|
Investigations
are just now being launched into the causes of two unrelated
fatal crane accidents at bridge sites that occurred within
24 hours of each other. Three workers were killed and five
injured in Toledo on Feb. 16 and there is one confirmed fatality
in Stratford, Conn., at ENR press time on Feb. 17.
The accident in Toledo occurred
about 2:30 p.m. at the site of the $220- million Maumee River
Bridge, a precast segmental cable-stayed structure with a
1,225-ft main span. As crews from St. Louis-based Fru-Con
Construction Corp. were repositioning a 2-million-lb, 315-ft
launching truss to prepare for another segment placement,
the truss collapsed. Killed were ironworkers Robert Lipinski
Jr., 44, of Grand Rapids, Ohio; Mike Moreau, 30, of Lambertville,
and Mike Phillips, 42, of South Toledo. All were members of
ironworkers'; union Local 55. Five other workers were injured,
two seriously. The truss, which was not carrying a segment,
fell partly onto Interstate 280, but no motorists were injured,
says Joe Rutherford, Ohio Dept. of Transportation spokesman.
It is unclear how many workers were on site, but Fru-Con generally
has more than 300 workers on the project, he says.
I-280 will remain closed indefinitely,
"until we can ensure the safety of the investigation
of the workers in the area, the investigators themselves and
the motorists," Rutherford says. The county coroner,
Toledo police, U.S. Occupational Safety and Health Administration
and Fru- Con all are conducting investigations. "There's
been preliminary contact with the police department,"
says Rutherford.
OSHA, Fru-Con and ODOT had a partnering
agreement for safety on the job, a state first. Until the
accident, Fru-Con had worked 1 million man hours between March
2002 and Dec. 31, 2003, with just five lost-time injuries400%
better than the national average.
The $3-million truss was one of
two custom-built by Italian manufacturer Paolo de Nicola.
It normally takes the pair of trusses one week to complete
each 150-ft span. They had completed 11 of 30 spans late last
week, say Fru-Con sources. The crane lifts the sections of
roadway into place. Once a span of roadway is completed, the
crane's back end and middle legs are advanced inchworm-like
to the next pier. Each span weighs between 75 to 100 tons,
says Rutherford. The new bridge will rise 130 ft above the
existing route carrying 1-280.
Fru-Con had been on track to finish
the job 14 months ahead of the scheduled completion date of
mid-2006 with a $5-million value-engineering bonus, says Rutherford.
The impact on the schedule now is not yet known, but four
bridge piers and two segments were damaged. OSHA has six months
to report its findings, though it will not likely take that
long, says Rutherford.
The bridge is the largest public
works project in Ohio. Designed by Figg Engineering Group,
Tallahassee, it will have a unique cradle system for its single
plane of cables attached to a 404-ft-tall pylon, featuring
200-ft panels of glass.
Less than 24 hours later, at a
$96-million bridge replacement job in Stratford, Conn., two
barge-mounted cranes collapsed, killing the crane operator,
says Connecticut Dept. of Transportation spokesman Paul Breen.
"One is in the river and the other's boom flipped backwards
and impacted the western shore," he says. The cranes
were lifting out a girder of the 1,800-ft-long, four-lane
steel-grated Sikorsky Memorial Bridge, which has been replaced
by a new bridge opened last year over the Housatonic River.
Apparently the boom of one crane snapped, causing the collapse.
Balfour Beatty Construction Inc.,
Atlanta, won the contract for the job in 2001. It was due
to be completed in 2005 under an extended schedule. At ENR
press time on Feb. 17, the state fire marshal who handles
crane accidents, the state police and OSHA were all still
on the accident scene, but all lanes of State Route 15 had
been reopened to traffic, says Breen.
|