Bottleneck. Restoring
power is key to resuming refinery operations on the Gulf
Coast. (Photo by Michael Goodman for ENR)
Raked by two monster
hurricanes in less than four weeks, the oil industry in the
Gulf of Mexico has "shut in" all offshore oil production
and more than three-quarters of its gas production. Widespread
refinery closures from both Katrina and Rita have pinched
fuel supply, driving gasoline and diesel prices to stratospheric
levels. Washington has responded by introducing legislation
to promote construction of the first new refineries in the
U.S. in nearly 30 years. In the states hit by the two storms,
oil companies and electric utilities withheld cost estimates
pending full assessment of the damage.
Some 3.5-million barrels per day
of refining capacity remained offline due to Rita on Sept.
27, according to the U.S. Minerals Management Service. Another
879,000 bbl per day of refining capacity from three Louisiana
plants and one Mississippi facility remain out of service
from Katrina. They include Chevrons Pascagoula, Miss.,
refinery; ConocoPhillips Alliance plant in Belle Chasse,
La.; ExxonMobil/PDVSAs Chalmette, La., facility; and
Murphy Oils Meraux, La., plant, reports Platts, which,
like ENR, is a unit of the McGraw-Hill Cos.
All seven refineries in the Lake Charles, La.,-Port Arthur, Texas, region–the area hardest hit by Rita–remain off-line, as does 1.79 million bbl per day of refining capacity in the Houston/Texas City area, down from 2.29 million, says the U.S. Dept. of Energy.
ConocoPhillips 239,000-bbl-per-day
refinery in Lake Charles suffered wind damage and is without
power, the company says. It has no timetable for restart.
San Antonio-based Valero Energy Corp. says its severely damaged
Port Arthur, Texas, refinery will restart in two weeks to
a month after repairs are made. And Royal Dutch/Shell plans
to restart its 333,700-bbl-per-day refinery in Deer Park,
Texas, within the next few days, a company spokesman said
Sept. 26.
The tenuous balance between supply
and demand has underscored the need for added refining capacity.
"Were running at utilization rates in the mid-90s
[%]," says Ron Chittim, senior refining associate with
the American Petroleum Institute, Washington, D.C. U.S. refineries
can process more than 17 million bbl per day, but the country
consumes 20 million bbl per day. "The supply-demand balance
is pretty tight," Chittim notes.
On Sept. 26, Rep. Joe Barton (R-Texas),
chairman of the House Energy Committee, introduced a bill
to reform siting procedures for new refineries and promote
construction through a number of other means. Noting that
about 47% of U.S. refining capacity is concentrated in the
Gulf of Mexico, Barton said, "If there is a silver lining
in this tragic situation, it may be that our country understands
how fragile...our energy infrastructure is."
The bill would make DOE the lead
agency for refinery siting and permitting, while authorizing
it to provide financial assistance to states to review applications
for siting, construction, expansion and/or operation. The
committee is expected to discuss the bill this week.
Oil and gas producers are continuing
to tally the damage from Ritas rampage. Chevron suffered
the biggest loss when its Typhoon tension-leg platform was
severed from its moorings in 2,679 ft. of water in the Green
Canyon area, approximately 165 miles south-southwest of New
Orleans. The platform has been secured, but is not producing.
Three jack-up rigs owned by the
Rowan Cos. Inc., Houston, went adrift but were later found.
The firm was unable to account for a fourth. Two Diamond Offshore
Drilling Inc. semisubmersible rigs broke from their moorings
and grounded 100 miles away. GlobalSantaFe Corp., Houston,
also reported as missing two jack-up rigs valued at $22.2-million.
A preliminary count by Pickering Energy Partners Inc., a Houston-based
analyst, had four of the Gulfs 92 jack-ups "likely
destroyed" and seven of the 36 floaters loose from moorings.
Sabine Pipe Lines Henry Hub
in Vermilion Parish, La., declared force majeure and has remained
closed since Sept. 23. The Henry Hub, which connects with
nine interstate and four intrastate pipelines, is the pricing
point for natural-gas futures traded on the New York Mercantile
Exchange. ChevonTexaco-owned Sabine reported on Sept. 26 that
it was investigating gas leaks close to the Henry Hub.
In Texas, Louisiana and Arkansas,
1.8 million customers lost power after Hurricane Rita came
onshore. But the structural damage to most of the affected
companies was minimal, with the exception of New Orleans-based
Entergy Corp.
Entergys transmission grid
suffered more from Rita than Katrina, a company spokeswoman
says. At least 301 transmission-line structures and 301 substations
are out of service from damage caused by Rita. All transmission
lines to Entergys major industrial loads, which include
the seven refineries in the Lake Charles/Port Arthur area,
have extensive damage.
Citgo crews are gearing up to restart
a 325,000-bbl-per-day refinery in Lake Charles once power
is on, a spokesman says. "Were not sure when well
have power to begin to restart" he says. Transmission
lines serving the Louisiana Offshore Oil Ports Fourchon
booster station and the Henry Hub gas pipeline interconnection
also are out.
The 500-kV bulk grid interconnect
with Entergys generating capacity in the eastern portion
of its service territory must be restored before service can
be restored to the refineries and other customers in its western
region, the spokeswoman says. With 12 of the 14 generating
units, totaling 3,505 MW, in the western region out, Entergy
on Sept. 26 began rolling outages to its customers in suburban
Houston. "Entergy expects a long and difficult restoration
in the aftermath of the extensive damage caused by Hurricane
Rita," the spokeswoman says.
Entergy had 766,000 customers who
lost power from Rita, compared to 1.1 billion from Katrina.
Entergy estimates it will cost $1 billion to repair and replace
its infrastructure damaged by Katrina. No estimates are available
for Rita.
Officials said Entergy New Orleans,
the operating company that was the most damaged by Katrina,
faces up to $475 million in infrastructure repairs. The subsidiary
filed for bankruptcy on Sept. 25. "We took this action
after careful review of the various options available to preserve
Entergy New Orleans business over the near and long
term," says Dan Packer, CEO of Entergy New Orleans.
The bankruptcy court approved $100
million of loans to Entergy New Orleans to meet its near-term
obligations, which include efforts to repair infrastructure.