|
The imminent completion
of a small but complex slurry wall that takes a $4-billion Manhattan
project a step forward is, for Arturo L. Ressi di Cervia, a
bit of deja vu.
The 27,700 sq ft of slurry wall
wedged between a school and New York City Transit elevated
subway tracks in Queens required the extraction of two levels
of tiebacks at the edge of another slurry wall that Treviicos
Corp., Englewood Cliffs, N.J., built four years ago, says
di Cervia, the firm's director. There are two more slurry
walls in the immediate vicinity that the firm built, he says.
 |
| TOUGH
SITE Slurry wall segments were placed in tight
working conditions. |
Now Treviicos is wrapping up a
$3.5-million subcontract to the Park Ridge, N.J., office of
Kiewit Constructors Inc., which has the $16-million contract
for excavation and earth support systems that lays the base
for New York City's $4-billion East Side Access project that
will send Long Island Rail Road trains to Manhattan's Grand
Central Station. The network of walls, sheet piles and 800-kip
tiebacks will allow future crews to set up tunnel operations
to Manhattan.
The slurry wall now is receiving
the last of 21 panels socketed 6 in. into hard rock and chemically
grouted, says Henry Riley, Treviicos superintendent. About
3,510 cu yd of concrete will be poured.
The subcontract, begun in December
2002, was slated for nine weeks, but "contractually it
was foreseen that delays might be possible due to boulders,"
says di Cervia. Boulders of 3 to 4 ft across and up to 5 ft
high were found. Work also was slowed because of requests
by the transit authority not to swing the 250-ton cranes at
an angle facing the tracks. This caused picking and placing
of the asymmetrical L-shaped rebar cages at a more difficult
angle.
The wall, up to 48 in. thick, goes
down to 83 ft through a geological "crazy quilt,"
facing the 63rd St. tunnel tubes built with two levels of
tracks. The lower level will accommodate LIRR trains that
will eventually serve Grand Central.
The wall is being placed in an
irregularly shaped semicircle. When complete, Kiewit will
excavate a pit to allow a contractor to assemble a tunnel
boring machine and move it through the existing tunnel to
Manhattan where a new tunnel will be driven, says Dwight Metcalf,
Kiewit project manager. Existing bulkheads on the existing
tubes will be broken out to start the tunnel.
Another wall will be built across
the street "like this, only five times bigger,"
Metcalf says. That job is set to go to bid in early May. It
will support an open-cut excavation to provide access for
an earth pressure balance tunneling machine that will work
in the opposite direction, to railyards and a connection to
existing LIRR tracks.
|