|
No owner of a complex
construction project sees the job completed without some headaches,
and the U.S. Congress is no exception. The 535-member owner
of the estimated $550-million U.S. Capitol Visitor Center,
under way in Washington, D.C., is pressing contractors on
cost growth and schedule slippage. While construction officials
acknowledge the site problems, they claim the project can
meet a key completion deadline in September 2006.
 |
| Set
in stone. Congress worries about missed project
deadlines but work pushes on. |
In July 14 testimony to a U.S.
Senate Appropriations subcommittee, the U.S. Government Accountability
Office reported that a series of problems, from inadequate
stone delivery to subcontractor legal battles, could delay
the 588,000-sq-ft underground facility by six months or be
costly to expedite. The report by GAO, Congress investigative
arm, is the latest in monthly project updates to its inquisitive
owner.
"Work on some selected milestones
scheduled for completion by todays hearing is incomplete;
some work has been postponed and some new issues have arisen
that could affect the projects progress," according
to testimony presented by Terrell Dorn, GAO assistant director
of physical infrastructure issues. He noted that Manhattan
Construction Co., project contractor for the centers
work on interiors and utilities, completed only 3 of 17 milestones
on time. However, site officials said Manhattan has now finished
at least 12 of those milestones.
One thorny problem is production
and delivery delays for sandstone, a key building material.
Architect of the Capitol Alan Hantman told the subcommittee
that stone for the project "in the quantities specified
by the contract continues below expected levels." Officials
attribute the delay also to an ongoing dispute in a Pennsylvania
federal district court between two key Manhattan subcontractors
responsible for stone supply and fabrication.
"We have taken some important
steps that we hope will facilitate and expedite the fabrication
and delivery of stone," said Hantman. That could include
pressing the court to require the firms to produce the stone,
according to published reports. Project officials say they
may resequence work, but GAO is concerned that such fixes
could increase project costs later if "mitigation involves
expediting installation to recover lost time." GAO contends
that the project is likely not to be "substantially completed"
until the first quarter of 2007.
Site officials disagree. "The
schedule is tight but still doable," says Tom Fontana,
project spokesman. "We recognize GAOs concerns
but our contractors will resolve the issues and make up lost
time." He says shortage of masons is a bigger problem
than stone deliveries, adding that worker levels will "double
and triple" in coming weeks.
(Photo courtesy of the Office of the
Architect of the Capitol)
|