Blackout is expected to open spigot for new transmission and state-of-the-art technology
FIXING
THE GRID (Photo courtesy of Southern Co).
Whatever the official
investigations eventually conclude, enhanced investment in
the North American transmission system will have to be a part
of the answer to the Aug. 14 blackout. Despite differing views
on solutions, most sources agree the electrical system needs
development because it has been cash-starved and fervent local
opposition often has blocked efforts to expand it.
Between $30 billion and $60 billion
of investment is required to bring the grid up to the state
of the art and open its congested arteries, essentially doubling
the asset base, says Elliot Roseman, principal with ICF Consulting,
Fairfax, Va.
Investment in the grid has trended
steadily downward since 1989, in disturbing contrast to the
trend in load growth and investment in generation construction.
"In the last 20 years, theres been a negative investment
in transmission of $100 million per year," says Peter
Rigby, director of utilities, energy and project finance at
Standard & Poors, New York City. S&P, like ENR, is
a division of the McGraw-Hill Companies.
Industry groups, politicians, regulators
and others long have raised the call for new investment in
transmission. But a combination of siting and financial obstacles
has blocked effective action, says Roseman. A "balkanized"
permitting process hamstrings line siting, he says.
The process, unchanged since the
time when vertically integrated utilities planned generation
and transmission for their own largely protected service areas,
is ill-suited to todays market, where huge blocks of
power wheel across several states. "Any line 230-kv or
above should have a joint basis, maybe under a regional transmission
organization, [the National Association of Regulatory Utility
Commissioners, the Western Governors Association] or
something else," he says.
COMMAND
AND CONTROLIndependent
system operator in New England blocked outage.
(Photo courtesy of ISO-New England)
Financial incentives for investors
in transmission projects also have been lacking. Equity funds,
pension funds, construction companies and operation and maintenance
companies might be willing to invest in new transmission if
they could obtain a stable profile of regulated returns, Roseman
argues. Rigby says states have allowed an average return on
transmission investment of 11.6%. But Trans-Elect Inc., Washington,
D.C., which privately owns and operates transmission systems,
considers 14.5 to 15% to be the acceptable range for private
investment in new construction, says Bob Mitchell, executive
vice president.
ISOs and RTOs can best assess where
the investment could do the most good for their regions, says
Roseman. Utilities without proper metering, data and monitoring
equipment will need technology upgrades, possibly in addition
to new or upgraded lines. Other technology promises to increase
the capacity of existing lines without additional construction
in the right-of-way. For example, a convertible static compensator
recently installed by the New York Power Authority at its
Marcy Substation uses solid-state power electronics to control
power flows, increase line capacity and improve reliability
(ENR 6/21/99 p. 14).
Mandatory standards for reliability
and interconnections would clear some of the fog from the
decision-making process, says Roseman. In the absence of mandatory
standards, some operators have run their systems close to
and even over their design limits, masking shortcomings in
the grid, he says. Making the standards mandatory would reveal
where the system is underpeforming.
The blackout has improved the odds
for passage of energy legislation in Congress. Provisions
to stimulate spending on transmission may be included.
A conference to reconcile the House
and Senate bills is expected to begin soon after Congress
returns from its August recess. The House-passed version has
several incentives for transmission infrastructure. The Senate
version has fewer.
The omnibus energy bill that the
House approved in April would allow transmission lines to
be written off in 15 years, compared with 20 years now, change
the provisions for gains utilities realize when they sell
transmission facilities to an RTO or independent transmission
company and have the Federal Energy Regulatory Commission
establish "incentive-based...rate treatments."
Edison Electric Institute, Washington,
D.C., says the last item involves higher rates of return than
now permitted. The Senate bill also has a provision on treatment
of transmission asset sales.
In addition, the House measure
would direct the Dept. of Energy to study "electric transmission
congestion." That could lead to the DOE Secretarys
designating "interstate congestion areas." FERC
then would be authorized to issue permits to build or modify
transmission facilities in those "congestion areas"
if a state is unable or unwilling to do so. It also would
allow acquisition of needed rights-of-way for such lines by
eminent domain proceedings in federal court.
Utility companies would love to
see the House provisions included in the final version. "While
there is clearly no single magic bullet to achieve this, we
believe strongly that House and Senate lawmakers have an unparalleled
opportunity to craft a final legislative product that contains
critically important steps to help ensure electric system
reliability and bolster transmission capacity," says
EEI President Thomas Kuhn.
NEW
DEAL Marcy substation is high-tech.
(Photo courtesy of NYPA)
"Clearly the Republicans are
looking at a broader bill, and maybe even some Democrats,
but there are some other Democrats that want to peel
off something to deal with the reliability issue,"
says Casey Dinges, the American Society of Civil Engineers
managing director for external affairs. He feels that in the
wake of the blackout, Congress must act on energy legislation.
But the Southeast has resisted
pressures to restructure for good reason, say utility owners
in the region. Electricity prices there are low and reliability
is high. Neither Atlanta-based Southern Co. nor Raleigh-based
Progress Energy is particularly interested in forming a regional
transmission organization, as FERC has urged. "Were
working on putting an agreement together, but there is no
timeline," says Todd Terrell, a Southern Co. spokesman.
Progress officials say the momentum for establishing an RTO
just isnt there any more.
Both companies are investing in
new transmission infrastructure. Southern Co. has spent $3.7
billion on transmission since 1999, including upgrading substations
and lines to higher voltage and 206 miles of new lines. It
plans to spend another $4.4 billion through 2006.
Georgia Transmission Co., which
builds for the utilities that co-own it, last year had serious
trouble building new lines. Several county governments banned
construction of new high-voltage lines for three years. The
Georgia Supreme Court overturned the ban in January. Still,
Georgia Transmission is finding it more and more difficult
to place lines to meet need and build in reliability, says
spokesman Craig Heighton. "The question is always, Who
says there is a need?" he says.
Georgia Transmission has a 99.997%
reliability rate in spite of the 47% increase in demand over
the past 10 years. "Were putting in millions of
dollars worth of infrastructure and its not for unneeded
systems," says Heighton.
Waukesha, Wis.-based American Transmission
Co.s Arrowhead-Weston 345-kv transmission proposal in
northwest Wisconsin has been one of the countrys most
famous examples of the difficulty facing new transmission
construction. The estimate for the 220-mile line jumped from
about $150 million to $396 million last November because of
cost escalation in the four years since the project was first
proposed and added costs to mitigate impacts on the environment
and the communities in the lines path (ENR 11/18/02
p. 7). An activist group has opposed construction, urging
instead the development of alternatives.
advertisement
...
For some, the solution lies in
returning to an older model. In a study for the American Public
Power Association published last November, Kiah E. Harris,
power supply planning engineer at Burns & McDonnell Engineering
Co., Kansas City, found that "the industry is moving
back to a world where traditional utilities are building generation
in many locations," thus avoiding the need for major
transmission additions.
"In todays situation,
the parties have no control over the transmission system and,
therefore, generation must be sited as close to load centers
as possible," he wrote. "A by-product of the FERC
[proposed standard market design] is that it will encourage
further reduction in the reliance on the transmission system
for firm deliveries."
Because of the "forced interest
in local generation, the transmission system is ever
more being relegated to nonfirm energy usage, and its expansion
is becoming less important on a system-wide basis," he
wrote. Far from prompting a new wave of transmission investment,
reliability concerns may lead instead to greater investment
in smaller powerplants to serve local loads. "Todays
uncertainty is telling many parties to take the smaller plant
size, site it local to the load so minimal transmission is
needed and forgo economies of scale," Harris wrote.