|
...city light rail and commuter rail systems.
One section awaits the finish of
Terminal D, where a white tensile-steel roof shaped in peaks
and valleys is forming.
Conceptual terminal design reviews
began in 2000 with HNTB, Kansas City, as managing design architect
for 75 consultants. Locally based HKS Inc. is managing architect.
Each element has a different architect of record,
says Mark Skjervem, DFW Terminal D executive manager. Crews
broke ground that summer, with 2 million cu yd of excavation.
That went through first quarter 2001, with design packages
going out, piers put into the ground and buying steel,
he says. We were erecting steel in the summer of 01.
Then 9/11 happens. That threw us a curve ball.
 |
| PRIME
ELEMENTS New people mover system (top) awaits linkage
to new Terminal D (above). |
Consequently, the team discussed
new design parameters for the terminal shell and proximity
of the new parking garage. We were hoping it would be
minimal. It was extremely significant, Skjervem recalls.
Our structural design team and a blast consultant worked
hand-in-hand with the Federal Aviation Administration to mitigate
these issues.
Project officials then had to work
with the Transportation Security Administration. We
had new players to deal with, while keeping the construction
schedule on track, says Skjervem. The schedule was pushed
back from a January 2005 opening to April 2005 and $25 million
added in design changes. After hardening was required for
the terminal core, some 9,000 tons of extra steel was needed
to strengthen roof trusses.
The terminal is founded on drilled
piers in layers of clays and a flaky shale 20 ft deep. Every
truckload of excavation had to be tested for jet fuel and
other contaminants. C-shaped concession villages
bookend the terminal, and an enclosed elevated passage for
international travelers leads them to customs. After clearing
customs, three banks of elevators link to a new 300-room hotel.
Outside the terminal, a 300-ft
pedestrian bridge connects to an 81,000-space, 3-million-sq-ft
garage equipped with smart technology that directs
customers to available parking. Its a parking
space within five minutes concept, says Shaun
Pratt, DFW senior project manager for the $113-million garage.
Each floor has a terrazzo design with a specific flower or
color. A 300 x 180-ft canopied area will feature artistic
exhibits part of the $6-million art budget allotted
for the capital program. Other elements will include circular
floor murals indicating various check-in counters for customers.
(Photos courtesy of DFW)
|