The U.S. Nuclear
Regulatory Commission imposed its largest fine ever—$28
million—on FirstEnergy Corp.’s nuclear subsidiary
for failing to report potential problems with its Davis-Besse
nuclear powerplant.
The fine eclipsed the $5.45-million
civil penalty assessed against the Akron, Ohio-based utility
last April. The latest fine includes $4.35 million to be divided
among several agencies and charities for community goodwill
projects. FirstEnergy has 60 days to pay the fine.
In February 2002, inspectors at
Davis-Besse, Oak Harbor, Ohio, found a 4 x 7-in. cavity all
the way through the 6-in. carbon-steel reactor pressure-vessel
head of the plant’s single 925-MW pressurized-water-reactor.
Only a 0.3-in. stainless-steel liner remained to hold the
2,200-psi pressure in the vessel (ENR 4/8/02 p. 10). FirstEnergy
eventually spent $605 million on repairs, which included replacing
the head. The unit was shut down until March 2004.
Ken Schneider, FirstEnergy spokesman,
notes the utility made many changes at the plant and corporate
levels to guard against a recurrence of the problems. “We
have a new management team at the plant,” he says. “We
have more executive team staffing at the corporate level to
improve oversight [at the plant], including numerous people
with strong nuclear experience.”
The company agreed to cooperate
with the Dept. of Justice as it pursues criminal indictments
against three former FirstEnergy Davis-Besse staffers: Andrew
J. Siemaszko, a former systems engineer; David C. Geisen,
a former engineering manager; and Rodney M. Cook, an outside
contractor-consultant at the plant. Siemaszko and Geisen were
indicted on five counts each, while Cook was indicted on four.
They each face up to five years in prison and a fine of up
to $250,000. The three were involved in mishandling the reporting
of the reactor head problems.