|
Mile by mile and pin
by pin, contractors are stabilizing and widening a Pennsylvania
highway once studded with crosses marking the sites of traffic
fatalities.
The notoriously dangerous two-lane,
7-mile stretch of Lewistown Narrows highway is now undergoing
a $105-million retrofit and widening to four lanes. It is
the states most complex highway project ever, says Gary
Hoffman, PennDOT deputy secretary for highway administration.
Walsh Construction, Chicago, won
the four-year contract to reconstruct the length of Route
22/322 in 2004. Hemmed in on the north side by boulder-strewn
slopes and on the south side by the Juniata River and the
Pennsylvania Canal, crews also must allow two lanes to remain
open for 20,000 vehicles a day to pass.
The road will be reconfigured so
that the eastbound, riverside lanes are separated from and
lower than the westbound lanes. Concrete barriers will separate
the sets of lanes. "Were putting in fill at the
base of the slopes that will act as a counterweight [against
the slopes of the mountain], and the westbound lanes will
be on that fill," Hoffman says.
Pilings drilled into the bedrock
pin the roadway in place. The technique is rare in Pennsylvania
and has never been used to such a great extent in the nation,
says Neil Fannin, a PennDOT geotechnical engineer. "The
amount of pilings were using there is exceptional."
The 7-in.-dia steel pipe pilings
range in length from 15 to 45 ft. The pilings are drilled
through a top layer of soil, then through a clay layer and
embedded 6 ft into the bedrock. The "micropiles"
are filled with grout, which will bond the pipes to the rock.
Each pipe has
a 0.5-in. wall thickness and are
spaced 1 to 2 ft apart for three miles, says Jonathan Raab,
geotechnical engineer with Harrisburg-based GTS Technologies
Inc., development and design consultant. "Without a doubt,
the Narrows is the largest project with these types of stability
issues that has ever been done in the state."
The Federal Highway Administration
did not have a strong precedent for the design of the project,
Raab notes. "This method of micro-pile stabilization
has been used elsewhere, but on a much smaller scale,"
he says.
With the scale and the variety
of soils, "the application here is unique because of
the geology of the site and the difficulty of what were
trying to do," FHWA geotechnical engineer Silas Nichols
says.
|