Replacement of a
piece of major equipment can take a big bite out of a powerplants
revenue, as the plant must be offline for the work to be done.
But a Midwest utility completed demolition and replacement
of one electrostatic precipitator in 10 weeks this spring
and plans to repeat the operation next year.
"The key driver for (replacing)
the precipitators was the physical degradation from 35 years
of operating experience," says Terry Ward, project manager
for Cincinnati-based Cinergy Corp., the parent of PSI Energy
Inc., which owns and operates Cayuga Generating Station, Cayuga,
Ind. Ward anticipates stricter federal or state opacity regulations.
The new precipitators remove 99% of particulate matter and
exceed state permit opacity requirements by 50%, he says.
Moving
Day. Roll-in of Unit 1 precipitator (above) released
crew to start assembly of Unit 2s (top right). (Photos
Courtesy of Cinergy Corp.)
PSI operates two 535-MW coal-fired
boilers at Cayuga. In early 2003, Cinergy took bids for the
precipitators. Wheelabrator Air Pollution Control Inc., Pittsburgh,
won the lump-sum contract to replace the equipment during
the plants scheduled spring maintenance outage. The
owner will not divulge costs.
"Weve done it a number
of times," says Lou Rettura, Wheelabrator project manager.
"We used a technique where we assembled in a separate
location. It limits the downtime." Under Wheelabrators
plan, workers construct each precipitators two boxes
in a staging area, then perform functional tests on components
before mounting the boxes on huge dollies and rolling them
into position.
Ward liked the approach. "Repairing
or rebuilding the current ESPs would have required significantly
longer outages for two of our low-cost baseload units,"
he says. Richard Jerch, project manager for Chicago-based
Sargent & Lundy, Cinergys architect-engineer, says
he had heard of the technique, but had not seen it before.
"Roll-in seemed a pretty attractive way," he says.
"Its becoming more common as older units require
more retrofit. There must be space available (for assembly)
with relatively clear space to roll in."
Last summer Wheelabrator began
assembly of the precipitator for Unit 1 on temporary steel
baseplates in a parking lot. The 40 x 80-ft footprint of the
new boxes is larger than the old 26 x 83-ft footprint, so
workers in 2003 had added caissons for an extended foundation.
The roll-in path was prepared by moving a large condensate
storage tank and placing crushed limestone and some steel
plates to enable it to bear 2,000 lb per sq ft.
When the plants spring maintenance
outage began March 5, Wheelabrator demolished the existing
Unit 1 precipitator. Grand Ridge, Fla.-based subcontractor
Ducky Johnsons House Moving Inc. jacked the 100-ft-tall,
1,000-ton precipitator boxes onto 24 self-propelled modular
transporters, with eight swivel-steered wheels each. "We
did not have a direct shot into this precipitator location,"
says Jerch. "We had to make some 90° turns."
Roll-in of the first box began on March 27 and was completed
the next day. The second box was in place March 30. "We
actually had clearances on the front and back side of 1Ú2
in.," says Wheelabrators Rettura. "It was
as slick as putting a plug in a receptacle."
The first precipitators collecting
electrodes were damaged in transit and had to be refabricated.
The problem delayed Wheelabrators schedule, but the
contractor was ready when the outage began, says Ward. As
the powerplant started up again in May, Wheelabrator began
assembling the Unit 2 precipitator boxes on the other side
of the plant in preparation for next Marchs outage.
There have been no significant cost or schedule changes, Ward
says.