|
Washingtons
Tacoma Public School District has become a reluctant pioneer
in the slow-but-steady paradigm shift toward computer-aided
design and construction, thanks to a convincing argument from
the design team to help meet an aggressive construction schedule
for a 279,000-sq-ft high school. By allowing the structural
engineer to preorder and detail Mt. Tahoma High Schools
1,900 tons of primary steel, taking on risk typically the
contractors, TPSD set in motion a chain of events that
has sliced at least three months off construction.
The strategy has paid off. The
$77.7-million school is on course and budget for substantial
completion June 11. "Its working out just as well
as we hoped," says Peter J. Wall, TPSDs director
of planning and construction.
But if integrated steel design
(ISD) goes awry, it opens up a pandoras claims box.
"If you own the shop drawings" and a piece of steel
comes out wrong, "it can affect the whole schedule,"
says Brandy Matthews-Fox, president of CPM Inc., Seattle,
the owners representative.
That is why only extenuating circumstances
would prompt TPSD to go down the risky path of ISD again.
It did so with Mt. Tahoma because the school is the linchpin
of its $450-million capital program. To keep the program on
course, the Mt. Tahoma building must be done by August. Then
the old Mt. Tahoma building can be vacated and begin its short
life as a "swing school" to receive student bodies
from the other high schools scheduled for improvements. "It
was in the districts best interest to give the Mt. Tahoma
project every advantage to be completed in a timely manner,"
says Wall.
The engineer pushing ISD, Lanny
Flynn, vice president of design-build in the Tacoma, Wash.,
office of project engineer Putnam Collins Scott Associates
(PCSA), doesnt agree that it increases the owners
exposure. "I feel what we did lowers the owners
risk," especially on a public project, says Flynn.
ISD relies on three-dimensional,
object-based modeling of the structural steel and reduces
the risk of a nonperforming, low-bid detailer, says Flynn.
It also results in better-coordinated drawings, fewer fabrication
errors and allows foundation work to begin immediately after
the contract award, he says.
 |
| BOLD
DETAILS Schedule success relied on engineer using
3-D modeling and removing the mill order and steel detailing
from the critical path. |
Steel was preordered on Oct. 22,
2002, fabrication began on Feb. 3, 2003, and erection started
March 1. Steel was topped out in June. Prompt startup relied
on the districts much earlier decision to complete sitework
before bidding the general contract. If the site is not ready,
ISD is no help, says Matthews-Fox.
There have been only 13 requests
for information associated with the structural steel, says
Flynn. Four hundred is more typical for a project of this
size and complexity. Of 2,908 anchor bolts on the project,
which also includes a 3,200-seat stadium, only four for one
base plate required modification. There were no mismatched
connections, even though they contained 15,256 bolts. In the
school building, there were no problems with 3,045 assemblies,
reports the team.
 |
Everyone cautions against using
ISD frivolously. "There is no reason to go with ISD if
you have a normal project," says Jim Burk, senior project
manager for the general contractor, Lease Crutcher Lewis,
Seattle. He says the approach, which went "tremendously
smoothly" in this case, has the potential to fail. One
reason is that the detailers drawings go directly out
on the fabricators shop floor without being reviewed
by the general contractor or steel erector. "If you dont
have quality players," says Burk, ISD can "fall
on its face."
 |
| STRUCTURE
ELEVATED Approach is called challenging because
the structural engineer pushes the design process. |
Mt. Tahoma now is 80% finished.
Completing it on time hinged on removing the mill order procurement
and structural steel detailing from the critical path. A week
after the Jan. 8, 2003, award, crews were placing footings.
Steel erection began only nine weeks after contract award.
Wall credits much of the success
to LCL. "I dont know if another contractor would
have been able to respond that quickly" to steel arriving
so early, he says. The approach accelerates other elements
and procurement, forcing everyone to work harder, he adds.
Calling Mt. Tahoma "a very
positive experience," Tom Bates, managing principal of
BLRB Architects, Tacoma, says it nevertheless "was challenging"
because the structural engineer was pushing the design process.
The arrival of 3-D detailing packages
and the ability to link them with design software and computer
numerically controlled fabrication equipment provided Flynn
with the opportunity to do more than dream of ISDsomething
he had been doing long before he arrived at PCSA three years
ago. Besides the high school, PCSA has used ISD on a hospital
expansion, a high-rise office tower, a medical office building
and a jail.
But Flynn cautions that structural
engineers should have experience in steel construction and
fabrication before they take on ISD. When an engineer leads
the detailing, "it is critical" to develop a drawing
presentation standard that most fabricators can fabricate
off, he says.
"It had a positive spin on
the process," says John Farmer, general manager for the
steel fabricator, Allied Steel Inc., Lewistown, Mont. There
were only 24 misfits of more than 20,000 pieces.
Quality advantages alone do not
drive an owner to go with ISD, says Flynn. The approach remains
a hard sell for any reason other than schedule advantage.
(Rendering top courtesy of BLRB Architects.
All other photos and rendering courtesy of Putnum Collins
Scott Associates)
Click below to view more articles
related to this story >>
Museum,
District Collaborate To Build An Unusual Hybrid
New
Jersey Officials Focus on Bringing In New Blood
Demographics
Drive Market: Kids Keep School Work Going Strong
|