Photo by Scott Judy
The general contractor and the Dept. of Veterans Affairs remain at odds over when the roughly $300 million Orlando hospital project can be completed.

Perplexed by continuing problems at a $300-million veterans hospital project in Orlando, Rep. Jeff Miller (R-Fla.) told officials with the Dept. of Veterans Affairs and contractor Brasfield & Gorrie, "I want answers," as he convened a U.S. House field hearing across the street from the troubled job site on Aug. 13.

Instead, the three-hour hearing of the House Committee on Veterans’ Affairs produced even more questions about the project and who would finish it. Throughout the hearing, VA officials largely refused to comment about a pending possible termination of the general contractor on the project, Brasfield & Gorrie. Meanwhile, the contractor’s CEO spent much of his testimony pointing fingers at the VA over continuing delays caused by design changes.

Both sides told the Florida politicians who took part in the hearing—including Sen. Bill Nelson (D-Fla.) as guest—that they were continuing to work together to get the project back on track; but the most notable unanswered question remained whether that would—or could—happen.

In a statement, Miller summarized: “It is clear from today’s hearing both VA and the contractor still have quite a long way to go to come together and figure out how to work together, which is what needs to happen.”

At the outset, VA’s Glenn D. Haggstrom, principal executive director of the Office of Acquisitions, Logistics and Construction, told the congressional committee that he could not discuss a key issue surrounding the project.

“We are unable to answer questions” about the pending possible termination of Brasfield & Gorrie, Haggstrom said. Haggstrom cited a desire not to interfere with the decision of the VA’s contracting officer, identified as Noella A. Bond by the contractor. Bond’s deadline for reviewing Brasfield & Gorrie’s response to the VA’s notice to cure—the term for an initial notice of intent to terminate—ended Aug. 9, but Haggstrom said the contracting officer’s decision was still pending.

Following up, Miller said he found it “perplexing” that the VA had issued a cure notice to the contractor in June, just shortly after making public statements that it was working in concert with the company to solve problems. Haggstrom responded by stating the decision wasn’t his, but instead was the sole discretion of Bond, who declined the committee’s invitation to testify. Pressured by Miller, Haggstrom admitted however, that he had been in contact with Bond about the decision.

Haggstrom testified that termination could delay the project by as much as eight months, but also said he didn’t know what the contracting officer's decision would be. That left open the possibility that further negative action against the contractor could again follow VA comments of cooperation.

Furthering the theme of ongoing cooperation, Brasfield & Gorrie CEO Jim Gorrie early in his testimony revealed that the two parties had come to a tentative agreement over expediting the project just one business day prior to the hearing, and pointed to a document as he did so.

Miller quickly asked to have the agreement entered into the testimony, but Gorrie deferred to Haggstrom, who asked that it not be allowed while the contracting officer was still reviewing it. And Miller adhered to Haggstrom's request.