|
The famously flat Dutch
countryside is proving to be a difficult platform for one of
Europes latest high-speed railroads, now spreading between
Amsterdam and the Belgian border. To build the 100-kilometer
link, tunneling technology is being stretched to new limits,
while soil-like "brown yogurt" combined with complicated
contractual boundaries and tragedy on a bridge test Dutch engineering
nerve.
Along an arc roughly south from
Amsterdam to Belgium, six teams are now forming the base for
a 300-km-per-hour train service, due to start operations in
2006. Their tools include a tunnel boring machine with the
worlds biggest cutting head, at 14.87 meters in diameter.
On the sidelines, another construction team is preparing to
install track and equipment to complete well over $3 billion
of project infrastructure.
 |
BIGGEST
Dutch TBM's 14.87-m cutting head is churning through peat,
clay and saturated sand.
(Photo courtesy of Bouygues) |
Managing the interface between
these two tasks has been "the biggest challenge,"
says David Gedney, chief exec-utive officer of track and equipment
contractor Infraspeed B.V, Zoetermeer. Disparate civil contractors
with their own headaches must pull out before Gedneys
workers can gain control of the route to complete the system
by 2007.
Tensions between the bulk civil
engineering work and the following fit-out stem from the contractual
separation of those intimately linked pieces of railroad,
suggests Bart-Jan Kouwenhoven, a senior manager with the states
project company, Projectorganisatie Hogensnelheidslijn-Zuid
(HSL-Zuid). "The way [contracts] are structured creates
different horizons
.We have the role of coordinating
all this work," he says.
Contractual novelty arises from
the governments unusual procurement approach. Facing
budget constraints, HSZ-Zuid adopted private financing for
track and equipment, explains project director Wim Knopperts.
Needing civil work done first, it fast-tracked those elements
by making contractors responsible for design, sewing seeds
for later difficulties. "Design-construct for this type
of work is not familiar here," says Gert Nederend, managing
construction of the lines biggest bridge.
The first design-build contract,
for the Green Heart tunnel, went to Paris-based Bouygues S.A.,
with local support, in late 1999 for $365 million. The remaining
five civil bids started above budget by 20%, said a source
at the time. But "very difficult negotiations" drove
prices down, adds Knopperts. The five civil jobs were finally
signed for about $1.6 billion altogether in mid-2000.
After rebidding track and fixed
equipment work, also to reduce costs, HSL-Zuid awarded that
contract to Infraspeed, in 2001. Owned by U.S.-based Fluor
Transportation, Dutch-based Royal BAM NBM N.V., Siemens Nederland
N.V. and two U.K. financiers, Infraspeed must finance, design
and construct the project in the five years and maintain it
for another 25 years.
Fluor, Infraspeeds smallest
shareholder, is managing construction. The three contractors,
in their own right, jointly have a fixed-price, "date
certain" turnkey contract with Infraspeed to deliver
the system, worth around $1 billion, says Gedney. The contractors
hold 51% of Infraspeed during construction to ensure the bankers
dont have "undue influence," he says. Later,
the contractors will reduce their stake to 25%.
 |
| BEHIND
THE CUTTER Track base is built as TBM advances
tp reduce tunnel buoyancy. (Photo courtesy of Bouygues) |
But first, civil engineering must
end. Crossing clay and peat ground for the northern two-thirds,
the track will run on a piled concrete slab instead of conventional
embankments and viaducts. About 170 structures straddle obstacles
along the whole route. But the major elements are concentrated
in the nations verdant Green Heart area, near Leiden,
and also around the wide Hollandsch Diep River, south of Dordrecht.
To preserve the pleasant, windmill-strewn
Green Heart, Bouygues, supported by locally based Koop Holding
Europe, is building a 9-km-long tunnel, driving the central
7.2 km between cut-and-cover ramps with a huge TBM. Of five
short list bidders, Bouygues alone offered a single bore instead
of twin tunnels proposed by HSL-Zuid, says project director
Joseph Harnois.
The firm wanted to eliminate building
mandatory escape cross tunnels between bores, a job requiring
tricky ground freezing, says Harnois. At $365 million, Bouygues
price undercut its rivals by a large margin, while keeping
the job profitable, he adds.
Key to Bouygues single bore
is the giant bentonite slurry TBM, weighing over 3,000 tonnes.
It must cut through some 12 m of peat and clay at either end
and plunge some 35 m down in saturated sand, with pore water
pressures up to 3.5 bar, says Frans Vahle, HSL-Zuids
tunnel manager.
Frances NFM Technologies,
at Le Creusot, supplied the TBM for $35 million, including
installation and startup, says machine design manager Gilbert
Fantanille. The TBM was the first slurry machine of the 24
NFM built in the last decade, says Fantanille. And it was
a big step. "The main bearing is the largest that can
be made in Europe. I dont know anywhere in the world
that can make a larger one," he says.
The TBMs 110-m-long backup
comprises girders spanning between front and rear gantries.
Space below allows the railroad track base to be built as
the TBM advances, reducing tunnel buoyancy in the groundwater.
As well as delivering lining segments, the backup carries
precast boxes forming the central equipment gallery under
the track floor. Workers ahead of the rear gantry backfill
around the gallery. They are followed by teams completing
reinforced concrete structures, including the tunnels
central dividing wall.
As it advances, the TBM erects
nine precast lining segments, plus one keystone per ring.
Made by a Bouygues affiliate in Belgium, the segments are
generally 60 centimeters thick, 2 m long and weigh 14 tonnes
each. Bouygues eliminated positioning bolts with a small plastic
roller on each segment effectively slipping into a slot in
its neighbor.
In a full days work, Bouygues
sets aside four hours for repairs. But at each of three permanent
access shafts along the route, the contractor stops for major
maintenance including replacing all picks, worn or not. "Maintenance
is not to repair, but to ensure there is no problem afterward"
explains Harnois.
 |
| HAMMERHEADS
Hoisting into place. (Photo courtesy of Bouygues) |
To receive the TBM, Bouygues fills
the lower 18 m of the 31-m-dia shafts with a weak sand/cement
mix over the base plug. Workers hand-dig an access slot through
the mix to expose the cutter head. The most recent stop, at
the central shaft, lasted from late this March to early May.
A final planned pit stop at the third shaft is set for October,
six months before TBM tunneling is due to end.
Having long since completed main
design, Bouygues and the owner only recently decided on fire
protection. Following several European tunnel disasters, HSL-Zuid
wants its lining protected to avoid collapse in the weak sand.
Bouygues commissioned trials both for spray-on retardant and
polypropylene fibers mixed in the segment, settling for the
former.
Harnois seems pleased with progress,
though the contract is understood to be about 10 months late
for reasons "beyond our control." Difficulties between
the owner and affected local authorities contributed. But
with the TBM generally advancing "better than forecast
even by us," Bouygues is clawing back lost time, says
Harnois. Peaking at 22 m in a day, the advance has averaged
16 m, he adds.
Further south, the railroads
biggest bridge, at 1.2 km long, must still wait for a fatal
accident investigation to end before the three final spans
close the Hollandsch Diep River crossing. A man fell to his
death in April when a major deck element slipped during installation
of a main span box (ENR 5/12 p. 15).
Designed to carry fast, heavy trains
on a 2% slope, the bridge has 12, mainly 105-m spans with
a continuous single trough deck topped with a 14-m-wide composite
concrete slab. The roughly 3-m-deep steel troughs rest on
V-shaped pier-top supports of similar dimensions.
The mainly Dutch, six-firm consortium
HSL-Drechtse Steden signed the $427 million design-build contract
in mid-2000, aiming to complete the bridge next May. Two 2.5-km
sunken tube tunnels under the Oude Maas and Dordtsche Kil
rivers, plus some 9 km of simple track also form part of the
contract.
HSL-Drechtse Steden has design
responsibility for the bridge "as long as we stick to
the program of requirements," says project manager Nederend.
The contractors local designers followed a concept by
Van Benthem Crouwel Architekten, Amsterdam, with Arup Group
Ltd., London, which won a design competition called by the
government in 1998. And it was the cheapest option, says Gaby
Schouten, HSL-Zuid's bridge project manager.
Except for concrete piers, all
major elements, including nearly 9,000 tonnes of steel, are
prefabricated nearby and delivered by river. Precast concrete
caissons, each sunk onto large steel piles, support cast-in-place
piers. The 25-m- long x 10-m-wide caissons travelled on pontoons
before being sunk into place.
Deck steelwork troughs were barged
to site in 60-m lengths, with concrete slabs already attached,
all weighing some 1,200 tonne. At each pier top "hammerheads"
form the deck support and end sections of each span. Hammerheads
are 45-m-long box fabrications made integrally with V-shaped
supports of similar proportions bearing on the piers.
Too tall to clear overhead obstructions
on the boat ride from the fabricators yard, hammerheads
travelled to the site on their sides, leaving tops slabs to
be cast later on the bridge. With hammerheads in position
at either end of a span, a subcontractor attaches hoists to
them to raise the intervening 60-m deck section. While hoisting
one of the last sections in April, a hammerhead moved fatally
for reasons still to be determined.
With bridge site work starting
in February 2001, the last hammerhead was due up late this
May, eight months after the first. But even before the accident,
the contract was running months late, partly because of local
authority planning demands and some design changes, says Schouten.
 |
| ON
HOLD Fatal probe slows progress. (Photo courtesy
of Directie-HSL-Zuid) |
All the problems added to pressure
that was already daunting. "I dont say we underestimated,
but its been quite a job," comments Nederend. Design
took some 35% more effort than planned, he estimates, and
substantially more equipment was needed for the bridges
erection.
For Infraspeed, the civil contractors
tribulations create more anxieties, accentuated by "horizontal
interfaces" between civil and equipment work, says Kimmo
Oostermeijer, who manages an HSL-Zuid team linking both set
of contracts. Given a second chance, all construction would
have been integrated in separate packages along the route,
adds HSL-Zuids Kouwenhoven.
One problem was the timing of contracts,
believes Harnois. "Infraspeed came into the project too
late," he says. Because of the time lag between civil
and equipment contracts, Infraspeed was initially left working
with outdated information, adds Gedney.
Civil contracts began being awarded
in early 1999 and designs by the consortia formed the basis
of Infraspeeds bid "as of January 2001," he
says. While Infraspeed prepared its bid, civil teams continued
refining their designs. "When we got on board...we had
to go back and take a look at designs as they were being executed
and we found some pretty basic changes," adds Gedney.
One resulting mismatch was between
bolt holes in ground slabs and Infraspeeds power line
supports, says Gedney. So instead of civil contractors casting-in
the bolts, Infraspeed must drill in embeds later. "Its
big because there are 80,000 embeds," he says. Another
clash emerged between fixings for Infraspeeds precast
track and the underlying slab rebar.
Seemingly unruffled by tensions
in the field, HSL-Zuid director Knopperts says the project
is within budget and schedule. HSL-Zuid added nine months
to the program two years ago, after hitting land acquisition
snags, he says. Trains are due to start in the south in October
2006, with the rest following the next April. Despite the
interface irritants, HSL-Zuids Kouwenhoven remains enthralled
by the project. "It makes me want to get up every morning
and go to work," he says.
|