 |
| SETTING
SAIL Immersed tubes will be installed this summer.
(Photo by Willam J. Angelo for ENR) |
With hopes of speeding
urban mass transit while revitalizing a critical minority business
corridor, officials at the Massachusetts Bay Transportation
Authority are well on their way to completing Boston's first
bus rapid transit service. The $1.6-billion, 20-year project
includes a major street widening, 13 new stations and two separate
mile-long tunnels utilizing a number of techniques including
the first use of soil freezing combined with the New Austrian
Tunneling Method to bore under a structure.
Phase One of the three-stage project,
a $50-million new busway down Washington Street from Dudley
Square to the New England Medical Center MBTA station, is
already completed. Phase Two, the $601-million tunnel complex
linking South Station to Logan International Airport, is scheduled
for completion early next year. The final phase, a $952-million
tunnel linking the Medical Center Station to South Station,
is scheduled for a 2010 completion. All work will be done
utilizing unit-price lump-sum bids.
One particularly difficult portion
of the project is a $110-million section involving a 325-ft-long
NATM tunnel under 100-year-old Russia Wharf. That binocular
tunnel lies west of a rectangular 180-ft-long cut-and- cover
transition tunnel linked to a rectangular 700-ft-long, three-piece,
concrete immersed tube tunnel across Fort Point Channel, that
is in turn tied to another 100-ft cut-and-cover piece. Cambridge,
Mass.-based Modern Continental Construction Co. Inc. is the
general contractor and is doing the NATM portion in joint
venture with Innsbruck, Austria-based Beton-und Monierbau.
Russia Wharf is a three-building
complex, all seven stories high, supported on 45-ft-long wooden
piles. Before mining on the overlapping 27-ft-dia tunnels
could start last September, the soil under the wharf had to
be frozen. About 180 pipes were placed up to 25 ft deep early
last year to carry a brine solution. "We had to go NATM/freezing
because it was the least invasive and most cost-effective
process," says Edward L. Karpinski Jr., MBTA deputy director.
"We looked at cut and cover, a soft ground shield and
boring machine, but costs and impacts didn't work for us."
"We think it's the first time
ground freezing and NATM have been combined under a structure,"
says Stephen A. DelGrosso, Modern Continental's senior project
manager. "The combination works great but we had to underpin
parts of the structure with a steel frame and 120-ft-deep
rock-socketed mini piles and two drilled monoshafts each 150
ft deep." Some of the piles are incorporated into the
center wall and the rest are outside the primary tunnel lining.
 |
COMBO
New Austrian Tunneling Method was used with ground freezing
for first time under a structure.
(Photo courtesy of Modern Continental) |
Shotcrete applied up to 12 in.
thick comprises the primary tunnel lining. A PVC lining incorporating
water barriers and grout injection hoses ensures tunnel dryness.
Another 12-in. shotcrete secondary lining then will be applied,
along with a 2-in. shotcrete finish layer. A cast-in-place
3-ft-thick concrete invert is now being poured.
"The biggest challenge was
digging between the piles and mitigating potential building
movement by maintaining the frozen ground," says DelGrosso.
"We used a roadheader attachment on an excavator for
the crown and excavation bucket on the bench." The underpinning
has some eight-ton structural steel sections that had to be
placed through windows using chain falls, come-alongs and
a trolley system, DelGrosso adds.
The contractors had to turn down
the temperature of the ground freezing operation to about
5°F because the soil contained more organics than expected,
which raised concerns about the strength of the frozen carrying
beam across the tunnel, says DelGrosso. Excavation on the
eastbound tunnel is completed and work on the westbound side
will start this summer. Other portions of the Phase Two tunnel,
all cut- and-cover sections, are either finished or are being
completed by J.F. White Contracting Co., Framingham, Mass.,
Perini/Kiewit/Cashman joint venture, Framingham; and a Medway,
Mass.-based Kiewit/Atkinson/Cashman joint venture. Three engineering
firms, DMJM+Harris, Stone & Webster, and STV, are also
involved.
The immersed tubes are being set
behind a replica of the Tea Party ship. Workers drove two
lines of 75-ft-long sheet piles across the tidal channel to
create a trench for the concrete immersed tubes, which are
being built in a nearby casting basin. While dredging the
55-ft-wide trench down about 40 ft through organics, clay
and till, they hit the top of a hard, glacial rock, which
required divers to drill cores and use a hydraulic splitter
to break up a 200-sq-ft section. "It is roughly 20,000
psi and an 8-ton chisel didn't work," says DelGrosso.
"And we couldn't dislodge it, so we had to use divers,
which has caused delays and a probable claim."
This summer, the tubes will be
floated into the channel under two bridges and over the sheeting.
"Each tube will be set in a lay barge, ballasted and
lowered with winches," says DelGrosso. The tubes will
sit on hydraulic pin-jack foundations. Once set to grade,
sand will be pumped under the tubes.
While Phase Two is winding down,
preliminary engineering already has started on Phase Three
by the locally based joint venture of URS/DMJM+Harris. "We're
looking at a number of alternatives to try and lock in federal
funding because we need at least 50% participation,"
says Peter F. McNulty, joint venture project manager. "Technically
speaking, the big issues are location of shafts and portals
and the complexities of twin driven 24-ft-dia tunnels crossing
underneath portions of the Central Artery/Tunnel and several
transit stations."
 |
CONNECTED
Immersed tubes will link up with dug tunnels at Fort Point
Channel.
(Photo by Willam J. Angelo for ENR) |
The work is all through clay and
sand and mostly about 60 ft deep, he says. Construction is
scheduled to start by 2006.
"Ridership is already up 50%
along the Washington corridor," says David W. Ryan, MBTA
assistant general manager. Because of opposition to a catenary
system, the surface system uses busses powered by compressed
natural gas. But the CNG's can't go in tunnels, so dual diesel/electric
powered busses will be used there, says Ryan. But by 2010
only one type of vehicle will be used systemwideeither
dual mode, all electric, or an evolved CNG.
Ryan says the project is having
a major economic impact, with at least $500 million of new
private development under way along the Washington Street
corridor. When completed, the Silver Line will tie into three
other mass transit lines plus South Station, which handles
Amtrak, commuter rail and a nearby bus terminal. "That's
its real appeal," says Ryan.
|