|
Standing last month
at the edge of a gorge 1,500 ft downstream from the Hoover Dam,
Federal Highways Administration project manager F. Dave Zanetell
marked the Boulder City, Nev., site where work may begin this
fall on a 1,905-ft-long single-arch bridge. Its planned completion
has been pushed back a year to 2008. Without a bi-state commitment
to alternative funding, the delay could have been worse for
the structure that will allow traffic to bypass the dam.
Delayed reauthorization of the
Transportation Equity Act for the 21st Century (TEA-21) held
up the final $90-million piece of federal funding for the
$234-million project. Victor M. Mendez, director of the Arizona
Dept. of Transportation, and his Nevada counterpart, Jeff
Fontaine, last month pledged $50 million each in GARVEE (Grant
Anticipation Revenue Vehicle) bonds to keep the project moving.
This stopgap use of GARVEE bonds could become more frequent
as reauthorization continues its holding pattern in Congress.
"Other states will take note
of Arizona and Nevada using GARVEE bonds to keep the project
going," says Thomas R. Warne, a consultant and former
head of the Utah Dept. of Transportation. "If it makes
sense for their programs, they may pursue using GARVEE bonds
as well."
 |
 |
 |
| KEY
States provide stopgap funds to begin centerpiece arch
span (model, above) while work continues on approach structures.
FHWAs Zanetell says first phases are below estimate.
(Photo top courtesy of the Federal Highway Administration;
photos bottom by Tony Illia for ENR) |
States have sold some $5 billion
in GARVEE bonds since 1998, says Barney Allison, partner with
Nossaman, Guthner, Knox & Elliott, a Los Angeles-based
law firm. Since the bonds imply years of debt service payments
before repayment in federal funding kicks in, "youre
saying this project is a priority today," he adds.
The two-lane U.S. Highway 93, a
key route in the North America Free Trade Agreement, traverses
the crest of Hoover Dam and handles 13,000 vehicles daily.
Since the 9/11 terrorist attacks, truck traffic over the dam
has been rerouted 23 miles away, costing consumers some $30
million annually, says Zanetell. The bypass will provide a
more direct route.
A team led by HDR Inc., Omaha,
with Pasadena, Calif.-based Jacobs Engineering unit Sverdrup
Civil and San Francisco-based T.Y. Lin International, designed
the centerpiece span, tentatively scheduled to bid in September.
Rising 890 ft over the Colorado River, it will be the longest
concrete span in North America. Bidders can choose one of
FHWAs suggested methodsusing dual towers with
tiebacks to cast the span in place or erecting precast segments
with cranesor propose other methods. The expected 36-month
contract will be followed by a $15-million asphalt paving
contract.
Construction on the overall route,
which includes 4 miles of four-lane road, began last year.
Using A+B bidding, the first two phases are at least 10% below
engineers estimate, Zanetell says. The $21.4-million,
1.8-mile Arizona approach, built by R.E. Monks Construction
Inc., Fountain Hills, Ariz., with Chino Valley, Ariz.-based
Vastco Inc., is 85% complete.
Scheduled to finish by November,
the project includes a 16.7-ft-tall diamond interchange with
1,300-ft-long ramps cut into mountain slopes to enable two
lanes in each direction at a gateway road into the Lake Mead
recreational area. Awaiting final girder placement is the
902-ft-long Sugarloaf Mountain Bridge over a 160-ft-deep ravine.
The crossing consists of 77 prestressed, 128-ft-long concrete
box girders, each weighing 132,000 lb.
The $30.1-million, 2.2-mile Nevada
approach, built by Edward Kraemer & Sons Inc., Plain,
Wis., is 30% complete and ahead of its October 2005 deadline.
It includes six new bridges, including a 465-ft-long, cast-in-place
box girder structure and a 12-ft-tall x 24-ft-wide culvert
wildlife crossing at U.S. 93.
Due to rugged terrain and basalt,
the project requires a total of 3.2 million cu yd of material
to be excavated using drill-and-blast methods. Fencing and
other measures are needed to protect endangered species such
as bighorn sheep. The most challenging componentthe
arch bridgeis yet to come.
|