New Look. V-shaped
concrete piers mimic upstream Memorial Bridges arches.
After more than four
years of construction, the $2.4-billion plan to build a new
Woodrow Wilson Bridge across the Potomac River and expand adjacent
segments of the Capital Beltway has reached the one-third-complete
mark. The scorecard so far? Neil Pedersen, head of the Maryland
State Highway Administration, which oversees the lions
share of the contracts, says: "We are on schedule. We are
slightly under our budget. For a megaproject these days, that
is quite an accomplishment."
After the huge cost run-up on Bostons
"Big Dig," any $1-billion-plus transportation megaproject
faces sterner scrutiny than before from the U.S. Dept. of
Transportation, not to mention other federal and state auditors.
What puts the Wilson bridge even more squarely at center stage
is that it is Washington, D.C.s megaproject, with Congress
and U.S. DOT right on its doorstep. "Were in the
spotlight, so the expectations are really ramped up,"
says Robert D. Douglass, project director for Marylands
highway agency. Click
here to view drawing>>
While pleased with the progress
so far, project officials know that there is lots left to
do and a tight timetable. For Russell Fuhrman, executive project
manager for general engineering consultant team Potomac Crossing
Consultants, the overriding issue is "schedule, schedule,
schedule." Fuhrman also is a senior manager with Parsons
Brinckerhoff, New York City, which with San Francisco-based
URS and Baltimore-based Rummel Klepper & Kahl LLP make
up PCC.
The massive construction job was
triggered by the need to replace the existing 44-year-old
Wilson Bridge, a six-lane bascule structure. It was designed
to handle 75,000 vehicles a day, but is groaning under its
current 200,000-vehicle daily load. Because the bridges
drawspan only has a 50-foot channel clearance, motorists also
have endured about 250 openings a year so ships can pass through.
A 2004 evaluation rated the old bridges condition as
"fair," but, as in previous reviews, found weld
metal and base metal cracks, rusting and loose or broken deck
panel tie-down rods.
<
Tight
Quarters. Until existing bridge (right) is demolished,
it restricts amount of space available for working on
new northern bridge (center).
Knowing that patchwork could not
go on indefinitely and that more capacity was needed, a new
crossing emerged after a long public debate. The plan now
being built includes two parallel 6,075-ft-long bascule bridges,
each featuring reinforced concrete piers and structural steel
girders. The southern bridge will be 110 ft wide and its upstream
sibling 124 ft wide. Each will have room for six lanes plus
shoulders. At the peak, each deck rises about 100 ft from
the top of the pier foundations. With a 135-ft clearance,
annual drawspan openings should drop to 65.
The key date staring at the project
team is spring 2006, when the new southern bridge is slated
to open. Traffic then will be shifted to that new structure
and the old bridge will be demolished. Work has proceeded
on both new bridges, but once the old bridge is demolished,
contractors can push single-mindedly on the second new bridge,
aiming for a 2008 opening.
Keeping the project on track has
not been easy. Maryland officials initially bid the superstructure
as a single contract, but they were dismayed at the December
2001 bid opening when the lone bid came in at $860 million,
or more than 70% above their estimate, officials were shocked.
Searching for options, they recruited an outside panel, led
by former Utah DOT Executive Director Thomas Warne, whose
key recommendation was to split the job into three contractsone
for the bascule section; a second for the mostly overland
segment from the Virginia shore to the bascule; and a third
piece, mostly over water, from Maryland to the drawspan.
The three-contract gamble has paid
off. Maryland had more biddersthree, seven and four
proposals, respectively, for the three contracts. More importantly,
the three low bids came in at a combined $496 million, almost
matching the states original superstructure estimate.
SHAs Douglass says the rebidding "cost us a year,"
but saved $362 million.
Another factor behind the increased
competition was that Maryland, under pressure from FHWA, dropped
a union-only project labor agreement requirement. Douglass
says there are contractor-negotiated union agreements on the
bascule and Maryland approaches, but not the Virginia approach.
Nonunion G.A. & F.C. Wagman Inc., York, Pa., won three
Maryland interchange contracts, while one won by John Driggs
Co., Capitol Heights, Md., was a union contract. PLAs "became
a true non-issue from our standpoint," Douglass says.
In the foundation phase, another
serious problem cropped up. Shock waves from driving piles
were killing hundreds of fish. "Nobody had anticipated
this," says Michael S. Baker, of URS, PCCs environmental
construction manager. Without a fix, piledriving could have
been halted for several costly months.
The remedy was air bubbles. Compressed
air was fed through a perforated hose circling a pile. An
outer steel tube surrounded the loop of hose. The "curtain"
of air bubbles absorbed the shock waves and reduced fish fatalities
to only a few. The fix was not expensive, Baker says. "This
was done with stuff they had in the yard."
Steel prices were a third major
threat. As steel costs soared, Maryland sought ideas from
its steel fabricators, contractors and others. The outcome
was a pact reached last summer for the Maryland approach and
bascule under which contractors agreed to absorb increases
up to 7% above steels price at the time of the bid.
The state will cover increases above 7%, up to a cap of $4
million on the bascule and $9 million on the Maryland approach.
Contractors also agreed to triple the penalties for missing
deadlines, to $75,000 a day. A similar deal is in the works
for the Virginia approach.
"Its a fair solution
that the state came up with," says J. Daniel Bell, American
Bridge Co. bascule project manager. Bob Dacre, vice president
for project management with bascule steel fabricator PDM Bridge
LLC, Eau Claire, Wis., agrees. "I think that everybody
did the right thing and we reached an agreement that we consider
fair and equitable," he says. Maryland officials are
"very tough bargainers, but their word is good and their
commitment to dealing in a fair and forthright manner is there,"
he adds.
Contractors on each bridge segment
say their jobs are going well, but they point to challenges,
some of which stem from the bridges distinctive design.
Designers aimed for "something that is aesthetically
pleasing, that matches the architecture of the bridges in
the area," says Greg Shafer, project manager for designer
Parsons, Pasadena, Calif. They had in mind crossings like
the arched Memorial Bridge...
Gives readers a glimpse of who is planning and constructing some of the largest projects throughout the U.S. Much information for pulse is derived from McGraw-Hill Construction Dodge.
For more information on a project in Pulse that has a DR#, or for general information on Dodge products and services, please visit our Website at www.dodge.construction.com.
Information is provided on construction projects in following stages in each issue of ENR: Planning, Contracts/Bids/Proposals and Bid/Proposal Dates.