Bruce Bennett: Leader Demands Innovation on Vital River Passage

Text size: A A
Photo Courtesy USACE/William Gilmour
One of the major challenges at Olmsted was transporting 5,000-ton dam components.
----- Advertising -----

 

BENNETT
When Bruce Bennett became executive project director for the joint venture of URS Corp., San Francisco, and Alberici Constructors, St. Louis, his task was to build the dam section of Olmsted Locks and Dam. He was bound by certain contract constraints—namely, no cofferdams.

The contract required construction "in the wet," which meant that Bennett had to figure out a way to lift, move, lower and secure the 5,000-ton concrete shells that form the dam, which stretches 2,596 feet across the Ohio River.

"This manner of dam building has never been done to such a scale," says William Gilmour, resident engineer at the Olmsted Locks and Dam site for the owner, the U.S. Army Corp of Engineers. Gilmour has worked with Bennett throughout the project. Bennett and his team "do what it takes to get the technical challenges solved," says Gilmour.

All of Bennett's skills come into play at the riverine jobsite, which is characterized by murky, 60-ft-deep moving waters through which enormous objects must be lowered and placed in the blind to final tolerances within 0.5 inches.

"We knew we were going to have to figure out a way to set these shells to these kind of tolerances, but we didn't know how," says Bennett.

To meet the challenge, Bennett and his team had to improvise. They invented a pile-driving template that could accept variable shapes and sizes of pile; a screed that could work at a 70-ft depth through water; and software to lower and place fragile, 10-million-lb objects by coordinating GPS, total stations and ten 1,000-ton strand jacks atop the world's biggest catamaran gantry crane. As the project moves into 2012, Bennett will continue innovating to try and meet a newly adjusted budget and schedule.

Keywords:

----- Advertising -----
Video
  Blogs: ENR Staff   Blogs: Other Voices  
Critical Path: ENR's editors and bloggers deliver their insights, opinions, cool-headed analysis and hot-headed rantings
Project Leads/Pulse

Gives readers a glimpse of who is planning and constructing some of the largest projects throughout the U.S. Much information for pulse is derived from McGraw-Hill Construction Dodge.

For more information on a project in Pulse that has a DR#, or for general information on Dodge products and services, please visit our Website at www.dodge.construction.com.

Information is provided on construction projects in following stages in each issue of ENR: Planning, Contracts/Bids/Proposals and Bid/Proposal Dates.

View all Project Leads/Pulse »

 Reader Comments:

Sign in to Comment

To write a comment about this story, please sign in. If this is your first time commenting on this site, you will be required to fill out a brief registration form. Your public username will be the beginning of the email address that you enter into the form (everything before the @ symbol). Other than that, none of the information that you enter will be publically displayed.

We welcome comments from all points of view. Off-topic or abusive comments, however, will be removed at the editors’ discretion.