Global Best Projects Winner, Best Small Project: Schoolhouse South Africa

Text size: A A
Photo by by Jonathan Leape
----- Advertising -----

Serving up to 80 students, this 6,000-sq-ft early childhood development center and teacher training facility in Johannesburg, South Africa, was the culmination of two years of planning, design and construction led by student volunteers from Cornell University. Opened in 2011, the schoolhouse has become an integral part of the neighborhood and showcases the use of innovative building systems in low-income communities.

"This project shows us all that beauty doesn't need to be expensive, and challenges aren't always led by very experienced professionals," said one judge. "I am proud of our industry when I see the next generation leading the way."

Cornell University Sustainable Design (CUSD) was formed by students involved with the Solar Decathlon competition to "rethink how we can continue a design-build program but broaden our horizons," says Barry Beagen, project director. The group's interest in social, ecological and economic sustainability led them to partner with Education Africa's Social Architecture program, which encourages student organizations to design and construct low-cost preschools within impoverished communities.

After visiting the project site and speaking with local educators and community leaders, CUSD organized the project's design development via a competition among Cornell architecture students. Goals such as passive energy and low maintenance were identified early on. Funding for the project, which normally would have cost more than $500,000, was covered by donations from suppliers, sponsor organizations and student volunteers from over 22 countries. CUSD promoted a shared ownership in the preschool and increased cross-cultural learning by encouraging foreign students to work side by side with members of the local community.

"It was very important to formulate a common vision, because everyone had a stake in it," Beagen says. "That common vision was the same with the suppliers, contractors and our partners as well, because we knew this project wasn't just about the volunteers coming and going."

The building's structure was formed using earth-filled polypropylene bags placed inside EcoBeam frames. The extremely low-cost system increased the building's thermal mass and eliminated the need for active heating or cooling systems. "By filling the bags with soil excavated during the foundation-laying process, we reduced waste and transportation while transforming residual matter into a high-performing and resilient wall system," says CUSD member Daniel Lu. A reinforced concrete ring beam was placed atop columns integrated into the wall system to increase interior spans and prolong the building's useful life. Clerestory windows and child-height portal windows eliminate the need for electric lighting.

During the three-month build, CUSD required on-site volunteers to conform to U.S. and South African safety standards. As a result, the project's 23,000 man hours resulted in no injuries, which "speaks volumes for the volunteer workers," said a judge.

While the students learned many new skills, Beagen says the most important lesson for him was found in building character and leadership. "To me, managing relationships among the students and among the different contractors was the most valuable experience."

Location Johannesburg

Project Team

Owner Basil Read Developments, Johannesburg

Architect Cornell University Sustainable Design, Ithaca, N.Y.

General Contractor PD Solutions, Johannesburg

Engineers Tetra Tech, Ithaca; PD Solutions, Johannesburg

Partner Organizations Education Africa, Johannesburg; City of Johannesburg; Play-With-A-Purpose, Muldersdrift, South Africa

Keywords:

----- Advertising -----
  Blogs: ENR Staff   Blogs: Other Voices  
Critical Path: ENR's editors and bloggers deliver their insights, opinions, cool-headed analysis and hot-headed rantings
Project Leads/Pulse

Gives readers a glimpse of who is planning and constructing some of the largest projects throughout the U.S. Much information for pulse is derived from McGraw-Hill Construction Dodge.

For more information on a project in Pulse that has a DR#, or for general information on Dodge products and services, please visit our Website at www.dodge.construction.com.

Information is provided on construction projects in following stages in each issue of ENR: Planning, Contracts/Bids/Proposals and Bid/Proposal Dates.

View all Project Leads/Pulse »

 Reader Comments:

Sign in to Comment

To write a comment about this story, please sign in. If this is your first time commenting on this site, you will be required to fill out a brief registration form. Your public username will be the beginning of the email address that you enter into the form (everything before the @ symbol). Other than that, none of the information that you enter will be publically displayed.

We welcome comments from all points of view. Off-topic or abusive comments, however, will be removed at the editors’ discretion.