|
|
| (Photo
courtesy of U.S. Army Corps of Engineers) |
A 400-kV transmission
line near Bayji, Iraq, has been restored to service after being
severed Sept. 14 in a morning attack on a nearby oil pipeline.
The loss of the line knocked out power to most of the country,
but redundancy in the transmission system allowed the Ministry
of Electricity to begin restoring electric service within hours
of the 2:00 a.m. attack. By Tuesday night, Sept. 14, 85% of
the country's service had been restored. The grid was stabilized
Thursday night.
Three crude-oil pipelines erupted
following explosions near the 676-MW Bayji Electricity Plant
north of Baghdad Tuesday morning. Heat rising from the sea
of blazing oil melted the high-voltage transmission line nearly
300 ft above, causing the 5,000-MW national grid to short-circuit.
"The severed circuit caused a sudden power loss of 750
MW within one second," writes Mitchell Frazier, a spokesman
for the U.S. Army Corps of Engineers team working with the
Electricity Ministry to restore the nation's electric system,
via e-mail from Baghdad. "This sudden loss of power created
an imbalance of power from the grid and neighboring substations....Mr.
Ahmad (technical manager of the gas turbines at Bayji) stated
the current grid system cannot handle or support the high
voltage and drastic change of power."
The emergency response by the ministry
is the first since the Coalition Provisional Authority transferred
sovereignty to the interim Iraqi Government at the end of
June. The move to quickly restore the nation's electricity
came as temperatures cooled in the past week and demand on
the national grid slacked off. Thursday most of Iraq was powered
with at least 16 hours of electricity, according to the Corps
of Engineers. Some areas received upwards of 20 to 24 hours
of service. The Corps previously reported that the Electricity
Ministry directed that Najaf was to receive 24-hour electric
service following the cessation of fighting by the Mahdi Army
militia of Shiite leader Moqtada al-Sadr in that city.
Iraqi and U.S. engineers have brought
three rehabilitated generators and one new generator online
this month, adding 47 MW to the grid. Last month, seven generators
were brought online, adding 202 MW. Since July 1, available
generation has increased by about 400 MW, says Frazier. The
goal is to add 1,000 MW by the end of the year.
Security at the attack site was
increased with soldiers from the Iraqi National Guard.
|