Mixing Social and Structural Skills, Project Leaders Guided Historic Rebuild in Minnesota

Text size: A A

Peter Sanderson was looking at a sea-link project in India when he heard about the Minneapolis Interstate 35W bridge collapse on Aug. 1, 2007. He knew immediately that he would not stay in India: “I believed surely there would be a lot of work to do in the U.S.”

title
Photo: Tim Davis
New St. Anthony Falls bridge rises at site of tragic I-35W crossing collapse.
----- Advertising -----

Not long after, Flatiron Construction Corp., Longmont, Colo., called upon Sanderson to lead the design-build team with Manson Construction Co. and designer Figg Engineering Group that would vie for, and win, the $234-million fast-track contract to rebuild the bridge.

“Peter was probably one of the best project managers I’ve worked with,” says Jon Chiglo, his counterpart at the Minnesota Dept. of Transportation. Between the leadership of Chiglo on the owner’s side, and Sanderson on the designbuilder’s side, the new precast segmental bridge with a 504-ft-long main span was ready for traffic three months early, just 13 months after the collapse.

Thanks to the tight ship the duo steered, the feat occurred with no major injuries, with constant community outreach and with unprecedented levels of quality inspections.

Bernard Amadei
Chiglo’s design-build savvy, discipline and calm professionalism were key in managing the rebuild of the I-35W bridge.

“Jon was extremely exacting, but helpful,” says Sanderson of those inspections. “It enabled us to get going. MnDOT reviewed drawings and designs and there was no obstruction.”

Chiglo cut his teeth on two of the eight design-build projects MnDOT had tackled before this historic one, and his ability to relate to the contracting team is evident: “When you look at the people [the design-build team] brought in, they left their lives behind,” he says. “They sacrificed quite a bit. There was no ability to go home very frequently. I really admire and appreciate that sacrifice. They did it because of the circumstances. It’s very encouraging when you see that kind of commitment.”

The commitment extended to public outreach. “Every Saturday morning, Peter Sanderson led people from the community on tours of the construction, giving them confidence in the new bridge,” says Linda Figg, president of the titular Tallahassee design firm. “Peter’s constant focus on safety resulted in no lost-time incidents, even through the intense Minneapolis winter and the accelerated schedule.”

Figg extended that outreach by coming up with a popular school program in which students made mosaic tiles to be placed on an approach to the bridge.

Chiglo and Sanderson anticipate more work to come. “I’m managing any money we might get in the stimulus package,” says Chiglo. “Last year, the state legislature passed additional funding, partly for replacement of deficient bridges. There are 121 bridges in the program and $2.5 billion over 10 years.

Sanderson hopes the stimulus package reflects a public realization of the need for better infrastructure and resulting work to come. “I’m looking forward to it. I think the whole construction industry is looking forward to it.”

 

----- Advertising -----
Video
  Blogs: ENR Staff   Blogs: Other Voices  
Critical Path: ENR's editors and bloggers deliver their insights, opinions, cool-headed analysis and hot-headed rantings
Project Leads/Pulse

Gives readers a glimpse of who is planning and constructing some of the largest projects throughout the U.S. Much information for pulse is derived from McGraw-Hill Construction Dodge.

For more information on a project in Pulse that has a DR#, or for general information on Dodge products and services, please visit our Website at www.dodge.construction.com.

Information is provided on construction projects in following stages in each issue of ENR: Planning, Contracts/Bids/Proposals and Bid/Proposal Dates.

View all Project Leads/Pulse »

 Reader Comments:

Sign in to Comment

To write a comment about this story, please sign in. If this is your first time commenting on this site, you will be required to fill out a brief registration form. Your public username will be the beginning of the email address that you enter into the form (everything before the @ symbol). Other than that, none of the information that you enter will be publically displayed.

We welcome comments from all points of view. Off-topic or abusive comments, however, will be removed at the editors’ discretion.