DYING BREED? Eight-unit,
4,096-Mw coal-fired Nanticoke plant is on the shutdown
list. (Photo courtesy of Ontario Power Generation)
Faced with a capacity
shortfall and fleets of dirty coal plants and aging nuclear
units, Ontario is planning to rebuild and dramatically expand
its electric infrastructure. The plan could soon make the
province North America's most active market for powerplant
construction and rehabilitation. Ontario's new Liberal government
is moving quickly to break the regulatory gridlock that has
paralyzed the power sector in Canada's most populous province
since a botched attempt to implement retail competition in
May 2002.
Ontario Energy Minister Dwight
Duncan says he will unveil a detailed electric-industry restructuring
plan later this spring aimed at increasing power supplies
and encouraging conservation. Duncan says he expects up to
$30 billion of public and private funds to be invested over
the next few years in new generating sources, nuclear-plant
rehabilitation and new high-voltage transmission lines. "We're
looking at a massive investment of capital going forward....It
could well be one of the largest peacetime investments in
the history of this country," he says.
Details of the plan still need
to be worked out but recent government reports suggest that
key elements will include rehabilitating one or more of province-owned
Ontario Power Generation's three mothballed units at its Pickering
nuclear station. Also on the table are encouraging the development
of new nuclear plants, probably through public-private partnerships,
and spurring the development of new gas-fired and renewable
generating capacity through long-term power-purchase agreements.
Ontario's Likely
Plan
Spring solicitation for 2,500 Mw of conventional, 300
Mw of "green" power
Target 5% of total capacity to be green by 2007, reaching
10% by 2010
Restart mothballed nuclear units; encourage development
of new nuclear plants
Build new transmission lines able to import at least 2,000
Mw
Dramatically improve efficiency through
demand-side management
Source: Government and other sources
The capacity-supply situation in
Ontario is serious and, with Duncan's new government pledging
to shut down 7,500 Mw of coal-fired plants by 2007, faces
increasing challenges. According to Ontario's Independent
Electricity Market Operator, the reserve margin is less than
10%, and on the hottest and coldest dayswhen demand
rises past 25,000 Mwthe province imports up to 3,000
Mw from Quebec, New York and other neighbors to keep the lights
on.
Only two plants totaling less than
700 Mwbarely enough to keep pace with load growthare
under construction in Ontario and scheduled to begin operation
later this year.
The Liberal government in the past
three months has taken several steps, beginning with a planned
April 1 increase in retail rates for smaller customers to
more accurately reflect wholesale prices, and to encourage
conservation. It also announced plans to solicit 2,500 Mw
of new generating capacity that could come on line quickly
to replace some of the old coal plants that it plans to take
off line by 2007. A parallel solicitation for 300 Mw of wind
farms and other "green" capacity also is planned.
In a newly issued report by the
Duncan-appointed OPG Review Committee, panel Chairman John
Manley called for a full-court press, warning, "Ontario
could be facing electricity shortages by 2007." Among
many other things, the panel called for a $450-million rehabilitation
at mothballed 515-Mw Pickering A nuclear Unit 1. But Manly
says similar work on Units 2 and 3 should not proceed without
"clear evidence of success" on the restart of Unit
1.
The committee also said the province
"must begin planning now to supplement and ultimately
replace its aging nuclear assets with new and better generations
of nuclear technology." Atomic Energy of Canada Ltd.,
a Canadian-government entity that develops "Canada Deuterium
Uranium," recently proposed building as many as eight
700-Mw CANDU nuclear units in Ontario.