In a time when new
dams in environmentally conscious California are as rare as
hens teeth, the state is about to welcome a record-setter.
Twenty-seven miles north of San Diego, the tallest roller
compacted concrete dam in North America is headed for completion
this summer. Olivenhain Dam and Reservoir will wind up about
$2 million below its $200-million budget, says Jerry Reed,
project manager for the San Diego County Water Authority.
The 318-ft-tall,
2,552-ft-long concrete gravity dam is the centerpiece of SDCWAs
$827-million Emergency Storage Project. Scheduled for completion
in 2012, the ESP will comprise over 90,000 acre-ft of new
storage, 17 miles of pipelines, and five pump stations.
BEST
FACE Dam's design offsets seismic loading by altering
1:1 slope ratio for the 318-ft-tall structure's top quarter.
(Photo courtesy of Parsons-Harza)
The project will
give the region a six-month backup if an earthquake or other
emergency cuts imported water supplies, says Ken Steele, SDCWAs
principal civil engineer. The dam must function after a magnitude
7.2 earthquake, says Mike Rogers, resident design engineer
with Parsons Harza, the projects locally based joint
venture design consultant. Olivenhain Municipal Water District
is providing one-sixth of the dams funding and is entitled
to a sixth of the reservoirs 7.8-billion-gal capacity.
Cost and schedule
drove the selection of RCC. The thick, dry mix of rock, flyash,
water and cement generally costs about half of conventional
concrete and requires one third the construction time, says
Reed. As in road construction, RCC is placed by dump trucks
and spreaders and compacted by vibratory rollers.
Tapering from 250
ft wide at the base to 20 ft at the crest, the dam crosses
three valleys. Redding, Calif.-based Ladd and Associates excavated
about 700,000 cu yd of material. Excavation depths ranged
from 15 ft to 100 ft, with about 25 ft being typical, Rogers
says.
To improve a fault-related
depression at the left abutment, Kiewit Pacific Inc., general
contractor for the primary structure, placed 230,000 cu yd
of RCC for an 85-ft-tall shaping block below the base. And
to strengthen soft, permeable rock at the right abutment,
Kiewit placed 15,000 cu yd, creating a 25-ft-tall shaping
block.
The location offered
advantages as well as challenges. An abundant local supply
of granite made importing aggregate or fines unnecessary.
Kiewits crusher typically produced up to 1,300 tons
of aggregate per hour, says Mike Pauletto, area manager for
Kiewit Pacifics Vancouver, Wash office. Concrete was
conveyed to the batch plant and trucked to the dam, where
it was applied in 18-in. lifts by spreaders, then compacted
to 12 in. by 10-ton and 12-ton rollers.
Through extensive
testing, the project team won approval from the state Division
of Safety of Dams for a value-engineered, time-saving RCC
mix. Kiewit proposed modifying the formula designed by Harrisburg,
Penn.-based Gannett Fleming, reducing the cement content from
150 to 125 lbs per cu yd and increasing the flyash from 125
lbs to 185 lbs. The value engineered mix will achieve full
strength of 4,500 psi after one year, compared with 3,000
psi for the original mix, Rogers says.
In a key contribution,
the value engineered formula virtually eliminated a time-consuming
intermediate step in concrete placement. To add tensile strength
and prevent seepage between lift joints, bedding mix, a form
of grout, is commonly added between each lift.
With its high cementatious
content, the mixs adhesive strength matches that provided
by grout, Rogers says, so Kiewit could usually skip the bedding
mix layer except after weekends or other long breaks in placement.
The value engineered mix "resisted segregation"
and "got compaction very easily," says Bruce Bennett,
project manager for Washington Group International Inc.s
infrastructure unit, which serves as SDCWAs project
management consultant.
Kiewit was able
to place this "contractor-friendly" mix "at
a very high rate of speed," including a record 294,000
cu yd total for June 2002, Pauletto says. Production time
was critical because RCC provides the best cohesion when fresh,
SDCWAs Reed points out: "The faster you go with
RCC, the better the quality."
Though state officials
ultimately agreed on the mixs quality and benefits,
the schedule put the team under the gun to make its case.
"We had a budget. We didnt have a lot of time to
keep on doing trials to prove we didnt need grout mix,"
Reed recalls.
Winning approval
of RCC was also a challenge because "state officials
are used to seeing it for rehab, rather than for new dams,"
Rogers says. DSOD expedited approval by taking the unusual
step of joining in the partnering process. Pauletto calls
it "a real bonus to have them on board with the partnering
session every month."
RCC also "allowed
us to curve the top part," providing a key seismic design
feature, Rogers says. On the downstream face, the upper 83
ft step back more gradually than the 1:1 slope of the lower
three quarters. The curvilinear design "eliminates the
stress concentration" of seismic loads, Rogers says.
Vertical joints at 100-ft intervals allow sections to move
independently in an earthquake.
advertisement
...
At each lift, the
dam is tied into the 300-ft-tall, three-sided inlet-outlet
tower, which Rogers calls "the money part of the job"
because of its importance to the dams operation. With
walls up to 6 ft thick at the base and 4 ft thick near the
top, the tower is crowned with a control building extending
25 ft above the crest. Six gates at various locations will
provide a SDCWA a choice of water quality in an emergency,
Rogers says.
Because RCC dams
can be subject to seepage between lifts, a drainage system
is being applied to the dams 210,000 sq ft upstream
face. A 2.5-mm-thick plastic geogrid is attached and covered
with a polyvinyl chloride membrane. Every 12 ft along the
upstream base, a 20-ft-long, 2-in.-dia. steel drainpipe will
catch seepage and convey it to the 6-ft-wide, 8-ft-tall drainage
gallery, Rogers says. With 10% to 20% of the liner still remaining
to be installed, SDCWA expects to start filling Aug. 6. The
process will take up to 10 months, Reed says.
The highlight of
the Emergency Storage Projects next phase will be a
$199-million, 11-mile-long tunnel linking San Vincente Reservoir
to SDCWAs second aqueduct. Ranging from 50 ft to 300
ft deep, the 13-ft-dia. tunnel will contain a 10-ft-dia. pipeline.
Construction on
the $199-million project is scheduled to start in late 2004.
RCC will make a return appearance late in the decade for the
programs final phase, when SDCWA plans to raise 59-year-old
San Vincente Dam from 234 ft to 288 ft.