Construction is expected
to begin next year on a 765-kv transmission line from West
Virginia to Virginia first proposed in 1990 by American Electric
Power Co., Columbus, Ohio. On Dec. 31, the U.S. Forest Service
issued its final environmental impact statement and record
of decision on the 11 miles of public lands crossed by the
90-mile Wyoming-Jacksons Ferry line. That action clears the
way for issuance of a permit by the Forest Service, says Todd
Burns, AEP spokesman.
State regulators in Virginia and
West Virginia approved the project in May 2001 and March 2002,
respectively. Construction can begin when the Forest Service
issues the permit and the U.S. Army Corps of Engineers issues
a letter saying that the project complies with Corps specifications,
says Burns.
Engineering of the $287-million
line is under way in-house and surveying is in progress in
the 1,000-ft-wide, state-approved route, which runs from Oceana,
W. Va., to Wythe County, Va. Right-of-way acquisition will
begin early this year on the the 200-ft-wide corridor. The
easement will be cleared by the end of the year, allowing
construction to begin next year, aiming for completion by
mid-2006, says Burns.
The line will consist of six-bundle
conductor strung on guyed-V steel towers, whose steel will
be darkened by etching to reduce the line's visual impact.
Average tower height will be 132 ft, with the tallest about
180 ft. The conductor bundling "will reduce noise from corona
by about half," says Burns.
AEP last reinforced the 765-kv
transmission system that delivers electricity to southern
West Virginia, Virginia and eastern Kentucky in 1973. Since
then, the area's peak demand has increased by more than 135%.
The line originally was proposed to run from the Wyoming substation
in West Virginia to the Cloverdale station near Roanoke, Va.
The route was cut back in 2000 to accommodate objections from
affected communities (ENR 5/22/00 p. 17).