BELEWS
PROJECT Largest SCR job in U.S. required big boom
and jib crane.
A North Carolina
utility is spending nearly $2 billion to clean its emissions.
A federally driven $450-million selective catalytic reduction
project, the largest in the U.S., is now nearing completion
and another $1.5-billion state-driven sulfur dioxide reduction
program is just ramping up.
Duke Power, Charlotte, N.C., has
started engineering on a $1.5-billion program designed to
reduce nitrogen oxide emissions by 30% and sulfur dioxide
emissions by 70% at its seven North Carolina coal-fired powerplants.
The effort was driven by state clean air legislation passed
last year that also freezes rates for five years. The program
will be amortized through existing rates and costs recouped
in a flexible manner to keep earnings stable. "Well
be scrubbing 12 units and likely do selective noncatalytic
reductions on 24 units," says Mary Katherine Green, Duke
spokesperson.
advertisement
...
Persistent smog, acid rain and
air quality problems in the western part of the state drove
the cleanup. On hot, sunny days NOx combines with organic
chemicals in the air to form ground-level ozone, a component
of smog. Sulfur dioxide also contributes to smog and acid
rain. SCRs channel hot flue gasses and injected anhydrous
ammonia through ceramic honeycombed bricks to convert more
than 80% NOx into nitrogen and water. SNCRs inject ammonia
into the gas stream, converting NOx to a lesser degree, or
about 25%. Wet scrubbers bubble flue gas through molten limestone
to transform SO2 into gypsum and water. "We used SCRs
where the largest emissions were and where we could do the
engineering," says Thomas C. Williams, Duke communications
manager. "SNCRs are more cost-effective on smaller and
older units and scrubbers will be used on all large plants."
Duke will perform SNCR engineering
work in-house but Alstom Power, Knoxville, Tenn., will provide
the engineering, equipment scoping and site testing for the
scrubber work. Plants involved include: the five-unit Allen
station, unit number five at the Cliffside station, the four
units at the Marshall station and the two units at Belews
Creek station. Contracts totaling about $300 million to $400
million will be let in the next six months for the Marshall
work. Work at all plants must be completed by 2013.
MARSHALL
PLAN Scrubber backfit, to be let soon, could cost
uptp $400 million.
Duke is wrapping up about $550
million in federally driven SCR work at two plants. Unit five
at Cliffside, a 760-Mw plant, is finished and phase two at
Belews Creek, a two-unit, 2,400-Mw plant, is nearing a June
2004 completion. Belews Creek is Dukes largest coal-burning
plant, consuming up to 19,000 tons of coal per day. To comply
with federal clean air standards, Duke is reducing NOx emissions
by 80% there.
Charlotte, N.C.-based Duke/Fluor
Daniel heads the three-year engineer-procure-construct deal
at Belews. Because of a tight site, the SCRs had to
be built over existing boiler buildings and precipitators,
resulting in 300-ft-tall towers that were structurally integrated
into the plant. "The SCR creates a huge sail so we had
to drill and grout several hundred rock anchors about 30 ft
to 40 ft deep in bedrock," says Harold L. Backman, Duke
project director. Over 7,000 tons of structural steel and
44,500 linear ft of piping were used on unit one. It has been
operating at full capacity since August.
The 29-year-old plant provides
power to more than 2 million homes in the Carolinas. It cost
about $357 million to build. Duke also is replacing boiler
tubing and controls and completing a precipitator refurbishment.
Because of the project size and location of the SCRs, a Manitowoc
21000 crane with a 420-ft boom and jib was needed to lift
equipment and ductwork fabricated on the ground. The rig was
last used in the cleanup at the World Trade Center.
"This is the largest SCR project
in the U.S. owing to the electric output of the station and
the tight site and the capacity for four layers of catalysts,"
says Ray Hollins, general manager of the joint venture. "We
upsized the four induced draft and four forced draft fans
and motors and added variable frequency drive to the ID fans
to better control speed." He notes they also replaced
the air heaters to increase boiler efficiency. That required
significant interior plant demolition and increased structural
steel on the SCR and building to support the heaters. The
SCR currently uses only two levels of catalysts but two more
levels are available for future management.
Duke/Fluor Daniel also completed
the Cliffside work. In July officials announced the venture
would disband because of a decline in powerplant construction.
The transition could take two years.
• December 28 Issue
• December 7 Ad Close
Stay top of mind in print and online to the owners, engineers and contractors you need to reach.
Get connected today by contacting your account manager, call: 800-458-3842 or