Needs Work. Salem/Hope
Creek has had troubled operation. (Photo courtesy of PSE&G
Nuclear)
The owners of three
large nuclear units in New Jersey plan to spend more than $800
million over the next five years on engineering and construction
to correct nagging problems at the facilities, upgrade the units,
and improve their reliability and profitability.
Work on the 1,049-MW Hope Creek
unit began this month. The two-unit, 2,212-MW Salem nuclear
station will also be improved in the program. Both plants
share a site on the lower Delaware River, in Salem County,
N.J.
The Salem units, owned by PSEG
Nuclear and Exelon Corp., are pressurized-water reactors that
started commercial operation in 1977 and 1981, respectively.
Hope Creek, owned by PSEGN, is a boiling-water reactor that
came online in 1986. PSEGN, the operator, in recent years
has been criticized for an alleged tendency to put off maintenance
work.
Next year, PSEGN will replace the
reactor vessel heads on both of the Salem units. In 2008 it
will replace the steam generator on Salem Unit 2. Unit 1's
steam generator was replaced in the mid-1990s. PSEGN also
plans to increase the total output of the Salem/Hope Creek
complex by about 200 MW through a variety of unspecified measures.
Hope Creek will receive a 125-MW increase in 2006. Salem Unit
2s 15-MW increase will be tied to its new steam generator.
PSEGN will spend more than $160
million in 2005 on its overall effort to rehabilitate and
improve the three plants, plus between $130 million and $140
million per year in 2006, 2007 and 2008, before ramping down
to about $80 million in 2009. Exelons contribution will
push the total over $800 million. The work will be done by
"a combination of in-house resources, consultants and
contractors," says a spokesman.
advertisement
...
The Oct. 10 rupture of an 8-in.-dia
steam pipe in the Hope Creek plants turbine building
led to the manual shutdown of the plant. Chris Bakken, PSEGN
chief nuclear officer, says Hope Creek will remain offline
and transition into a previously planned refueling outage
that had been scheduled to begin Oct. 28. Before restarting
Hope Creek in December, the utility will address the adequacy
of operator response and "the significant equipment issues"
the Oct. 10 event highlighted, says Bakken.
Among other things, PSEG is expected
to make extensive improvements to the plants control-rod
drive mechanisms, with which operators control the reactor.
Plans also call for upgrading the plants troubled nuclear
instrumentation system.
Next spring, PSEGN plans to begin
a major rehabilitation of the circulating-water system, which
"has been plagued with debris and silt that has clogged
up the heat exchangers," says David Lochbaum, a nuclear
safety engineer at the Union of Concerned Scientists. The
work will continue into 2006.
• December 28 Issue
• December 7 Ad Close
Stay top of mind in print and online to the owners, engineers and contractors you need to reach.
Get connected today by contacting your account manager, call: 800-458-3842 or