A Maryland state
legislator says federal officials and the state's attorney
general are reviewing a sole December bidwell above
engineer's estimateto build the new Woodrow Wilson Bridge
across the Potomac River. The state Dept. of Transportation
now is weighing three options for rebidding the job.
The U.S. Justice Dept., U.S. Dept.
of Transportation Inspector General and Maryland Attorney
General J. Joseph Curran Jr. are looking into the lone bid
for the bridge superstructure contract, says Peter Franchot
(D), chairman of the House of Delegates' transportation and
environment subcommittee. The proposal, submitted by Kiewit
Construction Co., Tidewater Construction Corp. and Clark Construction
Group Inc., totaled $860 million, or 72% above the State Highway
Administration estimate. SHA rejected the bid Jan. 29.
Maryland's Bid
Options
One contract: Entire outer bridge, firms also can bid
inner bridge
Three contracts: Both bascules; over-water part; over-land
part
Two contracts: Both bascules; outer span land and water
sections
Source:
Maryland Dept. of Transportation
Curran's office has had "conversations"
with Maryland DOT Secretary John Porcari and State Highway
Administrator Parker Williams, says Jack Cahalan, a Maryland
DOT spokesman. Curran spokesman Sean Caine says the Attorney
General spoke with Franchot about the bridge, but could not
confirm whether or not the office is performing an investigation.
Justice Dept. spokeswoman Gina Talamona had no comment and
a DOT IG spokesman didn't return a call seeking comment.
Franchot asserts that the bid
could be "described politely as inflated." But Jerry
Pfeffer, spokesman for the Kiewit-Tidewater-Clark group, says
none of the joint venture firms has been contacted by the
state AG, Justice or DOT IG. "When we put in a bid, we
always give it our best shot," he says."It's ludicrous
to suggest that we would conduct ourselves in any way other
than absolutely open and above board."
The superstructure is the largest
piece of the $2.4-billion project, which includes four big
interchange upgrades. Maryland retained an outside panel led
by former Utah DOT chief Tom Warne to recommend ways to rebid
the job. Williams says the state wants more contractor competition.
Plans still call for two parallel
six-lane bascule spans. But the state is deciding among three
contract options the panel recommended. They are:
A single contract for the outer six-lane span, with proposals
also allowed for the inner span.
Three contracts; one for the bascule portions; one for
the outer bridge's over-water segment, with bids also permitted
for the inner span's over-water portion; and one for the
outer bridge's over-land section, with bids allowed for
the inner span over-land portion.
Two contracts; one for both bascule portions and one for
the outer bridge's non-bascule sections, with bids also
allowed for the inner bridge's over-land and over-water
portions.
Porcari says the state will
decide "within several weeks, at the outside," which
option it will pick. He released a summary of the outside
panel's report, which said the Kiewit-Tidewater-Clark bid
"was too high." It said the state estimate was "technically
solid...based on the tangible factors like the cost of steel,
concrete and other materials." But it said the state
didn't adequately factor in such "intangibles" as
higher-than-estimated bids on other recent bridge projects
and the Wilson job's demand for specialized equipment.
Porcari says the panel found that
inclusion of a Wilson bridge project labor agreement provision,
deleted after the Federal Highway Administration objected,
did not have a major effect on the lack of bidders.
Just Released The McGraw-Hill Construction Outlook 2009 is the industry’s highly respected and most closely watched outlook for the year ahead. Get all the information needed to plan for 2009 and beyond.