|
Officials from the U.S.
Army Corps of Engineers, Kellogg Brown & Root and the Iraqi
Oil Ministry have hammered out a consolidated list of projects
necessary to put the Iraqi oil industry back on its feet. The
list is the result of a four-day meeting among principals in
Baghdad earlier this month. Their goal is to get the industry
back to its prewar oil production capacity of 2.5 million bbl
despite claims they are slowed by infrastructure maintenance
problems and security concerns.
"We are looking in a total
way at the infrastructure and working with the ministry to
get them back to prewar production capability," says
Steven Wright, a spokesman for the Corps' Kuwait-based Restore
Iraqi Oil Task Force. Until recently, the participating organizations
have focused on discrete aspects of the problem, trying to
manage their part of an industry in crisis. The July 6-9 meeting
gave participants a chance to set priorities.
The essential elements for hitting
prewar production capacity are pipeline restoration, maintaining
steady filtered-water supplies needed to reinject into Iraqi
oil wells, electricity and security against the looting and
sabotage that is being witnessed throughout the country, explains
Wright.
Limitations in pipeline capacity
are a principal factor in the industry's recovery. Maj. Joseph
Hanus, the Corps' northern area deputy engineer for Iraq,
notes, "We have a pipeline from Kirkuk to Baiji, which
is fairly old and corroded. It has a limited capacity of 500,000
bbl/day. So you can see already there are restricting factors."
That pipeline is a key segment in the Iraq-Turkey pipeline
by which oil from the north is exported (ENR 6/16 p. 18).
The Southern Oil Co. productioncurrently standing at
300,000 to 400,000 bbl/dayis limited by storage, power
supply and a shortage of filtered water.
Johnny Rozsypal, the Corps' southern
area engineer for Iraq, says that production "could increase"
with more sufficient storage and additional loading of crude
onto tankers. "They are also waiting for tankers,"
says Rozsypal. "Production could rise to 500,000 to 800,000
bbl/day if these issues are resolved."
Rozsypal also points to the Qarmat
Ali water pumping station as another priority for restoring
prewar production capacities. Before the war, the water station
supplied filtered water for reinjection into Iraqi oil wells
in the south. "We need filtered water to improve the
grade of the crude," he says. "We are trying to
get more water for the injection process."
Security problems including sabotage,
looting, and the deliberate destruction of electricity grids
also have hindered efforts to facilitate Iraq's prewar oil
production capacity.
Clifford G. Mumm, Bechtel National
Inc.'s project director overseeing the $680-million U.S. Agency
for International Development rebuilding contract in Iraq,
agrees that looting and other security concerns have hindered
work. When Bechtel crews first surveyed the 400-kv power transmission
line that runs south into Baghdad there were 13 towers down.
Now, 65 towers are down, Mumm said July 15 in an interview
with ENR in Washington, D.C. Looters are "harvesting
the copper" that they strip from the lines.
Mumm notes that Bechtel finished
the assessment portion of its work and submitted an implementation
plan in late June to USAID and military officials in Baghdad.
After review, specific reconstruction priorities and scope
of work will be decided, likely within the next few weeks.
Emergency work at Umm Qasr seaport is expected to be completed
in August.
To read interview with Cliff Mumm,
click here.
|