|
...with horizontal and inclined tubes.
These tubes reach back to 4.5-tonne-steel anchorages embedded
in shear walls at the buildings back corners.
While the spine column takes perimeter
vertical loads, the exoskeleton around it provides wind resistance
and dampens the buildings vibrations, according to Calatrava.
To build the tower, HSB set up
its own construction management team with most of its 13 staff
on loan from NCC. That arrangement is separate from NCCs
$30- million superstructure job, which does not include the
$9-million exoskeleton.
NCCs site work, starting
in April 2002, reached the concrete roof last month. Mostly
thanks to wind, the main structure is about three months late,
says Nordgren. Apart from wind, the main challenge was the
towers height, especially pumping the concrete more
than 180 m up, he says.
NCC pumped from the ground at a
rate of one floor every eight to nine days, says Nordgren.
It cast the solid concrete floors in some 20 pours each. For
the core and its internal walls, NCC used self-climbing formwork.
Core formwork rose in a single assembly, five floors deep.
While in one position, the assembly allowed construction of
the core on one level and on internal walls over three floors
below, plus follow-up work, adds Nordgren.
With formwork being dismantled,
NCC will build the top three levels of core interior walls
out of precast concrete. This should finish up in mid-January,
says Nordgren. But that assumes the wind cooperates. Considering
work was halted again late last month due to wind, the end
date is not firm.
NCCs delays have bothered
the exoskeleton erector, Denmarks Promecom A.B. Fredericia.
The eight-person team has been hampered a few times, returning
to Denmark for four weeks on each occasion, says project manager
Karsten Rasmussen.
Promecom joined the project late,
in November 2003, after HSB had a falling out with its original
erector. Spanish contractor Elaborados Metálicos S.A
(EMESA), Coruña, was meant both to fabricate and erect
the 900 tonnes of exoskeleton. But the contract "has
been a disaster," says Ingvar Nohlin, HSBs project
director. His big complaint is about "quality problems
with the welding."
EMESA retained fabrication work
and completed steel delivery this summer. But a dispute over
payments with HSB is under arbitration, says Nohlin.
EMESA officials were not available
for comment. But Calatrava says the contractor is "a
very correct firm and very advanced." It has worked on
previous Calatrava jobs and is involved in the current erection
of the railroad station for Liège, in Belgium.
Early Momentum
For Promecon to gain early momentum on its hurriedly awarded
$2.3-million erection contract, "everything in the first
six weeks went very fast," says Rasmussen. Promecom used
three mobile cranes to lift steel at low levels. A winch arrangement
raised remaining steel from inside the rising concrete frame.
If wind allows, the last piece
of exoskeleton will be placed by the end of December, a couple
of months late, says Rasmussen. However, shell and core is
off the critical path, says Nohlin. With time to gain during
the fit-out, he still plans for a July opening.
The tower will be the landmark
structure for the small Swedish city that has grown in stature
since the Øresund fixed link with the Danish capital
opened four years ago. Nohlin concedes that an ordinary building
may have been more economical for HSB, which is a housing
cooperative. But he says that if HSB had wanted a conventional
design, it would not have asked Calatrava to do it.
|