|
With steel fabricators
and contractors bruised by jumps in steel prices, Transportation
Secretary Norman Mineta says he plans to explore ways to ease
the pain. They may include seeking legislative changes from
Congress.
The Federal Highway Administration
said on April 9 that it cannot provide price adjustments to
existing contracts. That led construction officials to look
into a legislative fix for the steel problem. If Mineta decides
to back such a change, it would give that option a major push.
The rise in prices has sparked
widespread worry in construction, including major bridge projects.
The steel-price impact "is a real issue thats facing
us right now," says Mineta. "Ive been told
that we cant do anything retroactively for contracts
that are already in place, but that we can provide provisions
in future contracts for escalator clauses for things like
increased steel prices."
Mineta wants fabricators to survive.
"The problem I see...is that if the fabricators go bankrupt
right now, theyre not going to be around for jobs coming
up," he says. Mineta says he plans to meet with DOTs
general counsel on whether "we have to go back to Congress
and get a legislative solution rather than a change in contractual
law. [Currently,] we dont have any wiggle room on what
to do on giving relief to contractors."
One of the major bridge projects
that could be affected by the steel price escalation is the
new Woodrow Wilson Bridge now being built across the Potomac
River at Alexandria, Va. The $720-million bridge will have
two parallel bascule spans totaling 12 lanes. It is the main
element in a $2.4-billion project that includes upgraded interchanges.
U.S. DOT, Maryland, Virginia and
the District of Columbia share the project cost. "Were
concerned about the increase in cost of steel, specifically
on this bridge," says Maryland DOT Secretary Robert L.
Flanagan. "It poses some very serious challenges to our
making the kind of progress that we want to make and will
be making" on the project.
Maryland Highway Administrator
Neil J. Pedersen wrote FHWA on April 2 that steel price trends
"present a real threat to the three [Wilson] superstructure
contracts," which involve more than 40,000 tons of structural
steel. Pedersen said about half is "at risk of delay
due to disputes regarding the price increases."
Officials plan to finish a new,
six-lane bridge, about one mile long, in early 2006. The existing,
six-lane bridge, which was completed in 1961, will be demolished
and a second, six-lane bridge will be built there. Completion
is expected in 2008.
"The fact that the secretary
is focused on the issue and is looking for remedies is indeed
encouraging," says Marianne Pastor, a vice president
with Williams Industries Inc., a steel fabricator on the Wilson
project. "He is possibly in the best position to influence
a solution that will be broad-based and equitable."
Manassas, Va.-based Williams has
the steel contract for the bridge section from Virginia to
its drawspan. Pastor says the firms share of the contract
initially was estimated at $30 million. All of the steel for
Williams part of the six-lane outer span has been purchased,
she says. But Pastor adds, "We are not willing to say
that it was not without some difficulty." That steel
now is in fabrication.
The California Dept. of Transportation
is watching steel prices as it plans the $740-million suspension
span of its San Francisco-Oakland Bay Bridge project. The
1,860-ft-long, single-suspension span will need 67,000 tons
of steel (ENR 11/3/03
p. 10). Caltrans planned a bid opening last Oct. 21, but postponed
it to Jan. 21 and then to May 26.
"We were just beginning to
hear about...changes in the steel market" in December,
says Dan McElhinney, chief deputy director in Caltrans
Oakland district. He says rescheduling bid dates "gave
both the department as well as the contractors the opportunity
to assess how [steel prices] might affect their ability to
bid."
|