TOWER
TOTER Helicopters are setting 40% of Path 15s
structures.
Relief is in sight
for one notorious electric-transmission bottleneck. Steel-lattice
towers and poles are rising this month in rugged, remote terrain
for a $306-million expansion of Path 15 in central California.
When energized this fall, a new
500-kv line will increase Path 15s capacity from 3,900
Mw to 5,400 Mw, expediting electricity transfers along an
84-mile stretch where three lines now narrow to two. The upgrade
is led by an innovative public-private partnership of Trans-Elect
Inc., Reston, Va., which is providing most of the financing;
Pacific Gas & Electric Inc., a San Francisco-based utility;
and the Western Area Power Administration, a Salt Lake City-based
U.S. Dept. of Energy agency (ENR 9/29/03 p. 17).
Located some 1,500 to 2,000 ft
west of two existing lines in the San Joaquin Valley, the
upgrades centerpiece will be an 84-mile line extending
from PG&Es Los Banos substation, near Los Banos
in Merced County, southeast to its Gates substation near Coalinga
in Fresno County. Maslonka & Associates Inc., the projects
design-build contractor, is erecting 246 steel-lattice towers
and 98 steel poles and stringing the transmission line.
"This is probably some of
the most difficult construction that weve run into,"
says Doug Larson, WAPA civil engineering manager. Mesa, Ariz.-based
Maslonka has built or improved over 100 miles of access roads.
Access is particularly challenging in one 12-mile leg characterized
by steep, eroded hills. A typical spur for a tower site might
be 20 ft wide with a 300-ft sheer drop, says Larson.
advertisement
...
Maslonka fast-tracked construction,
ordering the 100-ft to 160-ft-tall towers before completing
foundation design. For optimum production, two concrete batch
plants leapfrog down the line, one supplying foundation pours
while the other moves. Within 90 days of concrete placement,
"were flying steel towers in with the helicopter,"
reports Martin J. Maslonka, president.
All steel poles and 40% of the
towers are too heavy to be flown in. They are being erected
instead by a half-dozen all-terrain cranes with up to 200-ton
capacity, aided by 25 smaller cranes and winch-equipped bulldozers,
Maslonka says.
In the northern five to six miles
of the route, WAPA specified steel poles instead of towers
to protect endangered wildlife species. Ranging in height
from 127 ft to 207 ft, the poles are fitted with 17-in.-tall
black polyethylene cones to prevent birds of prey from perching
and hunting, says Ross Clark, WAPA electrical engineering
manager.
For the 500-kv line, the agency
selected standard aluminum conductor, steel-reinforced, in
a triangular bundle. "On a project of this size, you
want to use proven products that you know are going to last,"
says Clark.
Kansas City-based Burns & McDonnell
is upgrading PG&Es Gates and Los Banos substations.
Burns & McDonnell is installing two 500-kv circuit breakers
at Gates and 250 megavars of 230-kv shunt capacitors at Gates
and Los Banos and modifying Gates 500-kv bus to a breaker-and-a-half
design.
PG&E crews are reconfiguring
and reinforcing two 230-kv lines "to avoid overloading
them in case outage occurs at peak load," says Kevin
Dasso, PG&E director of electrical engineering. Some 40
miles south of Gates, PG&E is augmenting foundations to
raise about 100 towers an average of 10 ft to 15 ft to offset
additional line sag expected from higher loads and higher
temperatures, says Dasso.