Wisconsin Energy
Corp. and Bechtel Power Corp. have worked out an arrangement
to keep a construction team in place on a $2.2-billion powerplant
project while legal issues that delayed the jobs start
are resolved in court.
Bechtel was to receive a notice
to proceed on a two-unit, 1,200-MW coal-fired plant in Oak
Creek on March 1, with construction to begin May 1. The project,
first awarded in April 2004 under a lump-sum contract, was
delayed in November. Opponents objected partly because there
is no state law requiring the state public service commission
to consider lower-cost power options.
A circuit court judge vacated the
building permit issued by the commission and remanded the
case back to it. But the utility petitioned the Wisconsin
Supreme Court to hear an appeal. It agreed, and should rule
by June 30. The utility has asked for an expedited ruling
by mid-May.
Under an amendment to the EPC contract,
the notice to proceed was moved to July 1. But the utility
must now pay Bechtel delay-related escalation costs of $150,000
a day from March 15 to April 30, and $200,000 a day from May
1 through June 30. "Were paying to keep the subcontractors
available until July 1," says a Wisconsin Energy spokesman.
The extra cost will only be paid if the project proceeds.
Bechtel projected its delay-related
expenses on a daily basis but "the amount does not cover
our costs," says a Bechtel official. The agreed amount
represents 2.6% annual escalation, but the true costs are
much higher. Escalation is at least double a 3% annual escalation
rate, with boiler prices up 15% last year, says an industry
official.
Calpine Corp. is among the
opponents of the plants building permit, claiming that
lower-cost options exist. Calpine has a gas-fired powerplant
permitted in Wisconsin that would provide power at $600 per
installed kW, far below the $2,000 installed kW cost of the
Wisconsin Energy plant.