|
Preparations are
beginning for a formal inquiry into the April 20 collapse
of a Singapore mass-transit tunnel excavation in which four
workers were killed. For the record, all parties on the project
are limiting their comments to bland disclaimers, if they
are commenting at all. But knowledgeable sources are pointing
to price competition engendered by the design-build project
delivery as a contributing factor in the accident.
Nine parties are scheduled to testify
at a May 14 conference to be held by the Singapore governments
commission of inquiry. Formal proceedings are to start
June 1.
 |
| SHAFT
SITE Excavation next to circular shaft collapsed
when bracing panels failed. (Photo courtesy of Singapore
LTA) |
A section of the temporary
diaphragm wall supporting the excavation adjoining the proposed
Nicoll Highway Station collapsed, says Ho Meng Kit,
chief executive of the owner, the Land Transport Authority.
This caused soil subsidence of the immediate surrounding
area that resulted in substantial damage to about a 100-m
section of Nicoll Highway. In addition to causing the
deaths of three construction workers and an inspector, the
collapse also rendered two buildings unsafe.
The design was extremely
aggressive to the point that it took almost a year to approve,
says a knowledgeable source, who asks to remain anonymous.
To win the design-build contract, everybody was trying
to shave as much as possible in the cost to be more competitive.
Three or four groups competed for the work, and other
designs were more substantial than the one that won,
he says.
As for the design and methods
of construction, they were approved by the LTA, counters
Philip Khoo, Singapore-based deputy project manager of Nishimatsu
Construction Co. The project contract is held by a joint venture
of Tokyo-based Nishimatsu and Singapore-based Lum Chang Building
Contractors. Maunsell Consulting Co., an Australia-based unit
of AECOM, Los Angeles, is the projects permanent design
engineer.
The collapse occurred in a cut-and-cover
tunnel excavation for the Nicoll Highway station on the island
nations 33-km-long Circle Line where four tracks, stacked
two over two, widen onto a single level and begin to dip below
the Kalang River. A circular shaft for lowering a tunnel-boring
machine is adjacent to the site of the collapse.
The work began in 2001 and is part
of a $158-million contract by the design-build joint venture
to construct two stations, 1,600 m of cut-and-cover tunnels
and 800 m of bored tunnels. Completion of this stage of the
line was scheduled for 2007. LTA has declined to estimate
the impact on cost and schedule until the investigation is
completed.
The excavations design depth
is 33 m, with 10 levels of bracing. At the bottom, two levels
of jet grouting were installed. The first, 1.5 m thick, was
a sacrificial one between the 9th and 10th brace. The other,
1.5 m thick, tapering towards one side to nothing, was below
the bottom of the excavation.
The collapse occurred while workers
were excavating at about 30 m for the 10th level of strut.
An 800-mm slurry-wall retention system, without a capping
beam and with a waler at the top and none in the lower levels,
failed. Each slurry-wall panel was supported with a
single brace. Consequently, when the bracing failed, the slurry-wall
panels were acting individually and, like domino pieces, fell
one-by-one, says one source.
Monitoring of wall movements suggested
that design parameters were exceeded well before failure occurred.
Monitoring data are not available, but sources report that
wall deformations of 450 mm were observed before the collapse.
Owners of nearby...
|