|
On a continuous adrenaline
rush, a hyperdedicated team working in the wings of Ground
Zero has been bounding toward a goal once considered unachievable-completion
of the $50-million renewal of the Winter Garden at the World
Financial Center by the anniversary of the Sept. 11 terrorist
attacks. The effort to repolish the architectural gem of lower
Manhattan, a cavernous steel-and-glass skylight smashed close
to smithereens by the collapse of the 110-story One World
Trade Center, owes it success in large part to a brilliantly
conceived exterior hoist-and-trolley system. The contraption
not only sped the roof steel rehabilitation, it compressed
the reglazing of nearly 60,000 sq ft of glass from the two
years the job originally took into just 4.5 months.
Over the year, the cacophony of
reconstruction noise at the grand atrium building has served
as a welcome counterpoint to the somber strains issuing from
the 16-acre crater across the street". This project provided
a certain optimism everybody was so hungry for," says Craig
Copeland, an associate in the New York City office of the
Winter Garden's original and current architect, Cesar Pelli
& Associates. "It inspired everything," he adds.
 |
| OVER
THE TOP Trolley system let glaziers do their work
in just 4.5 months. (Photo courtesy of Turner Construction/NAT
Valentine) |
The magnitude of the task only
served to supercharge the workers. "We got 250% from these
people," says James White, project superintendent for the
WFC recovery team of Turner Construction Co., New York City,
and the acknowledged mastermind behind not just the trolley
system but the overall strategy for getting to the finish
line by Sept. 5.
The rebuilt Winter Garden stands
as a 110-ft-tall symbol of hope amidst the shattered lives
and dreams of the area. And with its new glass entryway facing
Ground Zero, it also is a giant welcome-back mat for the citizens
of New York City and beyond. Beyond that, it has boosted the
spirits of those grappling with the sticky issues of rebuilding,
a process rife with emotions, politics, economics and countless
agendas.
It is "a fantastic symbol for the
planning effort," says Margaret Helfand, a principal of Helfand
Myerberg Guggenheimer Architects, New York City, and outgoing
chair of New York New Visions, a coalition of more than 80
firms and groups representing architects, planners, graphic
designers and engineers that has labored without compensation
to advise city and state officials on the area's renewal.
Among its many accomplishments, NYNV designed, pro bono, the
Ground Zero viewing fence, a portion of which is set to open
Sept. 11.
Helfand predicts that with its
new "front door" on West Street, which replaces stone cladding,
the Winter Garden will become "the major public space downtown,"
and "much more important than it ever was before."
CRITICAL LINK. The $65-million
Winter Garden, between West Street and the Hudson River, opened
in 1987 as the centerpiece of the 8.5-million-sq-ft WFC (ENR
3/7/85 p. 28). One of the few "quality-of-life" indoor spaces
in Manhattan, it is a critical indoor pedestrian link to mass-transit
connections, both subways and ferries, to New Jersey. "It
is the reason Cesar Pelli won the commission for the WFC in
the first place," says Sabrina Kanner, a vice president of
WFC owner Brookfield Financial Properties, and project manager
for the rebuild.
The structure's four-story, U-in-plan
base skirts the 192-ft-wide vaulted skylight, framed by architecturally
expressed steel truss arches 15 ft apart. A 110-ft-tall glass
window wall offers views of the Hudson River and New Jersey
to the west.
Trusses are pin-connected into
composite concrete and steel ladder columns along the sides
of the garden. In the long direction, trusses radiate from
an apse at the east end of the roof, across from Ground Zero.
Loads go to drilled-in caissons.
Upon initial inspection of the
damage, locally based Thornton-Tomasetti Engineers (T-T),
the garden's original structural consultant, thought the building
was unsalvageable. Many arches were damaged or partially down,
as was the east facade and a large portion of the east floor
framing. Most seriously, the system for lateral stability,
a 350-ft-long, 50 to 60-ft-wide horseshoe-shaped horizontal
diaphragm truss within the fourth floor, was heavily damaged
at its most critical area, the 50-ft-long turning point at
the curve of the horseshoe.
 |
| NEW
FRONT DOOR Dream team's (l. to r.) Zborovsky, Kanner,
White, architect Rafael Pelli and Copeland in front of
new wall. (Photo by Michael Goodman for ENR) |
Even more worrisome, says the engineer,
the inner edge of the truss was still attached to its edge
girder. But the breached girder had lost structural stability.
If lateral forces were to push the horseshoe apart, the whole
structure would have collapsed, says Leonid B. Zborovsky,
a T-T principal involved in the original project and the repair.
If that had happened, there would
have been damage to the 51-story Three WFC, to which the garden
was attached for lateral stability through its horseshoe truss.
"Miraculously," says Zborovsky,
a three-story pile of debris from One WTC, the downed pedestrian
bridge that gave access to the garden from the WTC and the
damaged Three WFC was propping the Winter Garden's broken
horseshoe truss.
But the fire department, searching
for survivors, was eager to remove the debris. Fortunately,
T-T also was representing New York City's Dept. of Design
and Construction as structural consultant at Ground Zero and
was able to convince officials to leave the debris until workers
could shore and brace the structure.
 |
| VIEW
IN Part of Ground Zero viewing fence is set to
be done by Sept. 11. (Rendering courtesy of New York New
Visions) |
From mid-September to December's
end, crews from local construction firm AMEC and scaffolding
contractor Atlantic-Heydt Corp., Brooklyn, N.Y., installed
compression struts between the ends of the garden's roof arches
and bracing at critical locations. Workers had to cut 5-ft-square
shafts four stories deep through the thicket of debris to
install shoring towers under damaged roof arches. The trick,
says Zborovsky, was staging the work to prevent further compromise
to the structure. During the operation, other than some broken
glass falling, there were no secondary collapses.
Beyond T-T's structural assessment
survey and shoring and debris removal, the city would not
allow any work on the garden until January, when it turned
the building back to the owner. "We couldn't get people to
the site because the pieces of the corner of Three WFC, including
One WTC steel, were dangling precariously over the Winter
Garden," says White.
White, at Ground Zero since Sept.
13, didn't waste the waiting time. Hired for the garden's
fine demolition and restoration, Turner used the "delay" to
collect original drawings, procure replacement glass, order
steel and lock up time for fabrication of replacement steel,
stone and the curtain wall.
The earliest preliminary schedule
for the Winter Garden redo called for completion by late October
or November 2002. But Brookfield wanted the work done by the
anniversary of Sept. 11, so White promised to finish by Sept.
5. With 350 activities, the schedule has not changed since
Oct. 1, other than the east facade redesign, he says.
Turner's approach was to work in
as many areas as possible at the same time and to get double
duty from as many systems as possible. The "dance floor,"
a work platform built 67 ft above the Winter Garden's first
floor, is an example. The platform provided a safety net for
roof workers, protected workers below from falling objects
and weather and gave workers roof access from the interior.
Another example are the arch shoring towers. They helped support
the dance floor, along with the horseshoe truss.
 |
| UNDONE,
REDONE Winter Garden damage was so severe that
engineers thought it not salvageable and in danger of
total collapse, threatening 51-story adjacent tower. (Photo
by Michael Goodman for ENR) |
Last but not least, the trolley
system deserves the most bows in the reconstruction. The inspiration
for the system is that "it took two years to glaze the roof
the first time and we needed to do it in four and a half months."
says White.
Crews from Atlantic-Heydt installed
the 375 x 225-ft structure up and over the Winter Garden roof
last January. Beams spanning the roof to shoring towers on
either side were located slightly offset from roof arches,
which align with skylight mullions.
Beam flanges became the rail for
the trolley rigs but the beams also supported damaged roof
arches during their restoration. In an operation that lasted
from February through April, ironworkers from the New York
City office of Canron Construction Co. hung an arch off a
beam while they cut out damaged segments, hoisted them away
using a 450-ton crawler crane and welded in replacement sections.
In areas of zero arch damage, and
then later after arches were repaired, workers hooked up trolley
motors for placement of the skylight system.
Glass installation started in April
on the west end of the garden and was completed by the end
of July. Turner had four trolley rigs on the job, each measuring
12 ft deep, 25 ft wide and 10 ft in height. Thanks to a four-point
suspension system, the rigs could follow the contour of the
roof. Each rig contained a platform that dropped out and a
small derrick equipped with suction cups to maneuver each
400-lb light of glass. "We would load the car in the morning
and it would never come down until the day's end," says White.
When it was time to move a rig
down the roofline to install another bay of skylight, workers
would drop the rig onto the ground, roll it to the next bay,
and hook it up to the next set of trolley beams.
 |
| MISSING
BACKDROP View of WFC from the Hudson River is minus
the 110-story twin tower, One WTC. (Photo by Michael Goodman
for ENR) |
In the early months, the logistics
of getting equipment, workers and materials to and from the
site hampered progress. "The roadways were blocked," says
White, and the WTC work took precedence.
Turner worked closely with the
Port Authority of New York & New Jersey, which owns the
WTC site, and the city's Dept. of Design and Construction,
"to gain some space," says White. Using carpenters and laborers,
Turner even helped the city build command posts. Turner eventually
found ways to get vehicles down West Street and over to the
riverside promenade alongside the Winter Garden.
For the redo, Turner called upon
firms involved in the original project, even the quarry in
Italy for the stone flooring. Subs were hand-picked and though
most contracts were not competitively bid, "we were not gouged,"
says Brookfield's Kanner. "People were glad to have something
like this to work on [and] were generous with time and good
will. It was a crazy, creative group."
By virtue of the Sept. 11 anniversary
reopening, the Winter Garden has moved from the wings to center
stage in the public's eye. "The Winter Garden represents all
[that] we wish to embody in the development across the street,"
says architect Helfand, referring to Ground Zero proper. And
with its new front door, she adds, "it is a demonstration
that we can put things back and make them better."
|