Fresh
Start. With Gulf Coast devastated, critics are
calling for Entergy to consider redesigning its system.
The severity of the
hurricane damage to Entergy Corp.s Gulf Coast transmission
system has left industry observers wondering how the New Orleans-based
utility will rebuild the system. Company officials say the
first order of business is to get the existing infrastructure
back up and providing electricity to the 180,000 customers
now without power. But industry sources say that the system
Entergy had is not the one it should rebuild.
Hurricane Rita knocked out all
Entergy transmission lines between Lafayette, La., and the
Trinity River in East Texas371 substations and 334 transmission
lines, all told. At ENR press time on Oct. 4, the company
still had 25 spans and 20 substations out of service from
damage caused earlier by Katrina.
Industry observers say Entergys
transmission system is archaic, poorly designed and far too
constrained. It was designed and built to handle native load
and critics say Entergy has not upgraded it to accommodate
new, more efficient powerplants built by independent power
producers. "We find Entergys transmission system
to have artificial barriers to a vibrant wholesale market,"
says Marvin Carraway, secretary of the Mississippi Delta Energy
Agency, a joint-action agency composed of two municipal utilities.
The only upgrades since the 1940s were limited improvements
following the ice storm of 1994, he says. "Trying to
move economical power resources to customers in Mississippi
is a tough proposition. You run into transmission constraints
at every turn," Carraway says.
Upgrades Needed
A study commissioned by the Louisiana Public Service Commission
outlined upgrades that the Entergy system needed in that state.
"It completed the reliability upgrades, but it has been
slow to move on the following economic upgrades," says
an industry source. The upgrades included new lines and other
infrastructure to add 700 MW of transmission capacity near
New Orleans. Half the upgrades were completed when Hurricane
Katrina hit, an Entergy spokesman says. In Texas, the company
has added two 138-kV lines since 2004.
Hurricane Rita knocked out the
only interconnection between Entergys eastern and western
service territories, leaving Texas without enough power. It
took a week to connect and energize an alternate 500-kV line
that runs 250 miles from Arkansas to Texas.
Independent power producers have
been fighting Entergy over transmission upgrades for years.
Some have given up and sold their plants for a fraction of
their construction costs. One source calls it "predatory
behavior." Citing its "singular goal [of restoring
power] as safely and as quickly as possible," Entergy
declined to respond to the criticism.
"A redesign of the system
takes years to implement. We cant simply string up new
line with additional capacity without considering how it would
affect the system," says Mike Twomey, Entergy vice president
of regulatory affairs in Louisiana.
Beyond that, the company must look
at who will pay for the upgrades, says an analyst. Utilities
are unlikely to make an investment unless they know how they
will recover their costs, and state regulators must approve
cost recovery from customers, he says.
In Louisiana, that pos-sibility
already has raised eyebrows. Public Service Commissioner Foster
Campbell says he will not vote for a rate increase to cover
the storm recovery costs of a company that has $28 billion
in assets and $10 billion in annual revenue. "Im
not about to be stampeded into feeling sorry for Entergy,"
he says.