|
...Dept. of Transportation and Development
this month was scheduled to present an argument for design-building
the bridge to state legislators, says Tony Ducote, bridge
engineer administrator.
Economic Boost
The Highway 10 bridge would spur economic development in
a depressed, agricultural area dotted with magnificent plantation
homes. The project is funded by the Transportation Infrastructure
Model for Economic Development program funded through a 4¢
fuel tax, says Paul Fossier, LDOTD project manager.
Anticipating the bridge, local
cities began planning an 210-mile east-west parkway in 1992,
between I-49 and I-59. "The bridge is a key to Zachary
Taylor Parkway becoming a reality," says Billy DAquilla,
mayor of St. Francisville.
The total 14-mile project length
includes a four-lane, cable-stayed bridge with a 1,400-ft
main span and two-lane approaches. The state has completed
preliminary plans for a steel superstructure and concrete
deck. If the project receives approval for design-build, DOTD
will spend the next six to eight months on procurement documents
with a planned 2005 bid, Fossier says. Ducote says design-build
could lead to use of new technology: "There may be potential
for something other than caissons."
The special fuel tax also funds
the planned expansion of the Huey P. Long Bridge, a combined
rail-highway steel trestle. Ray Mumphrey, DOTD project manager,
says plans are complete for the substructure, which includes
widening of the main piers. Environmental studies will be
complete by March 2005.
Harrisburg-based Modjeski &
Masters Chairman William B. Conway told engineers at a recent
conference that widening poses "a pioneering engineering
problem of the first magnitude." M&M is handling
design for the $316-million job.
The 3,524-ft-long bridge is constructed
on six caisson-supported and three pile-supported piers. It
has two tracks with a bracketed roadway on each side that
will be doubled to include three, 11-ft lanes in each direction
plus an 8-ft shoulder.
"We are widening those piers
on the existing caissons and we are fortunate that they could
accept those loads," notes Mumphrey. The piers will be
widened using steel brackets eventually concealed behind concrete
panels. The steel trusses will be extended on either side
with methodical balancing. "We [do not] know of another
bridge in the United States that has been widened this way
with this technique," Conway said.
The method will allow traffic to
continue during construction but lengthens construction time.
"The contractor and steel erector have to follow a fairly
rigorous sequence of construction," he says.
 |
| OLD
AND NEW. New arched truss crossing in La Crosse stands
alongside old one to take on traffic. (Photo courtesy
of Wisconsin DOT) |
Northern Crossings
Escalating traffic also spurred the need to expand a 2,573-ft-long
cantilevered bridge in La Crosse, Wis. The 23-month, $40-million
project adds two new lanes of U.S.-14/61-State Route 16, located
35 ft south of the two-lane Cass Street Bridge to take eastbound
traffic in November. The existing bridge handles 19,000 vehicles
daily with 28,000 expected by 2024. Steve Flottmeyer, project
manager for Wisconsin Dept. of Transportation, says rehabilitation
of the old bridge will begin early next year. Lunda Construction
Co., Black River Falls, Wis., completed its $22.5-million
contract in June for two 60-ft-deep pier footings, a massive
arch truss main span and 11 piers. Approach work, concrete
deck placement, lighting and other aesthetics are nearing
completion.
The La Crosse job hit a critical
milestone when the 475-ft-long main span floated into place
last December (ENR 12/22/03 p. 16). Lunda installed the 2.8-million-lb
arch truss in eight hours after a massive coordination effort
that took nearly nine months to plan.
 |
|
YOUTHFUL TALENT. Frederick handled truss float-in at age
28. (Photo courtesy of Lunda Construction Co.) |
"It was a huge exercise in
logistics," says Brady J. Frederick, project manager.
A U.S. Navy Civil Engineer Corps veteran and only 29 years
old, he drafted plans for a 40-member team and provided to-the-minute
agendas. "He did a very fine job for us," says Lunda
project manager Paul Nortman. Frederick coordinated with the
Corps of Engineers to adjust channel water levels, among other
tasks.
The channel had to remain open
for freight traffic, so Lunda opted to erect the span downstream
on 68 ft of falsework anchored to three barges. After the
float-in, crews pumped water into the bulkheads. Workers made
one bearing adjustment of less then a quarter inch to finish
installation.
The project was marred by the 2003
death of 34-year-old Anthony J. Poterala, an ironworker. For
reasons still unknown, he apparently unclipped his lanyard,
tightroped across the truss and fell 65 ft onto a crane barge.
The Occupational Safety and Health Administration proposed
$2,500 in fines. The inspection is still open and civil litigation
is pending.
Lunda also holds a $120-million
contract with Minnesota Dept. of Transportation to construct
two new segmental bridges over the Mississippi carrying I-494
traffic in St. Paul. Named "Wakota"an amalgam
of Washington and Dakota countiesthe $250-million job
is scheduled to finish in 2007.
 |
|
PAST AND FUTURE. Cape Girardeaus recently opened
Bill Emerson Bridge (above left) would be followed by
other major new Mississippi River bridges, including the
Wakota Bridge (above right) and a $1-billion new St. Louis
crossing (below). (Photos Courtesy of HNTB) |
Awaiting federal and state funding
is the biggest Mississippi crossing of all, designed to carry
I-70 traffic between St. Louis and Illinois. The 10-year project
would include the widest cable-stayed bridge in the world,
at 222 ft. When finished, the $1.6-billion M&M-designed
bridge would span 2,000 ft over the river, with a total three-span
length of 3,150 ft.
Illinois and Missouri have
been planning the new crossing since 1992. The project is
aimed at reducing I-55/64/70 congestion on the existing bridge.
"Im hoping that there is execution soon but it
is all contingent on the federal transportation bill,"
says Mary Lamie, Illinois DOT District 8 engineer.
|