|
Investigators
have begun sifting for clues to the cause of a bizarre fatal
bridge accident in Colorado in a process expected to take
six to eight months.
 |
| DANGER
AHEAD Girder temporarily braced by adjacent overpass
flipped over and sagged into active lanes below. (Photo
by Marc Williams) |
On May 15, a bridge girder that
had been erected over the eastbound lanes of Interstate 70
west of Denver fell on its side and sagged into the path of
a sport-utility vehicle, killing its three occupants, all
members of one family. Construction work was not in progress
at the time of the accident. The girder had been erected four
days earlier, but subsequent scheduled work had been suspended
because of bad weather.
Asphalt Specialties Co. Inc.,
Henderson, Colo., is the prime contractor for the $12-million
project to improve the interchange between Colo. 470 and I-70
in Jefferson County. The project is adding three girder lines
fabricated by AFCO Steel, Little Rock, to widen the C-470
overpass, built in 1988, from between 50 ft and 62 ft to 80
ft to accommodate one additional lane of traffic and extend
a merge lane.
Subcontractor Ridge Erections,
Arvada, Colo., on May 11 set the first girder, consisting
of two segments totaling 28 tons. It picked each piece with
separate cranes and spliced the steel in the air with bolted
plates to create a 153-ft span. Subsequent construction was
to have added a third segment across the westbound lanes of
I-70 to the other two girders. The sequence was left to the
contractors option, but Mark Leonard, state bridge engineer,
does not know what it was.
Five angle brackets held the girder
in place, with one bolt in the girder and one to three bolts
in the top of the deck of the adjacent overpass, Leonard says.
But he doesnt know details. The contract documents
do not specify the means or methods of temporary support,
he says.
Rainy weather that threatened to
become snow caused the suspension of work scheduled for the
rest of the week, but winds were not high. To observers,
it was...
|