Change.
New structure design (right) replaced clevis connection.
Loose bolts contributed
to the collapse of 30 extra-high-voltage transmission towers
as Hurricane Wilma moved across South Florida, an independent
engineering analysis has determined. The October 2005 storm
crippled Florida Power & Light Co.’s electrical
system.
The 30 steel-pole H-frame structures
on FPL’s Conservation-Corbett 500-kV transmission line
between Palm Beach and Broward counties failed completely.
Juno Beach, Fla.-based FPL retained KEMA Inc., a Dutch engineering
firm, to investigate the performance of its electrical infrastructure
during the storm. KEMA found that hand tightening of crossbrace
connection bolts, a foundation failure resulting from faulty
installation and one tensile failure together could have initiated
a cascading affect bringing down the H-frames.
More than 3 million FPL customers
lost power in the storm, which was rated Category 3 at landfall,
near where the line fell.
New Design
The line was built in 1996 in accordance with the National
Electrical Safety Code, manufacturer’s guidelines and
general industry standards, which require tightening with
manual torque wrenches, says Richard E. Brown, senior principal
consultant in KEMA’s Raleigh, N.C., office. But FPL
had just adopted a new transmission line design, which used
a higher tension on the conductors. “They strung them
tighter,” Brown says. “When you string them tighter,
they are more susceptible to vibration.”
The new design also replaced a
clevis-type connection between the crossbrace and pole with
a direct connection using a plate welded to the pole, according
to the KEMA report. The two plates are connected by a single
bolt and nut, without washers or locking devices.
The report says manually tightening
the bolts could be difficult if a small offset exists between
the plate and crossbrace. “Tightening of the bolt would
only be possible if at the same time this offset is corrected,”
it says.
The line experienced aeolian, or
wind-induced, vibration problems in 1998. While assessing
the line, crews noticed some loose or missing bolts and likely
hand-tightened them, the report says. FPL also put vibration
dampers on the conductors to solve the problem.
“What likely happened is
they went back to check on whether the vibration problem was
corrected, and it was,” Brown says. “Conductor
vibration was reduced to a level below where conductor damage
would occur. But it appears that vibra-tion was not below
where loosening of the bolts could recur.”
The investigation found no inspection
record data showing that bolts were loose or missing before
last year, but could not determine when the structures were
last inspected. FPL inspects 500-kV transmission lines on
a four-year, 10% sample inspection, which KEMA concludes may
not have been sufficient to detect the bolt problem.
FPL declined to comment, discuss
the utility’s plans to harden its system or disclose
the location of the Conservation-Corbett line. The Public
Service Commission also declined to comment.
Since the storm, FPL has tightened
the bolts on the connection with about 4,600 ft-lb of torque,
says the report. FPL also is deliberately damaging the threads
so the bolts stay in place permanently. Neither is a standard
industry practice, according to Brown.
KEMA also found that when one structure
failed, the lines pulled adjacent ones down as well. “We
would have a row of six, 10, 15 structures that all came down,
probably initiated by a single pole coming down,” Brown
says. “The weight transfer to the adjacent poles was
devastating in the hurricane and resulted in cascading failures.”
FPL filed KEMA’s report last
month along with a petition to the Florida Public Service
Commission to establish a storm-recovery financing plan that
would eliminate a $1-billion deficit in its storm reserve
and help to build a new reserve. The plan includes issuing
bonds to pay for storm-related repairs and imposing a customer
storm surcharge. Alternatively, the utility asked for a higher
surcharge.