Japanese Disaster Puts Focus On U.S. Powerplant Problems

Text size: A A

Following the Fukushima Daiichi nuclear reactor crisis in Japan, the U.S. nuclear industry is more closely scrutinizing existing facilities, and long-standing problems are placing some plants under the microscope .

Courtesy of Progress Energy
Crystal River plant has cracks in walls.
Courtesy of NextEra Energy
Engineers note alkali silica reaction at Seabrook.
----- Advertising -----

“U.S. nuclear facilities are under constant inspection regimens, but since the earthquake we are going at it even stronger,” says Mitch Singer, spokesman for the Nuclear Energy Institute, a Washington, D.C.-based industry organization.

In one example, Progress Energy's Crystal River plant in Florida—offline since September 2009 for a refueling and maintenance outage—could be permanently closed.

While installing new steam generators to replace old ones in the containment building last March, Progress discovered a separation in the 42-inch wall and another during repair of that problem. Progress spent $150 million on the repair of the first separation and $290 million on replacement power costs, says Tim Leljedal, Progress Energy spokesman.

The utility is analyzing its options, including repair or decommissioning. “We have a strong preference to repair the facility and return it to service,” Leljedal says. There is no deadline for deciding on the plant's future, but he says Progress will give the Florida Public Service Commission an update on June 27.

At NextEra Energy Resources' Seabrook nuclear powerplant in Seabrook, N.H., officials are concerned about a concrete electrical tunnel weakened by groundwater beneath the facility. The problem arises as Seabrook's license renewal application is pending.

At issue is the probable link between an alkali-silica reaction (ASR) in the tunnel's concrete and loss of more than 20% of its strength, which officials from the Nuclear Regulatory Commission say is the first such occurrence it has identified in the U.S. While the ASR problem has not been detected at other sites, NRC says it could be occurring elsewhere.

The NRC has reached out to the Dept. of Transportation for expert advice since it is unclear how ASR will affect the tunnel over time.

Arthur Burritt, NRC's branch chief for inspections at the Seabrook nuclear facility, says despite possible groundwater intrusion, the reactor has not been affected and that structures are still sound.

NextEra determined that the tunnel remained operable with a 50% reduction in design margin. A May 13 NRC inspection report notes that the performance deficiency related to ASR is significant because if left uncorrected it could result in a reactor trip. Core samples of reactive concrete taken in 2010 are currently undergoing analysis, with initial findings expected soon.

Keywords:

----- Advertising -----
  Blogs: ENR Staff   Blogs: Other Voices  
Critical Path: ENR's editors and bloggers deliver their insights, opinions, cool-headed analysis and hot-headed rantings
Project Leads/Pulse

Gives readers a glimpse of who is planning and constructing some of the largest projects throughout the U.S. Much information for pulse is derived from McGraw-Hill Construction Dodge.

For more information on a project in Pulse that has a DR#, or for general information on Dodge products and services, please visit our Website at www.dodge.construction.com.

Information is provided on construction projects in following stages in each issue of ENR: Planning, Contracts/Bids/Proposals and Bid/Proposal Dates.

View all Project Leads/Pulse »

 Reader Comments:

Sign in to Comment

To write a comment about this story, please sign in. If this is your first time commenting on this site, you will be required to fill out a brief registration form. Your public username will be the beginning of the email address that you enter into the form (everything before the @ symbol). Other than that, none of the information that you enter will be publically displayed.

We welcome comments from all points of view. Off-topic or abusive comments, however, will be removed at the editors’ discretion.