, the partners demolished
a larger project at the nearby former Long Beach
Naval Shipyard and a former plumbing fixture facility
on fifty acres, also in Southern California. In
all three of these similar projects, concrete
and steel recycled reached over 90% of the total
materials on the jobs.
|
|
Remote Controlled
Demolition |
| Introduced
just six months ago, the Brokk 330 diesel machine
has made a great impact on the demolition industry.
The Brokk now allows the operator complete mobility
to move the diesel-driven machine while controlling
the operation using a radio remote control box.
James Brady, vice president for BCA Equipment
Corporation in the Bronx, NY, sees the diesel
machine becoming a tool that is used for many
exterior applications including utilities, transportation
and bridge projects. "This machine can do
the job of a 20,000- to 30,000-lb excavator at
one-third the size-when you're working in a heavily
populated area like New York, size is a huge consideration."
There are many NADC members who own the Brokk
and have incorporated it into their day-to-day
equipment operations. Many contractors have used
the Brokk to solve complicated interior demolition
projects from floor-to-floor soft guts in a high
rise, to spillways inside a dam. Many have found
it an answer to the growing problem of manpower
on the job. The cost of workers using hand tools
versus the Brokk with skilled operator can see
a 6 to 1 advantage. This lowers overall cost,
increases production and, at the end of the day,
increases bottom line profits.
The uniqueness of the Brokk product is what has
propelled it to the front of the market. Most
contractors are looking for something that can
help them create profit in areas that their competition
has not penetrated.
|
|
Big R Demolishes
Denver Parking Facility |
| Recently
awarded the demolition of the Hyatt Regency Hotel
Parking Garage in Denver.
Big R Construction Company, located in Elizabeth,
Colo., was recently awarded the demolition of
the Hyatt Regency Hotel Parking Garage in Denver.
Big R was confronted with a variety of different
challenges as they began the project. First and
foremost was the fact the garage was attached
to a high-end hotel, the Hyatt Regency, and the
company had to work within established noise constraints
so the hotel's guests were not disturbed. In addition,
the garage was close to a 6-in. gas main.
Big R built protective cages for the gas main.
This insured that there would be no problems or
accidents with the line. All the concrete from
the parking garage was recycled. It was used as
a 4-ft base course for the new garage planned
for the site. The main reason the existing garage
had to be demolished in the first place was because
the original base was not properly prepared and
the floor had started to heave.
Big R Construction has been involved with the
recent redevelopment of Fitzsimons, an old Army
medical base. They did a great part of the demolition
of a number of old barracks and medical buildings.
Other major projects that they worked on include
Denver's North Side Treatment Plant. After all
the demolition work was completed, the plant was
turned into a city park. The company is also finishing
up a large project at the old Stapleton Airport,
Denver International Airport's predecessor.
|
|
R. Baker &
Son Demolishes John F. Kennedy International Airport
Concourse |
| This
high-profile project called for very tight security
and stringent safety precautions.
R. Baker & Son recently completed the demolition
of JFK'S American Airlines Concourse "C"
and terminal in Queens, NY. Begun in December,
2000 and completed by the end of June, 2001, this
high-profile project called for very tight security
and stringent safety precautions.
The project was made up of five integrated phases:
Phase One involved the interior demolition of
Concourse "C". This consisted of removing
all ceiling tiles, sheetrock, wood, electrical
conduit, electrical wiring and fiberglass insulation.
The owner, the Port Authority of NY & NJ,
severely restricted any generation of dust or
debris that might have found its way into the
engines of the jet planes.
Phase Two consisted of the separation of Concourse
"C" from the terminal building and the
demolition of the concourse. The separation of
the concourse had to be done with the utmost care
as the terminal area was occupied and remained
in use during the demolition.
Phase Three involved the interim demolition of
the center portion of the terminal that connected
Terminal No. 8 to Terminal No. 9. During the entire
hand-separation phase, terminal communication
lines were required to remain operational.
Phase Four involved the complete interior demolition
of the two ends of the terminal connecting Terminal
No. 8 and Terminal No. 9. A portion of this work
had to be done between midnight and 6:00 am to
minimize exposure to the public.
In Phase Five, the demolition consisted of the
removal of the remainder of the terminal connector
along with the baggage handling areas, roof structures
and any remaining walls and materials in the basement
area.
All metals and concrete generated by this project
were separated and shipped to the appropriate
recycler.
|
|
Automotive
Stripout Provides Testing Grounds for Allied-Gator
MT70 |
| All
equipment manufacturers test their products.
All equipment manufacturers test their products
and recently Allied-Gator was given a rare opportunity
to put its new Multi-Tool (MT) processor shear
to the test on a monumental industrial stripout
project side by side with several of its competitor
products. A total of 14 shears were chosen to
stripout and process for recycling over 15,000
tons of steel structure and equipment from an
area more than two million sq ft in size in just
four weeks. The equipment included three new Allied-Gator
MT70s, two Allied-Gator 2000 Series (2022 and
2029 models) and shears from two other leading
manufacturers.
 |
When put to the test, the Allied-Gator MT70 units
proved to be versatile enough to precisely reach
and efficiently shear the unwanted steel structure
and equipment without damaging surrounding lines
or building supports. The compact MT70s were easily
maneuvered into place, and the units demonstrated
enhanced power due to the enclosed single-cylinder
link system that delivered increasing power throughout
the full cycle of the cut. Everything from conveyors
and equipment to structural steel presented no
problem for the MT70s. In addition, the MT's revolutionary
design allowed the operator to clearly see the
actual cut, a feature that increased safety. Endurance
and reliability were also tested on site. All
units were required to operate on a grueling 24-hours-a-day,
7-days-a-week schedule for the 4-week dismantling
project. The MT's minimal maintenance requirements
minimized downtime as compared to the competitors.
Even though previous field testing of the MT70
units indicated their great potential, the challenges
presented at this project-the shear magnitude
of the job, the tight working conditions, and
the complete spectrum of materials that had to
be removed-clearly proved that these radically
different Multi-Tool Series far surpass the performance
of traditional shears.
Allied-Gator is planning nine sizes in the MT
Series and additional jaw sets for crackers and
crusher/pulverizers will be available soon.
|
|
Bierlein
Companies, Inc.-They're GR-R-REAT!! |
| The
sounds of Snap! Crackle! Pop! were not just coming
from its famous cereal.
Beginning in the spring of 2000 at Kellogg's
Cereal Plant in Battle Creek, Mich., the sounds
of Snap! Crackle! Pop! were not just coming from
its famous cereal. Kellogg's hired Bierlein to
demolish and remove an outdated 2,000,000-sq-ft
cereal manufacturing plant. This plant was replaced
with a state-of-the-art plant on the same site.
Portions of the facility being demolished were
the first structures built by Kellogg's for its
cereal manufacturing plant. Now obsolete, these
buildings were nestled in a cluster of newer buildings
and needed to be removed with the other structures
remaining intact and operational. Bierlein also
had to leave intact certain elements that were
attached to the outside of the surrounding buildings.
They covered the live lines and equipment with
crane mats to protect them from falling debris
as work progressed.
The train unloading docks for grains required
for cereal production were less than 20 ft away
from the demolition. Bierlein was required to
make certain that no dust or other contaminants
got into the grain while it was being unloaded.
Over 100,000 linear ft of asbestos insulation
was abated prior to the commencement of demolition
activities. A large quantity of PCBs were collected
and disposed of according to EPA specifications,
minimizing Kellogg's liability exposure and improving
the quality of the environment.
Like so many customers in the past, Kellogg's
has been extremely pleased with the contracted
demolition work. The project is scheduled for
an early completion in November, leaving Kellogg's
personnel saying, Bierlein Companies-They're GR-R-RREAT!!
|
|
|
|
|
| special advertising sections |
|
|