|
Scott Blair/Southwest Contractor
Unsecured girders with residual protective material slipped off pier caps. |
A mysterious Aug. 9 bridge collapse
in Mesa, Ariz., resulting from “lateral
instability” has prompted the
Arizona Dept. of Transportation to update
its construction specifications to
require temporary bracing during bridge
construction.
A 122-page report by CTL Group, a
Skokie, Ill.-based investigative consultant,
blames “a number of factors adding
together in a critical combination” as the
reason for a 114-ft-long bridge section
under construction to fall. No one was
injured.
Nine of 11 precast, pre-stressed
girders of a bridge section on the Loop
202 Red Mountain Highway dropped 25
ft from their pier caps. The girders on the
westbound lanes of the 87.8-ft-wide
bridge section, each 2.5-ft-deep and
105,000-lb, had been placed atop the pier
caps three weeks prior. They fell into the
Central Arizona Project’s nearby canal,
cracking upon impact. The girders are
being replaced at the contractor’s
expense, estimated at $185,000. Pier caps
sustained only minor scraping.
Results from the four-month investigation
cite “bearing eccentricity” and unremoved
girder protective material as
contributing to the incident. Other potential
factors include thermal expansion,
wind load and a lack of temporary lateral bracing. No work was done on the unsecured
girders while awaiting the cast-inplace
diaphragms, says Doug Nintzel,
Arizona Dept. of Transportation spokesman.
Temporary bracing, although a
common practice, is not required under
ADOT contract specifications.
But that will soon change. ADOT is
now updating its specifications to require
temporary bracing for all girders after
they are placed and before permanent
braces are added. It was one of the
report’s many recommendations for future
construction, including checking for
girder centering and clearing surfaces
before placement.
“Specifying temporary bracing in all
cases is another step we can take to enhance
safety,” says ADOT state engineer
Sam Elters. “While this was a rare event
and there are always risks in construction
projects, we are prepared to work with
our contractors to prevent any such accidents
in the future.”
The 4.8-mile, $195-million project, is
not expected to be delayed by the incident.
Phoenix-based Pulice Construction
Inc., the general constructor, has a 650-
working-day schedule. Royden Construction
Co. is the Phoenix-based subcontractor
responsible for girder manufacturing
and erection.
|