Posh
yachts docking in monaco after this summer will be sheltered
from dangerous Mediterranean storms. The port's existing century-old
sea walls sometimes are not up to the task. Using custom breakwaters
fabricated in Spain and France is the principality's elegant
way of calming 55-m-deep water in its $250-million Port Condamine
project. But the engineering demands stretched both the contractor's
skills and the project budget.
 |
| CONNECTION
Steel ball-and-socket joint attaches floating dock to
land base. (Photo courtesy of Dragados) |
The 160,000-tonne floating main
breakwater is "a prototype with a new level of
specification," says Fernando
Ortiz, project director with the construction consortium leader
Grupo Dragados, Madrid. But the team was surprised by the
unusually dense reinforcing and design complexities imposed
by the 12-day sea tow from the Spanish casting yard. "People
were not always confident about the possibility of finishing
this job," Ortiz says.
The project is a year late and
currently pegged at $135 million-more than double the original
estimate. The consortium and Monaco's Ministry of Public Works
are working through claims.
But away from negotiations, the
consortium has overcome the technical challenge of casting
the 352-m-long, 28-m-wide, 19-m-deep prestressed box. With
construction in Algeciras done, workers are prepping the breakwater
for the tow to Monaco.
At the tiny but affluent enclave,
the structure will join a smaller, French-built caisson to
form the two wave walls outside the existing harbor at Condamine.
From the south shore, the main box will reach diagonally across
the port approach providing shelter from the east. It will
be connected by a 650-tonne, steel ball-and-socket joint to
one of several caissons enclosing 8,000 sq m of reclaimed
land at Fort Antoine. The rest of the breakwater, anchored
by chains, will float with just 3 m of freeboard.
Projecting from the opposite shore
of the harbor entrance, the smaller box will end on the leeward
side of the main breakwater, completing the new wave barrier.
Because of shallower water, this smaller box will be propped
from below at points 25 m and 65 m from its offshore end.
Forming the props are vertical extensions at the ends of a
46-m-long, 17-m-deep concrete caisson, now resting on an underwater
earth embankment 40 m below the surface.
PONTOON
WALL DESIGN. The deep water and a weak sea bed at Port
Condamine's entrance led the Ministry's designer, Paris-based
Doris Engineering S.A, to plan the unusual pontoon-type sea
walls, says the firm's project director François Sedillot.
 |
 |
| SAFE
New wings (tinted) will protect harbor (right). (Photo
left courtesy of Bouygues, right courtesy of Doris Engineering)
|
Doris, which is also the owner's
project manager and supervisor, produced drawings detailed
enough for bidding the main design-build contracts for the
breakwaters and associated works, both awarded in summer 1999.
First off the starting block late
that year was a consortium including Paris-based Bouygues
S.A., with Groupe Vinci and others. The team began work at
La Ciotat, Marseilles, ultimately building seven caissons.
Most of them went to enclose the land reclamation for the
main breakwater's anchorage, forming part of that contract.
The consortium also built the smaller breakwater and its seabed
caisson support at the drydock.
The French breakwater is 145 m
long, 30 m wide at its base, 11 m deep and will be positioned
with 2 m above water. Because of its profile, it is smaller
and more effective at calming waves than a rectangular version,
claims Bouygues Offshore S.A., which developed the concept.
Basically, a 5-m-long sloping projection at base slab level
breaks oncoming waves. The perforated main vertical wall behind
dissipates water energy through turbulence.
SETTING
SAIL. The French team flooded the La Ciotat drydock
in mid-May, and now is preparing the breakwater for its 200-km
tow to Monaco later this month. The Spanish drydock will be
flooded by then, according to the schedule. Once in deep water,
the structure will take on additional ballast ahead of the
planned delivery in July or August. The Spanish team, also
including Fomento de Construcciones y Contratas S.A., with
minor partners, began work at Algeciras in 2000.
 |
|
| (Illustration
courtesy of Doris Engineering) |
 |
Designed to float with 16
m below sea level, the main breakwater is twin skinned.
Its internal walls and slabs, all around 50 cm thick,
are set several metres back to create ballast chambers.
The whole box is stiffened with cross walls and bulkheads.
For about half its length, precast floors will provide
parking for 400 cars on four levels.
The other half will contain
two floors of boat stores. To improve wave-breaking
performance, the box's base slab projects 8 m on either
side.
|
| (Illustration
courtesy of Doris Engineering) |
In shape and dimensions, the finished
structure remains virtually unchanged from Doris' design,
says Sedillot. The contractor's responsibility was to engineer
the breakwater for temporary loading at sea. And it had to
detail the rebar and prestressing, which was more daunting
than first expected, he concedes. "It's...very congested
in terms of density of reinforcing and prestressing,"
he says. The prestressing density of 80 kg per cu m of concrete
is at the top end of the scale, he adds.
It was tough to design the box
as a ship, accommodate the tight mesh of steel and pour concrete
through it as well, says Ortiz. And the unusually high 100-year
design life didn't help. The structure is "so new and
so special" that he hopes for a sympathetic hearing during
cost negotiations.
But Sedillot's response may not
be encouraging. "From our experience in the North Sea
and offshore structures in general, we have seen more difficult
structures," he says.
|