Design for Rapid Levee Construction Shaves Off Decade in Schedule

Text size: A A

Dwayne Smith, a senior engineer at URS Corp., San Francisco, is a geotechnical program manager on a levee enlargement project in New Orleans that is shaving a decade off the time it normally takes to build and consolidate such a structure.

Design for Rapid Levee Construction Shaves Off Decade in Schedule
Photo: Courtesy Angelle Bergeron
Smith's design uses sand, fabric, rock and clay stabbed with 8.8 million linear ft of wick drains to speed the work.
----- Advertising -----

Archer Western Contractors Ltd., Atlanta, holds the $114.9-million contract to deliver the 7.54-mile stretch of what will be some of the most massive earthen levees in the Greater New Orleans Hurricane and Storm Damage Risk Reduction System. The levees are built on soft, marshy soils in eastern New Orleans. From toe to toe, they are 320 ft to 360 ft wide, with elevations varying from 18-plus ft to 25-plus ft.

URS developed the design and specifications using Smith’s system, which layers a sand blanket, geotextile fabrics and rock over a landscape studded with 300,000 fabric-tape wick drains—almost nine million linear ft—to rapidly draw moisture from the soggy soil. It’s one of the largest projects in terms of square footage and number of holes ever done in the U.S., says Mark Palmatier, president and owner of U.S. Wick Drain, the wick installation supplier and contractor.

“When you put up to 30 ft of fill height on those soft soils, it would no doubt cause a slope failure,” explains Smith. Normally, such a levee would take 10 to 11 years of gradual buildup and consolidation to stabilize. However, by using Smith’s design, the U.S. Army Corps of Engineers is achieving that in 60 to 90 days. An array of monitors validates performance as the levee grows.

“Its really going well,” says John Grieshaber, chief of the execution support division in the Corps’ Hurricane Protection Office in New Orleans. He says the design is helping the Corps deliver promised levels of protection by June. He adds that he never thought he would see such a levee built this fast “on virgin marsh.”

 

----- Advertising -----
Video
  Blogs: ENR Staff   Blogs: Other Voices  
Critical Path: ENR's editors and bloggers deliver their insights, opinions, cool-headed analysis and hot-headed rantings
Project Leads/Pulse

Gives readers a glimpse of who is planning and constructing some of the largest projects throughout the U.S. Much information for pulse is derived from McGraw-Hill Construction Dodge.

For more information on a project in Pulse that has a DR#, or for general information on Dodge products and services, please visit our Website at www.dodge.construction.com.

Information is provided on construction projects in following stages in each issue of ENR: Planning, Contracts/Bids/Proposals and Bid/Proposal Dates.

View all Project Leads/Pulse »

 Reader Comments:

Sign in to Comment

To write a comment about this story, please sign in. If this is your first time commenting on this site, you will be required to fill out a brief registration form. Your public username will be the beginning of the email address that you enter into the form (everything before the @ symbol). Other than that, none of the information that you enter will be publically displayed.

We welcome comments from all points of view. Off-topic or abusive comments, however, will be removed at the editors’ discretion.