Accessible.
Large tunnel gives access for maintenance. (Photo courtesy
of UNC Chapel Hill Construction Management)
The University of North
Carolina at Chapel Hill is expanding its steam plants
capacity 53% with funds from a 2001 bond issue to build up the
south campus to accommodate growing enrollment. Contractors
now are making progress on a mile-long utility tunnel and steam
plant that by fall 2006 will deliver an additional 410,000 lb
of steam per hour for five new dormitories to house 1,000 students
and a new information technology building.
Construction is proceeding in three
phases, including one for the utility plant and two for separate
tunnels connecting to the plant. Together, construction costs
total $84 million. A joint venture of Whitaker Construction
and Associated Brigham Contractors (ABC), both of Brigham
City, Utah, expects to complete its lump-sum contract for
3,000 ft of tunnel in September. Clancy and Theys and Pipeline
Utilities, both of Raleigh, N.C., are joint-venturing on a
1,300-ft-long tunnel.
Challenges include the hilly landscape,
the 30-ft trench depth and a campus hospital that needs a
long lead time before contractors may disrupt service to relocate
existing lines.
"Weve done a lot of
traffic planning and construction phasing to ensure that the
hospitals operations arent interrupted,"
says Scott Clark, principal in charge for Fort Worth, Texas-based
Carter & Burgess, the projects engineer. He adds
that the plant and tunnel were situated near the hospital
to enhance the facilitys system reliability.
Excavating in the hilly terrain
has been a special challenge. "Weve had to blast
out granite to make way for the tunnel, and work around existing
utilities," says Judd Hamson, project manager for ABC
and Whitaker.
To shore up the trench and prep
the site for pouring the concrete floors and walls, contractors
are using 100 8 x 20-ft trench shields supplied by Burlington,
N.C.-based Coble Trench Safety, each of which weighs about
10,000 lb. "Many tunnels like these are sheet-piled,"
says Hamson. "But with this approach weve been
able to handle the excavation in a safer, faster manner."
Once finished, the tunnel will
house seven pipes, including two 30-in. chilled water lines,
five low-pressure and high-pressure steam pipes, a 2-in. trap
line and two 10-in. pumped condensate lines.
Calling the tunnel-utility plant
combination "a cost-effective way to deliver power and
service the campus infrastructure," Cameron Smith, UNC
Chapel Hill's construction manager, says maintenance crews
will access utilities through the underground structures
9 x 11-ft walkway. The top of the tunnel will be buried 8
to 10 ft deep, to allow future utilities to be placed above,
he adds.
Completing the project is
a utility plant constructed of cast-in-place concrete basement
and topped off by a structural steel skeleton. When Frank
Lill & Son, Rochester, N.Y., finishes it in the fall of
2006, the plant will house two water tube boilers that are
connected to the tunnel system.