|
Like a gigantic boulder
that has been tumbling down a steep slope for a decade, the
largest engineering and construction project on the planet
is gaining momentum as it heads into its final phase. Chinas
massive, multipurpose Three Gorges Dam project is proceeding
so smoothly that even long-term opponents concede that the
dams progress will not be derailed. The owner apparently
has resolved problems from earlier stages, including a fatal
tower crane collapse and concrete cracks (ENR 06/07 p. 15).
Current criticism focuses on social issues, such as relocation
and environmental water quality.
"Weve pretty much accepted
that it wont be stopped now. Theyre just too far
along," says Patrick McCully, campaigns director with
the International Rivers Network in Berkeley, Calif. While
acknowledging that the owners technical competence will
get the structure built, McCully says "it may be decades"
before the world knows whether the dam can control flooding
and avoid siltation, the bane of other large global hydro
projects.
 |
| OLD
HAND Former project engineer Lu, still active as
a consultant, charts progress. |
Lu Youmei, former general manager
of China Three Gorges Project Development Corp. (CTGPC), says
the critics are wrong to focus on individual aspects of the
megaproject. Three Gorges is complex, unique and should be
viewed in a comprehensive manner, he says. Lu, a civil engineer,
is confident that the dams positive aspects outweigh
the minuses.
CTGPC fired up the ninth of 14
700-MW generators in the left bank powerhouse in July. Flipping
on the switch for the massive turbine instantly pushed more
hydropower onto the grid of a power-starved nation. The remaining
five units are scheduled for phase-in by the end of 2005.
More power from right bank units will follow.
 |
| GATES
OF TRADE Locks boost Yangtze traffic. |
Three Gorges power is a keystone
of Chinas goal of adding 7.8% more annual generating
capacity from 2004-2010, says Li Yong-an, CTGPC president.
This will enable the roaring dragon to stay ahead of its 6.8%
annual forecast demand increase, he adds. At the same time,
the pollution issue has become as omnipresent as the perpetual
smog enshrouding the Yangtze Valley. "China is No. 1
in the world in carbon dioxide emissions and No. 2 in sulfur
dioxide. We are giving sustainable hydropower development
our top priority," Li says.
Also at the dam site last month,
the five-level ship locks also officially opened after a years
worth of operational testing. Barges queue along the 6.4-kilometer-long
left bank channel dual-lane chamber, waiting to be lifted
or lowered 113 meters to circumvent the dam. Designers promised
a speedy 2.5-hour pass-through, but in May and June it often
took four to six hours for a diverse, crowded fleet of 10,000-ton
vessels to make the transit.
With the ship lock, spillway
and left bank powerhouse in operation, the busiest place on
the jobsite these days is on the right bank. The Chinese finished
the cofferdam on that side of the river last year, shut the
diversion channel and sent the Yangtze back into its mainstream.
The reservoir pool rose as planned to 139 m at the dam face
this spring. At that level, each generator cranks out 580
MW of power, says CGTPC engineer Hu Daisong. When operators
dropped the level to 135 m before the summer rains came, the
yield slipped to 550 MW.
 |
| LAST
THIRD With cofferdam creating a dry work pit on
the Yangtzes right bank, tower cranes place concrete
for the final segment. |
Jobsite Beehive
The loss in electricity production is offset by a measure
of flood control during the wet season and added safety for
a small army of workers. For the past decade, construction
has proceeded from the left bank to the center spillway. On
that side, work remains on a single-stage, 3,000-ton passenger
ship lift and the commissioning of the five remaining generator/turbine
sets. But the epicenter now is a dry pit on the right bank.
Downstream from the coffer dam, there are some 11,400 workers
on three shifts daily. They are running a vast batch plant
and conveying roller-compacted concrete to the remaining dam
section. Nearby, crews are excavating rock for the powerhouse
and intake tunnel and building footings for generating machinery.
The three major contractors are
all headquartered 40 miles downriver in Yichang, but many
members of the work force live in dormitories at Sandouping,
the site of the dam. The largest outfit, Gezhouba Construction,
boasts a work force of 6,200. Many of them worked on the Gezhouba
Dam, which was completed in the 1980s. Regarded as the Three
Gorges A team, they primarily are responsible for running
an onsite batch plant and placing concrete in the powerhouse
foundation and along the remaining 584.2-m-long dam segment.
Qing Yun Hydrology Consortium backstops
Gezhouba on the dam face with 3,500 workers. Another 1,700
with a quasi-public company called the 378 Power & Hydraulics
Consortium supports powerhouse work. The government formed...
|