 |
| SUSPENDED
Bay Bridge east span awaits additional funding and decision
on a single bid that came in well over engineers
estimate. (Photo courtesy of newbaybridge.org) |
California officials
now appear likely to favor accepting a single $1.4-billion bid
submitted in May for a suspension bridge that is a signature
element of the San Francisco-Oakland Bay Bridges east
span. But state legislators faced a looming deadline last week
to close a $660-budget shortfall so that the state can beat
a Sept. 30 deadline for accepting the bid.
In a long-awaited report published
Aug. 16, the California Dept. of Transportation warns of a
year-long delay and more cost increases unless the legislature
approves additional funding for the spans self-anchored
cable suspension bridge. The report estimates that the entire
east spans cost has nearly doubled, from $2.6 billion
to $5.13 billion, since 2001.
The sole bidder, a joint venture
of American Bridge Co., Coraopolis, Pa., Nippon Steel Bridge,
Tokyo, and Fluor Enterprises, Aliso Viejo, Calif., submitted
a $1.4-billion bid, nearly double Caltrans $740-million
estimate (ENR 6/7 p. 11).
That bid expires Sept. 30, which
marks an extension granted by contractors to the 60 days allowed
for Caltrans to accept or reject a bid. "You cant
award the contract unless you have identified funding,"
says Robert Oakes, spokesman for state Sen. Tom Torlakson
(D), transportation committee chair. "If we dont
get something hammered out, were just going to have
to rebid the contract."
Some have blamed the spans
innovative design and stringent seismic requirements for increasing
costs, but drastic changes are impractical, Oakes says. "The
design we have is what we have. Its too late to talk
about going back," he says.
The funding shortfall marks a crossroads
in the Bay Bridge project. A joint venture of Kiewit Pacific
Co., FCI Constructors Inc. and Manson Construction Co. holds
the main construction contract for the suspension spans
$294-million foundations. They are 55% complete. Peter Kiewit
Sons Inc., with Skanska Inc., was interested in the
suspension bridge but never submitted a bid. Another major
portion of the east span, the $1.5-billion concrete viaduct
dubbed the Skyway, is about 55% complete.
Caltrans report, which surveys
the retrofit program for all seven of the states toll
bridges, cites a complex set of factors that have contributed
to the cost increases on the East Span. Post-9/11 changes
in the insurance and bonding markets, combined with the size
of the projects, "reduced available bidders and resulted
in a limited number of joint ventures capable of bidding these
projects," the report states.
Multiple Bay Area toll bridge projects
reduced contractor capacity and limited access to key marine
equipment, the report adds. Caltrans also notes that costs
were increased by pushing back the completion date from 2007
to 2011, an extension requested by contractors to handle the
complex design. In the past two years, cost escalation has
exceeded 10 to 15%, with some materials doubling in price.
Gov. Arnold Schwarzenegger (R)
has responded by proposing to shift financial responsibility
from Caltrans to the Metropolitan Transportation Commission,
an Oakland-based regional agency. He suggests dedicating a
new $3 local bridge toll recently approved by voters to pay
for the cost increases.
Oakes disapprovingly calls Schwarzeneggers
proposal "a non-starter, particularly when he has targeted
a toll increase that Bay Area voters [approved] on their own
to build projects....Its a state highway. Its
an Interstate highway and the state has always paid a share."
Adds MTC spokesman Randy Rentschler: "Obviously the governor
is starting to walk away from this part of the state highway
system, and we disagree with that."
Funding options include a stop-gap
measure that would increase the suspension spans budget
and defer the remaining shortfall to the next legislative
session. Also on the table is transfer-
ring toll-setting powers to MTC,
says Oakes. Even these measures will fail to address the underlying
problem. Says Rentschler: "As the population has doubled...the
infrastructure has not doubled with it.
|