 |
| (Photo
coutesy of Steel Dynamics Inc.) |
The most severe cost
crisis in living memory has hit fabricators and contractors
that work with anything made of steel. And nobody saw it coming.
Structurals, plate, rebar, mesh, studs, ductwork, guardrails,
fencesif it was a product made with steel and
you had a fixed-price contract to deliver it during the first
quarter, you were in trouble. And the contractual ripples
are expected to be felt for many months to come.
Reinforcing bar prices made the
first move last spring while structural steel prices began
moving up in the fourth quarter of 2003. But the unprecedented,
across-the-board price increases that followed during the
first quarter of this year stunned the industry. "If
this trend continues, it has the potential of putting the
majority of fabricators in the U.S. out of businessand
I mean the majority," says Robert Abramson, president
of Interstate Iron Works Corp., Whitehouse, N.J. Several other
fabricators agree that this is not an extreme statement.
At the beginning of 2004, steel
mills started indexing their base price directly to the price
of scrap, which had increased 41% in 2003 after jumping 47%
in 2002, as China drove demand for global scrap.
Scrap is the basic raw material
of minimills, which produce most construction materials. These
mills responded with surcharges that raised prices dollar
for dollar to match increases in scrap prices. The nations
largest minimill, Nucor-Yamato Co., Blytheville, Ark., tacked
a $20-per-ton surcharge onto its wide-flange products in January,
says Joe Stratman, plant general manager. This rose to $49
in February and $93 in March.
This action followed four increases
in Nucors base price for most wide-flange products in
the second half of last year, ranging between $10 to $15 per
ton each. Nucor just announced another $25-a-ton increase
in its base price in February, which brings the average price
of a ton of steel to around $420, says Stratman. The $162
in surcharges would boost that price another 39%, and fabricators
are bracing for more surcharges in April.
For many in the industry, the surcharges
came as a total surprise. One week before Christmas, Frank
Williams, partner in The Williams Group, Merrifield, Va.,
met with two suppliers regarding delivery of steel for a large
project over a three-to-six month period. "They said
they could not hold prices past April 1, which I felt we could
deal with," says Williams. "Then two weeks later,
I get a dear valued customer letter with these
huge surcharges." Using surcharges as cover, "we
have seen suppliers run in mass from existing quotes in contracts
and just not honor them," he says.
Bridge fabricators may be in a
better position to weather the storm because they tend to
be more financially sound after five years of robust markets,
says Williams. But commercial building fabricators, still
struggling to emerge from recession, are vulnerable to the
current situation. "I think you are going to see a tremendous
number of very large and very old fabricators shut their doors
in the next six months," he predicts.
Rebar fabricators are in the same
boat. For the past 30 years, reinforcing steel prices have
been very steady, keeping in a plus or minus 10% bandwidth,
says William Brack, CEO of Milford, Mass.-based fabricator
Barker Steel Co. So he figured last springs $35-per-ton
price increase was the firms hit for the year. "What
happened after that, nobody was prepared for," he says.
What followed was another $50-perton
increase in the fourth quarter of last year. "At that
point, people thought that was a record and we had a crisis
on our hands," says Brack. But the real crisis was still
coming with another price hike between January and the end
of April that will total $170 per ton, if announced increases
are included, he adds.
To make matters worse, there are
increasing concerns in the market about availability and delivery
times. Because supply problems are playing a crucial role
in price escalation, mills cannot ramp up production to take
advantage of higher prices, as they normally would if demand
was the primary concern.
"Business is being driven
now by the ability to maintain the availability of supply,"
says Brack. Ironically, he thinks that this may be fabricators
best hope in escaping the current crisis, since owners tend
to fear the cost of project delay more than higher materials
prices. "We are talking to our customers, and to keep
their jobs running, we need some cooperation in terms of price
relief," he says.
Perhaps the most damaging aspect
of the current steel market crisis is the uncertainty it has
sown. Mills are not tipping their hand on what prices will
be. "Price quotes for structurals are good for 30 days,
at best, and pipe quotes are only good for a few weeks,"
says John Murphy, chief procurement officer for Black &
Veatch, Overland Park, Kan. "No one knows how high prices
are going or how long this situation will continue."
Wire mesh is among the most unpredictable
material, says Brack, whose firm also runs a materials warehousing
operation. Mesh suppliers are only quoting prices at time
of delivery but will not guarantee when that delivery will
be, he says. Try putting that into a bid estimate.
"It is impossible to put together
an estimate in todays environment," says Joseph
Majewski, president of JPM Construction Consultants Inc.,
Spring Lake, N.J. "How do you tell a client that this
is the best guess because I dont know what is going
to happen 10 days from now?"
Majewski is trying to cope with
three announced price hikes totaling 50% for metal studs over
the next 45 days, with no guarantee that the actual price
increases will not be even higher. "You include a contingency
and hope youve got it covered," but in the end
a contingency is just a guess, he says.
This higher risk factor is changing
the way contractors now do business. "Historically in
our industry, weve built escalation into our jobs,"
says Eric Benson, president of San Diego-based Pacific Coast
Steel Inc. "Now, were quoting projects with open
escalation tied to the rising price of steel and some owners
are getting sticker shock." Benson says that general
contractors "are coming back to an industry that has
historically absorbed the price escalation and saying, What
are we supposed to plug in for our escalation?"
Firms may be "forced to deal with what they may consider
non-responsive bids," he adds.
This uncertainty is creating a
thriving environment for inflation. "The risk is that
in trying to guess what is going to happen in the next six
months, firms start factoring in more escalation than actually
happens," says Neil Platt, Pittsburgh-based purchasing
manager for Turner Corp.
"In the fourth quarter, we
lost a lot of really large jobs to really low-priced competition
and we were forced to survive on smaller jobs," says
Jim Mangarella, estimator for JM Ahle Co., a South River,
N.J.-based rebar fabricator. That turned out to be a blessing
in disguise, with small jobs shorter cycle offering
some protection against unexpected price hikes. "Now
our larger competition is overbidding prices like crazy,"
he says. Escalation clauses may help elevate the problem of
overbidding, says Williams. "Otherwise, people are going
to put in high bids up front to cover the risk factor,"
he says.
|
Pricing Time Lag
The onslaught of higher steel prices that began hammering
contractors at the start of the first quarter slammed
into ENRs published prices during February and
March. By the end of the quarter, ENRs 20-city
average price had increased 15.5% for channel beams,
19.4% for wide-flange beams, 18.4% for grade-60 reinforcing
bar and 20.2% for steel plate. These quarterly gains
make up the bulk of the year-to-year price increase.
Some readers of ENR have
expressed concern that the steel component for the February
cost indexes was up only 3.8% for the year. However,
the published February cost index is computed using
the published January steel price, which in turn was
collected in mid-December. Readers can find the most
up-to- date prices on the construction economics page
in the fourth issue of each month.
|
The current steel price and supply
situation is putting "an enormous cash strain on all
contractors honoring fixed-price contracts," says Bing
Drastrup, president of Santee, Calif.-based J.L. Davidson.
As a result, "the industrys ability to offer fixed
prices at this point is virtually gone," Drastrup says.
"If you have a project thats long range
we
are unable to put a firm price or to guess what the price
may be."
Exacerbating the problem, credit
also is tightening drastically. Only six months ago, 45 to
50-day payment terms "were quite acceptable," says
Drastrup. Now, "its net-30-or-nothing. And, if
youre over your credit line, its cash with shipment,"
he says. Further straining cash-strapped fabricators, a credit
line now buys only 60% of what it did six months ago. Between
supply shortages, shrinking credit, and a cash drought, "youre
getting it from all sides," Drastrup says.
Higher prices are complicating
other basic business issues. "The product we are now
carrying has doubled in cost and that means the financial
resources you need to carry that product are also increasing,"
says Brack. "We cant bankroll a contractor and
a contractor cant bankroll an owner."
Firms are now pushing for stability.
"Were going back and asking clients to make price
adjustments that will hold us harmless for price increases
going forward, so we can stop the bleeding at some point and
try to recover," Drastrup points out.
More seasoned and flexible contractors
seem to understand that replacing a fabricator is likely to
drive up costs further, Drastrup says. A new vendor will likely
seek full market prices rather than the cost adjustments requested
by the fabricator already on board. "On existing contracts,
there is not enough money in the pipeline," says Williams.
"It is going to be very difficult to get reimbursed on
some of these unprecedented cost increases."
|