|
Tampa Bay Water is
reaching several significant milestones on a multiyear, multimillion-dollar
program to develop, store, treat and transport new sources
of potable water. A 66-million-gal-per-day surface water plant
started production last month. After breaking ground in August,
contractors are marshaling a large heavy equipment fleet to
construct a 1,100-acre regional reservoir that will begin
storing 15 billion gallons of water when complete in August
2004. A 25-mgd seawater desalination plant is near completion
and is to begin production in November despite two bankruptcies
on the design-build-operate team. To tie these components
together and integrate them into the agency's existing system,
contractors are placing some 70 miles of large-diameter transmission
pipelines.
 |
|
ACCESS
Pipe work employs different placement methods, including
a 40-ft-dia shaft for a tunnel boring machine. (Photo
courtesy of Kenko Inc.)
|
Several interties and pump stations,
a wellfield and a 9-mgd groundwater treatment plant round
out 11 capital contracts currently under way. Totaling $609
million for design, construction and program management, the
work comprises the first and largest phase of Tampa Bay Water's
master plan, an ambitious three-stage effort to reduce the
water wholesaler's groundwater extraction under permit from
192 mgd at the program's inception in 1998 to 90 mgd in 2008.
"We had to do something. We had
over-permitted the system. We were extracting more groundwater
than we could replenish," says Jerry Maxwell, the agency's
executive director. Tampa Bay Water, which evolved from a
regional agency established in 1974, is a wholesale water
purveyor for Hillsborough, Pasco and Pinellas counties and
the cities of Tampa, St. Petersburg and New Port Richey. The
rate base includes about 2.1 million commercial and residential
customers.
 |
|
WATER
CZAR Outsourcer Maxwell.
|
Maxwell calls the vectors that
influence Gulf Coastal Florida's water policy "the four D's:
drought, drainage, development and drawdown." The agency's
power over the first three is minimal. "But we can attack
the drawdown. We knew we could cut down on groundwater extraction,
develop new sources of water further south, store it until
we need it and be able to blend several sources to deliver
a product that exceeds Safe Drinking Water Act standards,"
he says.
A steady rise in population is
one factor making water politics as contentious in lush, subtropical
Florida as in the arid West. Still, the agency's plans attracted
scant public notice until a six-year drought pushed the issue
onto front pages and television newscasts. "We normally average
52 to 54 inches of rain a year, but from 1988 to '94, we got
numbers in the 30s and 40s," says Maxwell. Suddenly a host
of interested parties took a keen interest in Tampa Bay Water's
evolving game plan: developers, agricultural interests, the
Florida Dept. of Environmental Protection, the South Florida
Water Management District, the general public and even a 750-lb
rogue alligator.
Maxwell credits the agency's board
of directors for looking at the big picture. It consists of
nine elected officials: two from each county and one from
each city. "Pinellas County is built out--it has a density
higher than Miami-Dade. It would be easy for them to balk
at spending money to build a reservoir in Hillsborough or
lay miles of pipe a long way from their user base," says Maxwell.
Pasco and Hillsborough counties have large, rural tracts dedicated
to citrus groves and cattle grazing. "In l996 and 1997 there
was a huge policy shift. We suddenly had a board that could
see beyond their own boundaries. They 'got it' when we started
looking at a regional, watershed-based concept," he says.
Click
here to view map
Tampa Bay Water looked to the consulting
engineering community to help formulate a master plan. "We
are a lean agency. We had 108 employees at the time," says
Maxwell, and 119 now. "We realized we needed outside expertise,
and a lot of it, to get to where we wanted to go." Outsourcing
also keeps down carrying costs for employee benefits, he adds.
Funding the state retirement system costs 16 to 18%, versus
a 6% match private companies carry on employee 401(k)s, he
says.
The agency hired Kansas City-based
Black & Veatch Corp. as program consultant. "We addressed
the basic question: 'How can we make the system work hydraulically
and maintain a higher water quality standard than the product
we're replacing?'" says Helen O. Bennett, the vice president
who heads B&V's Tampa Bay Water project work. "On top
of that, we had to consider the schedule. That's a major driver."
The owner brought on Jacobs Civil Inc., Pasadena, for program
management support, with emphasis on scheduling.
A negotiated agreement with the
Southwest Florida Water Management District tied funding to
groundwater drawdown reductions. SWFWMD offered $183 million
in state funds, contingent on the agency cutting groundwater
extraction by 18%, to 158 mgd by 2004, and by 2008, to 90
mgd. For the reservoir and eight miles of large-diameter connector
lines, the federal government has already committed $36 million
toward the $134-million cost. The owner hopes to secure another
$21 million before completion.
The agency is supporting the remainder
of the funding, through bonds and rate hikes. When the master
plan was put in place, the wholesale rate was 98¢ per 1,000
gallons, Maxwell says. It is now $1.75 and will be about $2
by 2004, when the first phase is completed. "Our rates are
competitive with other purveyors in the Southeast," he says.
On the the same day Black &
Veatch was hired in November 1998, Tampa Bay Water signed
consultants to oversee all 11 projects. Design engineers,
contractors and subcontractors soon followed. From the beginning,
"We made the objectives very clear. This is an integrated,
complex program. We have to reduce the groundwater 'take'
and deliver 65 mgd of new water within the next four to six
years," says Kenneth J. Herd, the agency's engineering and
projects manager.
The scope of the job forced engineers
to rethink strategy. "We had worked on systems consulting,
but we decided to go after design work on individual projects,"
says Douglas W. Fredericks, Camp Dresser & McKee Inc.'s
Tampa-based vice president. The bet paid off, as CDM won design
work on the entire surface supply system, including two pump
stations, connecting pipelines, an intertie and the water
treatment plant itself.
The first challenge CDM faced was
convincing US Filter Corp. to join forces to land the $96-million
surface water treatment plant contract. "We knew their ballasted
flocculation process was tailor-made for this job, but they
had grown so big so fast that it took us a while to find the
right people within their company to convince them that they
had a winner," says Fredericks. Palm Desert, Calif.-based
US Filter won the DBO contract, with a CDM plant design.
CDM coveted U.S. Filter's Actiflo
process because it utilizes a much smaller footprint than
a traditional plant. Ballasted flocculation is a two-step
procedure that integrates ozone disinfection instead of more
a conventional multi-stage system that requires large tanks
for coagulation, flocculation, filtration, settling and disinfection.
Actiflo uses two parallel process trains, where raw water
is loaded with chemical coagulant. Microsand particles and
polymer are added to the floc in the same tank. As fluid passes
through eight filtration channels into a clearwell, sludge
is removed for disposal. Sand is recirculated and clean water
is disinfected.
"It's a great technique for treating
high volumes of raw water in a small space, in a hurry," says
Fredericks. "The loading ratio, compared to a conventional
scheme, is 20:1." Plant design saves space through common
wall construction, instead of a conventional campus-style
layout. To add cost-effective capacity before the reservoir
comes on line in mid-2004, Tampa Bay Water decided to increase
plant yield by 10%, to 66 mgd. The $5.7-million change order
is the project's largest to date. Overall, change orders have
accounted for $13.1 million, or about 3% of $426 million worth
of construction.
The owner favored a 15-year design-build-operate
arrangement, with a five-year extension rider. "We like DBO.
It shifts more money into the capital plant, but saves money
in the long run by holding down operating costs. If you're
driving the same car for 20 years, you want a Mercedes instead
of a Hyundai," says Maxwell.
THE BIG
POND. A 900-acre above-ground
reservoir will supply the new surface water plant. An engineered
embankment and access roads stretch its footprint to 1,100
acres. The earthen berm will average 55 ft in height, impounding
up to 15 billion gallons of water. Omaha-based HDR Inc.'s
design uses a bentonite soil cutoff wall varying in depth
from 25 to 70 ft, with a geomembrane liner placed inside the
berm from the top of the cutoff wall to the base of the crest
road.
The owner spent more than two years
on geotechnical work, says C. Edwin Copeland Jr., HDR vice
president. Jeff Higgins, vice president and operations manager
for prime contractor Barnard Construction Inc., says the extensive
upfront information helped his firm put together a winning
$86-million bid.
Bozeman, Mont.-based Barnard also
tapped the local talent pool, hiring McDonald Construction
Co., a Lakeland-based earthmoving contractor with phosphate
mining experience. McDonald is providing much of the heavy
equipment, 130 pieces in all, that will be needed to move
some 12 million cu yd of earth. "In three or four weeks we'll
start building the cutoff wall and then remove about 1 million
cu yd of waste clay and replace it with competent soil," says
Derek Tisdel, Barnard project manager. The workhorses will
be Caterpillar 631 scrapers, which can push 18 to 20 cu yd
of material, and "a lot of D-8s and D-9s and 740-ton trucks--nothing
like the size you'll see in surface mining, but pretty big
equipment," he adds.
 |
|
VARIETY
Contractors can choose iron, steel or concrete pipe.
(Photo courtesy of Tampa Bay Water)
|
The contractor has allowed for
some lost time to rain, but "usually we can knock off when
the rain comes and then be back at it by mid-morning the next
day, " Tisdel says. Embankment construction will move in tandem
headings, starting at the center of the northern section and
moving east and south and west and south. Wetland mitigation
will proceed concurrently and pipeline work will start in
about four months. Once the embankment work is well along,
crews will construct an interior compacted soil cement liner,
timing work to finish within a month or two of the containment
wall.
Some 42,000 ft of 84-in.-dia steel
pipe will connect the reservoir to its intertie. "Pipe used
to be the most expensive way to provide water," says Copeland.
"With development and environmental concerns shifting priorities,
now it's one of the cheapest."
Some 70 miles of new transmission
mains are tying together the new production, storage and treatment
components. The project has been a boon to pipe vendors, who
have supplied 33 miles of ductile iron, 36 miles of welded
steel, 1 mile of prestressed concrete cylinder and a half-mile
of fiberglass reinforced pipe, in diameters between 30 and
84 in. To increase competition, the owner specified ductile
iron, steel or concrete, but let each contractor choose its
preference. Tampa Bay Water buys the materials because it
is exempt from Florida's sales tax. "We also carry all the
insurance, because we can get a comprehensive rate cheaper
than the contractors," says Maxwell. "Those measures save
about $8 million."
Contractors are using five methods
of pipe placement: pipe ramming, microtunneling, jack-and-bore,
liner plate with hand-tool drilling and directional drilling.
One of the most complicated segments, the Alafia River crossing,
involves 900 ft of 96-in.-dia steel casing. To cross the river,
Minneapolis-based Kenko Inc. constructed two secant pile shafts
on either side of the river. An earth pressure balance tunnel
boring machine cuts through soft limestone varying in compressive
strength from 400 to 12,000 psi.
NO SALT.
The 25-mgd desalination plant is also on time for a November
start-up, despite initial opposition by environmentalists
and bankruptcies on the DBO team. In many ways, the $108-million
plant is the master plan's cornerstone (ENR 10/16/2000 p.
46). Touted as the largest capacity reverse osmosis desalination
drinking water unit in the western hemisphere, the plant takes
raw water from the cooling water intake at an adjacent Tampa
Bay Electric Co. 1,800-Mw powerplant. The facility draws 15
Mw and produces water for about $2.02 per 1,000 gal. "It only
makes sense to site this plant next to its power source,"
says Maxwell. "Reverse osmosis is power-intensive. The process
is more efficient using warmer water from the plant's cooling
water intake stream. Discharging the brine back into the plant's
cooling water discharge stream, at a 1:70 ratio, minimizes
the salinity load." Tides induce more of a change in salinity
levels than the brine discharge, Maxwell says.
A carefully constructed 30-year
DBO contract protected the agency against damage from bankruptcies
on the team, first at Stone & Webster Corp. and then at
Covanta Energy Corp. (ENR 4/15 p. 29). Maxwell credits project
procurement manager R.W. Beck Inc., Seattle, with providing
expert guidance.
"For us to negotiate on our own
without good advice would be like going to bat against a major
league pitcher and expecting not to strike out--next to impossible,"
he says. When Covanta went into Chapter 11, Tampa Bay Water
exercised a buy-out option to isolate the project from bankruptcy
proceedings. As a result, the job remains on course.
 |
|
LATER,
GATOR Crew removes rogue alligator from pipeline
trench. (Photo courtesy of Kenko Inc.)
|
Other challenges are more mundane,
but no less tangible. One morning, a pipeline worker encountered
a 12-ft, 10-in. bull alligator. Workers wrapped the gator's
jaws and eyes with tape, hoisted him out of the ditch in an
improvised sling and had the state Fish and Wildlife Dept.
remove the animal.
Tampa Bay Water now is turning
toward configurations 2 and 3, which call for an additional
49 mgd of water by 2009. "Right now, we're trying to fine-tune
our demand forecasting," says Herd. Plans call for additional
wellfields and transmission mains, a 5-mgd brackish water
reverse osmosis unit and another 25-mgd desalination plant.
The trick is to balance demand growth, political support and
available funding, Herd says.
|