A
four-year-long intercontinental odyssey culminates this week
in replacement of the largest steam generators in a U.S. nuclear
powerplant. The generators were fabricated in Italy, shipped
via the Panama Canal to the head of the Gulf of California,
offloaded in Mexico and conveyed via country roads through
northern Mexico and southern Arizona to the Palo Verde generating
station by workers and supervisors speaking at least four
different languages. The operation will be repeated in 2005
and again in 2007.
CHANGE
OUT New steam generators are a tight squeeze. (Photo
courtesy of Arizona Public Service Co.)
The replacement
operation is occurring during a refueling and maintenance
outage that began Sept. 27 and is due to be finished in mid-December.
The two steam generators in 1,270-Mw Palo Verde Unit 2 were
moved out of the containment building Oct. 23 and 25. Their
replacements were moved in Oct. 27 and 29.
Arizona Public
Service Co., Phoenix, launched the $230-million operation
to design, fabricate, transport and install the new units
with a 1999 fabrication order placed with Ansaldo Energia
(now Ansaldo Comozzi), Milan, Italy. In 1999, APS also awarded
a $4-million fixed-price contract to Michael Baker Jr. Inc.,
Moon Township, Pa., to provide engineering, permitting and
construction oversight services for the transport operation.
The new steam generators were
designed somewhat larger than the old ones, which entered
commercial service in 1986, because of a need for more heat-transfer
area. The Inconel 600 material of the old generators
11,012 tubes was not holding up. "We found this material
starts to crack. Weve been losing megawatts for a couple
of years now," reducing generation capacity by about
2%, says Ron Pontas, APS installation project manager. The
new generators have 12,580 Inconel 690 tubes. Pontas says
the new material has been on the market for about a dozen
years, and appears to be more resistant to corrosion. But
because its heat-transfer coefficient is lower, "it needs
a longer tube bundle to make up," he adds. So the new
generators are 3.5 ft taller, with a girth 14 in. greater
in the evaporator section, than the old ones to accommodate
the added length and tube bundles.
advertisement
...
Ansaldo completed fabrication
and shipped the generators in August 2002, using transport
contractor Fagioli S.p.A., Parma, Italy. After a 35-day voyage
by heavy-lift ship, they arrived in the deepwater port of
Guaymas, Mexico, in late September. There they were transshipped
to a barge for final delivery to Puerto Peñasco, at
the head of the Gulf of California.
The original generators came through
Peñasco two decades ago, but development since then
has reduced the space necessary for the new ones. So Michael
Baker installed a sheetpile dock 7 miles away and dredged
a 500-ft channel an average of 3 to 5 ft deep to accommodate
the barges 15-ft draft and 20-m width. Docking originally
was scheduled for June, when humid weather and longer high-tides
would make offloading easier. But a delay in fabrication pushed
delivery out three months, and antinuclear protesters occupied
the docking site for four days before they were removed, costing
another months delay because of a lost tide window,
says Colin Olness, Bakers project manager. The delays
didnt affect the outage dates, but did mean the offloading
would occur in a less-than-optimal season. In addition, "We
lost a lot of the dredging that we were maintaining,"
says Olness.
On a calm day, Nov. 3, 2002, the
generators, already sitting on "self-propelled modular
transporters" powered by four diesel-driven hydraulic
power packs, rolled deliberately off the barge to a staging
area. "They're similar to the units that move the space
shuttle," says Olness. In the staging area they were
configured for road travel with a full complement of 208 tires
on 26 axles. One week later, the first generator set out on
the final 200-mile leg of the trip to Palo Verde, 40 west
of Phoenix. Completing that leg would take two more months.
The route had been prepared to
receive the 1,087-ton loaded rigs. Protection was required
for 426 structures, including wood culverts, concrete culverts,
bridges, a canal and railroad crossings. Exhaustive research
exhumed records going back to the 1930s, allowing Baker to
assess the load-carrying capacity of roadways and bridges
and devise strategies to improve them. But many records simply
werent available. "In Mexico, we just shored or
overbridged on all of them," says Olness.
Overbridging consisted of placing
an I-beam, 50 ft long and 10 ft wide, over existing bridges
deemed to need the protection. Shoring was required as well
to prepare for the load. Contractor Precision Heavy Haul (HQ
tk) leapfrogged the steam generators, which were moving at
an average speed below 5 mph, placing the overbridging ahead,
then moving it to the next bridge after the load had passed.
One of the most challenging obstacles
was Interstate 8 in Gila Bend, Ariz. "There is a bridge
on I-8 that crosses abandoned Phelps Dodge railroad tracks,"
says Olness. "We negotiated an agreement to use the railroad
right-of-way, then tore out the unused track and excavated
underneath the Interstate bridge until we achieved the 30-ft
clearance we needed."
The first generator, 75 ft long
and 24 ft dia, was moved across the U.S.-Mexico border at
Lukeville, Ariz., and parked. The transport team picked up
the second generator and delivered it on Jan. 2 to Palo Verde,
then returned to the border to bring up the second generator.
The transporting operation was complete Jan. 21. Actual time
in transit for each generator was 17 days, but the schedule
was extended because of holiday breaks at Thanksgiving and
Christmas and the staged movement of the first generator,
which was not part of the original plan, says Olness.
In March 2003, San Francisco-based
Bechtel began field work to prepare the steam generators for
installation. Already on the job since 1999 doing design packages
for the work, the contractor in March established facilities,
prefabricated piping and components, prepared the generators
joints for welding, qualified welders and performed training
on mockups. In August, construction began on a runway to feed
the old generators out of the 24-ft-dia hatch and to feed
the new ones in. The size of the hatch was one factor that
limited the growth in the design size of the new generators.
Just 2 in. of clearance was left when the evaporator sections
girth was expanded to accommodate the added tube bundles.
The workforce in the last week
of October was 733, close to its peak for the project, says
a Bechtel official. Except for an incident when an auxiliary
crane blew a seal, costing "a couple of days overall,"
the work has gone without a hitch, he says. Bechtel is planning
its work with the goal of completing demobilization Dec. 19,
before the Christmas holiday.
• December 28 Issue
• December 7 Ad Close
Stay top of mind in print and online to the owners, engineers and contractors you need to reach.
Get connected today by contacting your account manager, call: 800-458-3842 or