 |
|
HOT STUFF Loops of polyethylene
pipe containing glycol in piles and foundations will capture
geothermal heating and cooling in first North American
project. (Photo courtesy of Zeidler Partnership Architects) |
After a successful
20-year run in Europe, Austrian geothermal heating technology
is making its debut in North America. The low-cost thermal-active
foundations can provide up to 600 tons of heating or cooling
capacity and can be used in piles, diaphragm walls and foundation
slabs.
Developed by Nagele Energie-und
Haustechnik, GmbH, Feldkirch, Enercret uses looped piping
installed in slabs, walls and piles to circulate a glycol
mixture for conversion to heating or cooling. Already in use
in over 400 European buildings, the system can reduce utility
costs by 80%, say Nagele officials.
Those were important considerations
for foundation contractor Bermingham Construction Ltd., Hamilton,
Ontario, as it installed 57 14-in.-dia steel pipe piles 100
ft deep for the new $6-million Canada Marine Discovery Center.
Bermingham and Earth Energy Utility Corp., Burlington, Ontario,
are acquiring the North American rights from Nagele.
"Energy used to be pretty
cheap in North America," says Peter J. Smith, Bermingham
vice president. "That isnt so any more and we have
a cost-effective way to heat and cool any size building."
He notes the system has been used on a number of large commercial
structures, including a 20-story bank building in Hanover,
Germany, and a terminal at Londons Heathrow Airport.
Enercret also has been used to keep bridge decks ice-free
by placing loops in abutment piles.
 |
|
(Photo courtesy of Enercrete)
|
Enercret already has saved about
$100,000 in project construction costs. "In our original
design, we were going to drill separate piles outside the
building and run the loops in," says Joseph W. Chalklin,
project manager for Zeidler Partnership Architects, Toronto.
But Enercret "is perfect for the site because it has
poor soils and a high water table."
Each concrete-filled pile contains
two 1-in.-dia loops wrapped together with duct tape. "Each
loop is on a separate circuit that can be shut off if it leaks,"
says Chalklin. The piping connects to one of two manifolds
connected to the HVAC system for the 18,000-sq-ft, one-floor
structure.
 |
|
(Image courtesy of Zeidler Partnership
Architects)
|
"The system does not require
any special concrete and the high-density polyethylene tubing
is off-the-shelf, so costs are reasonable," says Smith.
"The mechanical room contains water-to-air heat pumps
connected to conventional ducting, so costs are roughly comparable
to conventional boilers and air-conditioning units."
He says the payback on the loops can be realized in as little
as four to five years at current energy prices. To check for
leaks during installation each loop is charged with 85-psi
air until final testing and acceptance. Bermingham took six
weeks to install the piles, 40,000 linear ft of piping and
equipment on its $350,000 contract. The general contractor,
James Kemp Construction Ltd., Hamilton, built the slab and
walls.
|