|
Construction has recently
begun on the first phase of the Federal Highway Administration's
Hoover Dam bypass bridge . The joint-venture team of R.E. Monks
Construction Co., Fountain Hills, Ariz., and Chino Valley, Ariz.-based
Vastco Inc. landed the initial $21.5-million contract to build
a 1.8-mile four-lane asphalt roadway from U.S. 93 to the Arizona
side of the Colorado River.
The work requires a 900-ft-long
precast concrete girder bridge, which crosses a 200-ft-deep
ravine, plus a cast-in-place intersection bridge at the Hoover
Dam Access and Kingman Wash roads. The two-year undertaking,
slated to finish by October 2004, also includes 1.7-million
cu yd worth of difficult excavation that must be drilled and
blasted. The A+B contract has liquidateddamages of up to $10,000
a day, but also includes 5% bonuses for materials that exceed
specifications.
"Essentially, it's a great way
of ensuring that all parties deliver a quality project that
will last over a long period of time," says Dave Zanetell,
FHWA's project manager.
In October, the Western Power Administration
awarded a $9.6-million utilityrelocation contract to Kansas
City-based Par Electrical Contractors Inc. to move eight steel
lattice transmission towers and accompanying 230-kV and 440-kV
lines from the path of the bridge. The first phase will finish
in June.
The project is expected to greatly
relieve the congested two-lane U.S. 95 highway, identified
as a NAFTA route, which currently runs over the crest of the
dam. The 2,000-ft-long bypass bridge will be a single-arch,
steel-and-concrete composite structure crossing the Colorado
River 1,700-ft downstream from the dam. HDR Inc., Omaha, with
Sverdrup Civil Inc., a unit of Pasadena-based Jacobs Engineering
Group Inc., and T.Y. Lin International, San Francisco, are
the project's engineering-design team (ENR 7/23/01 pg. 7)
Originally estimated at $198 million,
FHWA adjusted its total costs to $234 million after the geotechnical
survey, conducted by London-based AMEC PLC, found that Black
Canyon's rigorous slopes would require pricey excavation.
Contractors must create 90° and 73° sheer drops
at theNevada and Arizona sides, respectively, to minimize
the amount of excavation otherwise needed for more gradual
transitions.Controlled explosives will be used to carve-out
the canyon walls, which descend 850 ft to the Colorado River.
FHWA plans to advertise the second
phase, the 2.5-mile, four-lane Nevada approach, in June followed
by the bridge structure itself in October. The project is
scheduled for completion in 2007.
|